14960 W SUTTON ST 91403

Certificate Information: 14960 W SUTTON ST 91403

Application / Permit
15010-30000-03204
Plan Check / Job No.
B15WL04647
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New two story single family dwelling with attached garage
Permit Issued
Issued on 1/19/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2015 APPLICANT
Green Plans Picked Up 10/8/2015 APPLICANT
Assigned to Plan Check Engineer 10/22/2015 CHRISTINE MAALOUF
Corrections Issued 10/28/2015 CHRISTINE MAALOUF
Quality Review Completed 11/3/2015 DOUGLAS NAKATANI
Building Plans Picked Up 11/4/2015 APPLICANT
Applicant returned to address corrections 11/12/2015 CHRISTINE MAALOUF
Applicant returned to address corrections 1/5/2016 CHRISTINE MAALOUF
Plan Check Approved 1/7/2016 CHRISTINE MAALOUF
Issued 1/19/2016 LADBS
CofO in Progress 12/16/2021 JACK KARGODORIAN
Permit Finaled 3/8/2022 MICHAEL SMITH
CofO Issued 3/8/2022 MICHAEL SMITH
Permit Finaled 3/8/2022 MICHAEL SMITH

Permit Application Clearance Information

CPC Cleared 11/5/2015 NORMA GUZMAN
Miscellaneous Cleared 11/5/2015 NORMA GUZMAN
Eng Process Fee Ord 176,300 Cleared 11/18/2015 DAVID ARCHER
Hydrant and Access approval Cleared 11/18/2015 ANDREW KO
Permit Cleared 11/18/2015 DAVID ARCHER
Sewer availability Cleared 11/18/2015 DAVID ARCHER
Green Code Cleared 12/15/2015 RICHARD GARCIA
Low Impact Development Cleared 1/6/2016 AMMAR ELTAWIL
GPI Written Notices Cleared 1/7/2016 CHRISTINE MAALOUF
Grading Pre-Inspection Cleared 1/7/2016 CHRISTINE MAALOUF
Roof/Waste drainage to street Cleared 1/7/2016 HISASHI KOBAYAKAWA

Contact Information

Contractor Owner-Builder       ,
Engineer Kiggins, Shawn Douglas; Lic. No.: C67845 2020 REDESDALE AVE      LOS ANGELES, CA 90039
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/22/2017 Partial Approval MICHAEL YOUNG
Footing/Foundation/Slab 7/19/2017 Corrections Issued MICHAEL YOUNG
Footing/Foundation/Slab 8/30/2017 Not Ready for Inspection MICHAEL YOUNG
Excavation/Setback/Form/Re-Bar 8/31/2017 Corrections Issued MICHAEL YOUNG
Footing/Foundation/Slab 9/7/2017 Not Ready for Inspection MICHAEL YOUNG
Footing/Foundation/Slab 9/12/2017 No Access for Inspection MICHAEL YOUNG
Footing/Foundation/Slab 9/18/2017 Not Ready for Inspection MICHAEL YOUNG
Footing/Foundation/Slab 9/25/2017 Partial Approval MICHAEL YOUNG
Footing/Foundation/Slab 10/4/2017 Approved MICHAEL YOUNG
BUILDING-Rough-Frame 12/15/2017 Partial Approval MICHAEL YOUNG
Green Building Rough 12/15/2017 Partial Approval MICHAEL YOUNG
Verify Sprinkler Sign Off 12/15/2017 Not Ready for Inspection MICHAEL YOUNG
BUILDING-Rough-Frame 10/23/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/23/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 10/23/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 10/23/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/2/2018 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 6/12/2019 Not Ready for Inspection CHRISTOPHE COCHRAN
Sewer 1/22/2020 Conditional Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/9/2020 Partial Approval CHRISTOPHE COCHRAN
Green Building Rough 3/9/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 3/9/2020 Not Ready for Inspection CHRISTOPHE COCHRAN
Deputy Wood Construction 3/11/2020 Conditional Approval CHRISTOPHE COCHRAN
Insulation 9/8/2020 Partial Approval CHARLES POWELL
Shower Pan 9/8/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 9/18/2020 Approved CHARLES POWELL
HVAC-Rough 9/29/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 9/29/2020 Approved CHARLES POWELL
PLUMBING-Rough 9/29/2020 Approved CHARLES POWELL
Wood Frame 9/29/2020 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 10/8/2020 Conditional Approval MISAEL ESPARZA
Green Building Rough 10/8/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 10/8/2020 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 10/8/2020 Approved MISAEL ESPARZA
Insulation 10/16/2020 Partial Approval CHARLES POWELL
Drywall Nailing 10/26/2020 Approved CHARLES POWELL
Gas Test 3/5/2021 Approved CHARLES POWELL
PLUMBING-Final 10/1/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 10/7/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 10/14/2021 Approved JACK KARGODORIAN
PLUMBING-Final 10/14/2021 Approved JACK KARGODORIAN
HVAC-Final 10/26/2021 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 11/16/2021 Approved JACK KARGODORIAN
Final 11/16/2021 Corrections Issued JACK KARGODORIAN
Green Building Final 11/16/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV Approved JACK KARGODORIAN
Service/Power Release 11/16/2021 Not Ready for Inspection JACK KARGODORIAN
Smoke Detectors 11/16/2021 Approved JACK KARGODORIAN
Final 11/30/2021 Corrections Issued JACK KARGODORIAN
Service/Power Release 11/30/2021 Not Ready for Inspection JACK KARGODORIAN
Pre-Inspection 12/3/2021 Partial Approval MATT KELLERMAN
Final 12/16/2021 OK to Issue CofO JACK KARGODORIAN
Service/Power Release 12/16/2021 Approved JACK KARGODORIAN