13120 W NIMROD PL 90049

Certificate Information: 13120 W NIMROD PL 90049

Application / Permit
15010-30000-03786
Plan Check / Job No.
B15WL05458
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD with attached garage and basement.
Permit Issued
Issued on 8/10/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2015 APPLICANT
Assigned to Plan Check Engineer 11/19/2015 VLADIMIR ARUTYUNYAN
Corrections Issued 11/25/2015 VLADIMIR ARUTYUNYAN
Quality Review Completed 12/3/2015 DOUGLAS NAKATANI
Building Plans Picked Up 12/4/2015 APPLICANT
Green Plans Picked Up 5/31/2016 APPLICANT
Plan Check Approved 7/11/2016 VLADIMIR ARUTYUNYAN
Issued 8/10/2016 LADBS
CofO in Progress 8/9/2021 JOHN KIDWELL
Permit Finaled 10/18/2021 DANIEL ORRANTE
CofO Issued 10/18/2021 DANIEL ORRANTE
Permit Finaled 10/18/2021 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 5/4/2016 ROBERT DUFF
Low Impact Development Cleared 7/5/2016 MARTIN FRAGOSO
Green Code Cleared 7/7/2016 RICHARD GARCIA
Eng Process Fee Ord 176,300 Cleared 7/11/2016 RAVIL MANAPOV
Permit Cleared 7/11/2016 RAVIL MANAPOV
Roof/Waste drainage to street Cleared 7/11/2016 RAVIL MANAPOV
Sewer availability Cleared 7/11/2016 RAVIL MANAPOV
ZI Cleared 7/11/2016 ERIC CLAROS

