2401 W BRIARCREST ROAD 90210
Certificate Information: 2401 W BRIARCREST ROAD 90210
- Application / Permit
- 15010-30000-03254
- Plan Check / Job No.
- B15WL04728
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- construction of a new 2-story single family residence with attached carport
- Permit Issued
- Issued on 3/8/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2015 | APPLICANT |
| Green Plans Picked Up | 10/9/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2015 | TARIK SAOUD |
| Corrections Issued | 10/29/2015 | TARIK SAOUD |
| Quality Review Completed | 11/6/2015 | DOUGLAS NAKATANI |
| Building Plans Picked Up | 11/9/2015 | APPLICANT |
| Applicant returned to address corrections | 3/17/2016 | TARIK SAOUD |
| Plan Check Approved | 2/5/2018 | TARIK SAOUD |
| Issued | 3/8/2018 | LADBS |
| CofO in Progress | 4/20/2022 | RAUL BARAJAS |
| Permit Finaled | 5/6/2022 | DEROLD HAUFF |
| CofO Issued | 5/6/2022 | DEROLD HAUFF |
| Permit Finaled | 5/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2016 | HOWARD COOPER |
| BHO/Hillside ordinance | Cleared | 3/1/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 3/1/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 3/1/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 3/1/2016 | LEE GUILBEAUX |
| Permit | Cleared | 3/1/2016 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2016 | ADRIAN SANCHEZ |
| Hydrant and Access approval | Cleared | 3/8/2016 | ROBERT DUFF |
| Grading in hillside | Cleared | 3/10/2016 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 3/10/2016 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 3/10/2016 | SARAH HOUNSELL |
| Specific Plan | Cleared | 3/10/2016 | SARAH HOUNSELL |
| ZI | Cleared | 3/10/2016 | SARAH HOUNSELL |
| Sewer availability | Cleared | 3/18/2016 | ARNULFO NUNO |
| Low Impact Development | Cleared | 3/25/2016 | MARTIN FRAGOSO |
| Green Code | Cleared | 4/7/2016 | RICHARD GARCIA |
| Private street | Cleared | 10/6/2017 | DWAYNE WYATT |
| ZI | Cleared | 10/6/2017 | DWAYNE WYATT |
| Roof/Waste drainage to street | Cleared | 10/16/2017 | MAHELET GEBEYHU |
| Grading Pre-Inspection | Cleared | 2/5/2018 | TARIK SAOUD |
Contact Information
| Architect | Pali, Zoltan Emery; Lic. No.: C19741 | 8609 WASHINGTON BLVD CULVER CITY, CA 90232 |
| Contractor | Owner-Builder | , |
| Engineer | Fekete, Karoly; Lic. No.: C50134 | 1108 CHEROKEE TOPANGA, CA 90290 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
| Geologist | Cugno, Giuseppe; Lic. No.: EG1804 | J. BYER GROUP, THE 1461 E CHEVY CHASE DR, #200 GLENDALE, CA 91206 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/9/2018 | Conditional Approval | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 10/11/2018 | Not Ready for Inspection | RONALD COWAN |
| Footing/Foundation/Slab | 10/16/2018 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 10/18/2018 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 2/7/2019 | Partial Inspection | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/9/2019 | Partial Approval | DANNY TOLENTINO |
| Piling/Pier/Caisson | 4/24/2019 | Partial Approval | DANNY TOLENTINO |
| Reinforced Concrete Frame | 5/13/2019 | Partial Approval | DANNY TOLENTINO |
| Reinforced Concrete Frame | 5/20/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 6/12/2019 | Partial Approval | DANNY TOLENTINO |
| Reinforced Concrete Frame | 7/1/2019 | Partial Approval | DANNY TOLENTINO |
| ELECTRICAL-Rough | 8/6/2019 | Partial Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 8/6/2019 | Partial Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 8/14/2019 | Partial Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/13/2019 | Conditional Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 9/13/2019 | Partial Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/17/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/18/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/19/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/20/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/23/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/25/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/26/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Steel/Welding | 9/27/2019 | Partial Approval | RICHARD STEINBACH |
| Structural Steel Frame | 9/27/2019 | Partial Approval | RICHARD STEINBACH |
| Special/Order Compliance | 4/29/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2020 | Conditional Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 6/29/2021 | Partial Approval | RICHARD STEINBACH |
| Light Gage Steel Frame | 6/29/2021 | Partial Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 7/26/2021 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 8/31/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 11/18/2021 | Approved | RAUL BARAJAS |
| Gas Test | 12/9/2021 | Approved | RAUL BARAJAS |
| Gas Test | 12/10/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 12/16/2021 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 2/11/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 2/15/2022 | Approved | RAUL BARAJAS |
| Final | 2/15/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Final | 2/15/2022 | Approved | RAUL BARAJAS |
| Green Building Rough | 2/15/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 2/15/2022 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 2/15/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 2/15/2022 | Approved | RAUL BARAJAS |
| Structural Steel Frame | 2/15/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 2/15/2022 | Approved | RAUL BARAJAS |
| Final | 2/25/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 2/25/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Structural Steel Frame | 2/25/2022 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 3/3/2022 | Approved | RAUL BARAJAS |
| Final | 3/14/2022 | Corrections Issued | RAUL BARAJAS |
| Service/Power Release | 3/14/2022 | Not Required | RAUL BARAJAS |
| Structural Steel Frame | 3/14/2022 | Approved | RAUL BARAJAS |
| Final | 3/22/2022 | Corrections Issued | SCOTT FINNILA |
| HVAC-Final | 3/22/2022 | Approved | SCOTT FINNILA |
| Final | 4/6/2022 | Conditional Approval | RAUL BARAJAS |
| Final | 4/20/2022 | OK to Issue CofO | RAUL BARAJAS |