3620 W ELLSWORTH ST 90026

Certificate Information: 3620 W ELLSWORTH ST 90026

Application / Permit
15010-30000-02788
Plan Check / Job No.
B15WL04057
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
new 3 story s.f.d.
Permit Issued
Issued on 2/2/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/4/2015 APPLICANT
Assigned to Plan Check Engineer 8/20/2015 SHANGQIN XIE
Corrections Issued 8/27/2015 SHANGQIN XIE
Green Plans Picked Up 8/27/2015 APPLICANT
Quality Review Completed 8/28/2015 DOUGLAS NAKATANI
Building Plans Picked Up 9/2/2015 APPLICANT
Applicant returned to address corrections 10/20/2015 SHANGQIN XIE
Applicant returned to address corrections 11/6/2015 SHANGQIN XIE
Applicant returned to address corrections 11/13/2015 SHANGQIN XIE
Plan Check Approved 11/24/2015 SHANGQIN XIE
Issued 2/2/2017 LADBS
Refund Completed-Status Void 4/12/2017 YAN YAN
Re-Activate Permit 6/12/2017 YAN YAN
CofO in Progress 10/30/2025 FREDDIE RIVERA
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/30/2015 AVALYN KAMACHI
Eng Process Fee Ord 176,300 Cleared 9/30/2015 AVALYN KAMACHI
Highway dedication Cleared 9/30/2015 AVALYN KAMACHI
Permit Cleared 9/30/2015 AVALYN KAMACHI
Sewer availability Cleared 9/30/2015 AVALYN KAMACHI
Hydrant and Access approval Cleared 10/13/2015 ROBERT DUFF
Low Impact Development Cleared 10/13/2015 VIJAY DESAI
Roof/Waste drainage to street Cleared 10/13/2015 NATALIE MOORE
Green Code Cleared 11/10/2015 RICHARD GARCIA

Contact Information

Contractor Create R E Inc; Lic. No.: 999515-B 909 NORTH SEPULVEDA #385      EL SEGUNDO, CA 90245

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 7/28/2017 Approved ROBERT MCDOWELL
Final 11/21/2018 Corrections Issued ELMER BLAND
Footing/Foundation/Slab 6/10/2019 Corrections Issued PIERRE VEGA
Footing/Foundation/Slab 6/19/2019 OK to Expire Permit PIERRE VEGA
Footing/Foundation/Slab 6/20/2019 Corrections Issued PIERRE VEGA
Underground Mechanical 6/20/2019 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 7/24/2019 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 8/16/2019 Corrections Issued ROBERT VORHIS
Footing/Foundation/Slab 8/22/2019 Partial Approval ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 12/13/2019 Partial Inspection ROBERT VORHIS
Deputy Steel/Welding 1/21/2020 Approved ROBERT VORHIS
Deputy Steel/Welding 1/22/2020 Conditional Approval ROBERT VORHIS
Footing/Foundation/Slab 1/30/2020 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Partial Approval ROBERT VORHIS
Wood Frame 4/17/2020 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 5/8/2020 Not Ready for Inspection MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Not Ready for Inspection ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Partial Inspection ROBERT VORHIS
Wood Frame 6/23/2020 Partial Approval ROBERT VORHIS
PLUMBING-Rough 10/19/2020 Partial Approval SCOTT FINNILA
Special/Order Compliance 1/8/2021 Approved THOMAS LOGRASSO
ELECTRICAL-Rough 8/13/2021 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 8/13/2021 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 8/13/2021 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 9/1/2021 Partial Inspection ROBERT VORHIS
Underground Mechanical 9/23/2021 Corrections Issued ROBERT VORHIS
Underground Mechanical 9/29/2021 Approved ROBERT VORHIS
ELECTRICAL-Rough 10/13/2021 Not Ready for Inspection ROBERT VORHIS
HVAC-Rough 10/13/2021 Approved ROBERT VORHIS
PLUMBING-Rough 10/13/2021 Approved ROBERT VORHIS
Special/Order Compliance 10/13/2021 Partial Inspection AMY COLIN
ELECTRICAL-Rough 10/22/2021 Approved STUART CHAPMAN
Wood Frame 11/1/2021 Corrections Issued ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Approved ROBERT VORHIS
Underground Mechanical 11/15/2021 Not Ready for Inspection ROBERT VORHIS
BUILDING-Rough-Frame 11/24/2021 Corrections Issued CRAIG DAVIS
Green Building Rough 11/24/2021 Corrections Issued CRAIG DAVIS
Verify Sprinkler Sign Off 11/24/2021 Approved CRAIG DAVIS
BUILDING-Rough-Frame 12/7/2021 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Rough 12/7/2021 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 12/7/2021 Partial Approval ALIZAH MAYAGOITIA
PLUMBING-Rough 12/8/2021 Corrections Issued ALIZAH MAYAGOITIA
Insulation 12/13/2021 Approved ALIZAH MAYAGOITIA
Drywall Nailing 12/27/2021 No Access for Inspection RUBEN SALAS
Drywall Nailing 1/20/2022 Approved ADAM ESCOTO
Interior/Exterior Lathing 3/7/2022 Approved ADAM ESCOTO
Shower Pan 3/7/2022 Approved ADAM ESCOTO
Service/Power Release 8/23/2023 Corrections Issued FREDDIE RIVERA
Service/Power Release 10/26/2023 Corrections Issued FREDDIE RIVERA
Green Building Final 11/7/2024 Not Ready for Inspection FREDDIE RIVERA
Service/Power Release 11/7/2024 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Final 11/18/2024 Approved FREDDIE RIVERA
Service/Power Release 11/18/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 9/9/2025 Approved FREDDIE RIVERA
HVAC-Final 9/9/2025 Approved FREDDIE RIVERA
PLUMBING-Final 9/9/2025 Corrections Issued FREDDIE RIVERA
Special/Order Compliance 9/11/2025 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/25/2025 SGSOV Not Ready ARTHUR NEGRETE
BUILDING-Rough-Frame 9/29/2025 Approved FREDDIE RIVERA
Final 9/29/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 9/29/2025 Approved FREDDIE RIVERA
PLUMBING-Final 9/29/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 9/29/2025 Approved FREDDIE RIVERA
PLUMBING-Final 10/1/2025 Approved FREDDIE RIVERA
Final 10/30/2025 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved FREDDIE RIVERA