Contact Information

Contractor Owner-Builder       ,
Engineer Namdar, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/14/2017 Not Ready for Inspection DAVID KOSKI
Footing/Foundation/Slab 5/1/2017 Partial Inspection DAVID KOSKI
Footing/Foundation/Slab 5/11/2017 Corrections Issued DAVID KOSKI
Footing/Foundation/Slab 5/16/2017 Conditional Approval DAVID KOSKI
Footing/Foundation/Slab 6/2/2017 Not Ready for Inspection VINCENT SCIPIONI
Footing/Foundation/Slab 6/6/2017 Partial Approval KENNETH NAGLE
PLUMBING-Rough 6/30/2017 Corrections Issued VINCENT SCIPIONI
Underground Mechanical 7/5/2017 Not Ready for Inspection VINCENT SCIPIONI
PLUMBING-Rough 7/6/2017 Partial Approval VINCENT SCIPIONI
Masonry Wall/Backfill 7/7/2017 Corrections Issued VINCENT SCIPIONI
Masonry Wall/Backfill 7/11/2017 Partial Approval VINCENT SCIPIONI
Footing/Foundation/Slab 7/26/2017 Partial Approval VINCENT SCIPIONI
Footing/Foundation/Slab 7/31/2017 Corrections Issued VINCENT SCIPIONI
Footing/Foundation/Slab 8/3/2017 Partial Approval KENNETH NAGLE
Reinforced Concrete Frame 8/10/2017 Not Ready for Inspection VINCENT SCIPIONI
Reinforced Concrete Frame 8/14/2017 Partial Approval VINCENT SCIPIONI
Deputy Steel/Welding 8/16/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Drilled-In Anchors 8/23/2017 Conditional Approval VINCENT SCIPIONI
Footing/Foundation/Slab 8/23/2017 Partial Approval VINCENT SCIPIONI
Reinforced Concrete Frame 8/28/2017 Partial Approval VINCENT SCIPIONI
Deputy Steel/Welding 8/29/2017 Conditional Approval VINCENT SCIPIONI
Excavation/Setback/Form/Re-Bar 8/31/2017 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 9/6/2017 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 9/8/2017 Partial Approval VINCENT SCIPIONI
Deputy Steel/Welding 9/20/2017 Partial Approval JOHN LUMB
Floor/Roof Diaphrgm/Shear Wall 9/22/2017 Partial Approval VINCENT SCIPIONI
PLUMBING-Rough 9/25/2017 Partial Inspection VINCENT SCIPIONI
Deputy Steel/Welding 10/5/2017 No Access for Inspection VINCENT SCIPIONI
Deputy Steel/Welding 10/6/2017 No Access for Inspection VINCENT SCIPIONI
Footing/Foundation/Slab 11/3/2017 Partial Approval VINCENT SCIPIONI
Excavation/Setback/Form/Re-Bar 11/9/2017 Corrections Issued RICHARD STEINBACH
Reinforced Concrete Frame 11/9/2017 Conditional Approval RICHARD STEINBACH
Reinforced Concrete Frame 11/14/2017 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 11/28/2017 Approved RICHARD STEINBACH
Deputy Reinf. Concrete 12/5/2017 Conditional Approval VINCENT SCIPIONI
Floor/Roof Diaphrgm/Shear Wall 12/12/2017 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 12/27/2017 Partial Approval RICHARD STEINBACH
Deputy Wood Construction 1/19/2018 Conditional Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 1/26/2018 Not Ready for Inspection VINCENT SCIPIONI
PLUMBING-Rough 3/13/2018 Not Ready for Inspection VINCENT SCIPIONI
PLUMBING-Rough 3/15/2018 Partial Approval VINCENT SCIPIONI
Floor/Roof Diaphrgm/Shear Wall 4/6/2018 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 4/11/2018 Partial Approval VINCENT SCIPIONI
Green Building Rough 4/11/2018 Not Ready for Inspection VINCENT SCIPIONI
Verify Sprinkler Sign Off 4/11/2018 Not Ready for Inspection VINCENT SCIPIONI
Reinforced Concrete Frame 4/16/2018 Not Ready for Inspection VINCENT SCIPIONI
ELECTRICAL-Rough 4/26/2018 Partial Inspection VINCENT SCIPIONI
Interior/Exterior Lathing 5/23/2018 Partial Approval VINCENT SCIPIONI
PLUMBING-Rough 5/23/2018 Approved VINCENT SCIPIONI
Interior/Exterior Lathing 6/20/2018 Partial Approval VINCENT SCIPIONI
Interior/Exterior Lathing 8/9/2018 Partial Approval VINCENT SCIPIONI
Interior/Exterior Lathing 8/17/2018 Corrections Issued MICHAEL PELHAM
Interior/Exterior Lathing 8/30/2018 Partial Approval VINCENT SCIPIONI
Insulation 10/2/2018 Corrections Issued DANIEL ORRANTE
Insulation 10/10/2018 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 10/30/2018 Corrections Issued MICHAEL PELHAM
Green Building Rough 10/30/2018 Not Ready for Inspection MICHAEL PELHAM
Verify Sprinkler Sign Off 10/30/2018 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 11/1/2018 Corrections Issued MICHAEL PELHAM
BUILDING-Rough-Frame 11/20/2018 Approved RICHARD STEINBACH
Drywall Nailing 11/20/2018 Approved RICHARD STEINBACH
Green Building Rough 11/20/2018 Approved RICHARD STEINBACH
Interior/Exterior Lathing 5/8/2019 Approved TIM CHRISTENSEN
PLUMBING-Rough 11/8/2019 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 11/22/2019 Partial Approval DANNY TOLENTINO
Special/Order Compliance 1/9/2020 Corrections Issued DANNY TOLENTINO
PLUMBING-Final 7/6/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 7/23/2020 Corrections Issued ROBERT SHELLY
PLUMBING-Final 7/30/2020 Not Ready for Inspection ROBERT SHELLY
ELECTRICAL-Final 8/20/2020 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 8/20/2020 Not Ready for Inspection JOHN KIDWELL
Final 5/18/2021 Corrections Issued JOHN KIDWELL
Green Building Final 5/18/2021 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Approved JOHN KIDWELL
Service/Power Release 5/18/2021 Not Ready for Inspection JOHN KIDWELL
Smoke Detectors 5/18/2021 Approved JOHN KIDWELL
Final 7/16/2021 Not Ready for Inspection JOHN KIDWELL
Green Building Final 7/16/2021 Not Ready for Inspection JOHN KIDWELL
Service/Power Release 7/16/2021 Not Ready for Inspection JOHN KIDWELL
Final 8/6/2021 OK to Issue CofO JOHN KIDWELL
Green Building Final 8/6/2021 Approved JOHN KIDWELL
Service/Power Release 8/6/2021 Approved JOHN KIDWELL