Pre-Inspection
|
8/16/2016
|
Approved
|
BRAD BESCOS
|
|
Deputy Grading
|
11/9/2016
|
No Access for Inspection
|
BRAD BESCOS
|
|
Deputy Grading
|
11/10/2016
|
No Access for Inspection
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
11/14/2016
|
No Access for Inspection
|
BRAD BESCOS
|
|
Deputy Grading
|
11/15/2016
|
No Access for Inspection
|
BRAD BESCOS
|
|
Deputy Grading
|
11/16/2016
|
No Access for Inspection
|
BRAD BESCOS
|
|
Piling/Pier/Caisson
|
11/17/2016
|
Partial Approval
|
BRAD BESCOS
|
|
Piling/Pier/Caisson
|
11/22/2016
|
Partial Approval
|
BRAD BESCOS
|
|
Deputy Reinf. Concrete
|
11/23/2016
|
No Access for Inspection
|
BRAD BESCOS
|
|
Footing/Foundation/Slab
|
12/8/2016
|
Partial Approval
|
BRAD BESCOS
|
|
Underground Mechanical
|
1/4/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Underground Mechanical
|
1/11/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Footing/Foundation/Slab
|
1/18/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Footing/Foundation/Slab
|
2/16/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Rough-Elec/Plmb/HVAC
|
3/1/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Grounding or Bonding
|
3/6/2017
|
Not Ready for Inspection
|
JOEL WILLIAMS
|
|
Rough-Elec/Plmb/HVAC
|
3/6/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Footing/Foundation/Slab
|
3/8/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Grounding or Bonding
|
3/8/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
3/14/2017
|
Approved
|
BRAD BESCOS
|
|
Rough-Elec/Plmb/HVAC
|
3/23/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Reinforced Concrete Frame
|
4/7/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Rough-Elec/Plmb/HVAC
|
4/7/2017
|
Not Ready for Inspection
|
BRAD BESCOS
|
|
ELECTRICAL-Rough
|
4/27/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Reinforced Concrete Frame
|
4/27/2017
|
Corrections Issued
|
BRAD BESCOS
|
|
Reinforced Concrete Frame
|
5/2/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Reinforced Concrete Frame
|
5/11/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Deputy Reinf. Concrete
|
5/19/2017
|
Approved
|
BRAD BESCOS
|
|
Reinforced Concrete Frame
|
5/25/2017
|
Partial Approval
|
BRAD BESCOS
|
|
PLUMBING-Rough
|
6/6/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Underground Mechanical
|
6/6/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Footing/Foundation/Slab
|
6/15/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Reinforced Concrete Frame
|
6/26/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Footing/Foundation/Slab
|
6/29/2017
|
Partial Approval
|
BRAD BESCOS
|
|
ELECTRICAL-Rough
|
7/10/2017
|
Not Ready for Inspection
|
BRAD BESCOS
|
|
Pre-Gunite
|
7/10/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Reinforced Concrete Frame
|
7/10/2017
|
Partial Approval
|
BRAD BESCOS
|
|
ELECTRICAL-Rough
|
8/1/2017
|
Partial Approval
|
JOEL WILLIAMS
|
|
Reinforced Concrete Frame
|
8/1/2017
|
Partial Approval
|
BRAD BESCOS
|
|
ELECTRICAL-Rough
|
8/28/2017
|
Partial Approval
|
BRAD BESCOS
|
|
Reinforced Concrete Frame
|
8/28/2017
|
Approved
|
BRAD BESCOS
|
|
Reinforced Concrete Frame
|
9/26/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
11/1/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Reinforced Concrete Frame
|
11/1/2017
|
Conditional Approval
|
DANIEL GONZALEZ
|
|
Reinforced Concrete Frame
|
11/28/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Reinforced Concrete Frame
|
12/4/2017
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Steel/Welding
|
1/16/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
1/18/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Structural Steel Frame
|
1/26/2018
|
Approved
|
DANIEL GONZALEZ
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/13/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
2/16/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
2/28/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Reinforced Concrete Frame
|
2/28/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
3/16/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
3/16/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
4/3/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
4/3/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
HVAC-Rough
|
4/13/2018
|
Not Ready for Inspection
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
4/13/2018
|
Not Ready for Inspection
|
DANIEL GONZALEZ
|
|
HVAC-Rough
|
4/17/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
4/17/2018
|
Conditional Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
5/4/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
5/4/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
5/4/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Excavation/Setback/Form/Re-Bar
|
5/21/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
5/31/2018
|
Partial Inspection
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
5/31/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
5/31/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Reinforced Concrete Frame
|
5/31/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
6/27/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
Sewer
|
7/3/2018
|
Partial Approval
|
DANNY TOLENTINO
|
|
ELECTRICAL-Rough
|
7/12/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
ELECTRICAL-Rough
|
7/23/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
PLUMBING-Rough
|
7/23/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Deputy Drilled-In Anchors
|
8/17/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Deputy Steel/Welding
|
8/17/2018
|
No Access for Inspection
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
9/24/2018
|
Partial Approval
|
DANIEL GONZALEZ
|
|
Structural Steel Frame
|
9/24/2018
|
Partial Inspection
|
DANIEL GONZALEZ
|
|
Footing/Foundation/Slab
|
1/7/2019
|
Partial Approval
|
RONALD COWAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/22/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Green Building Rough
|
1/22/2019
|
Not Ready for Inspection
|
DANNY TOLENTINO
|
|
Verify Sprinkler Sign Off
|
1/22/2019
|
Not Ready for Inspection
|
DANNY TOLENTINO
|
|
Footing/Foundation/Slab
|
1/30/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Footing/Foundation/Slab
|
3/21/2019
|
Partial Approval
|
RONALD COWAN
|
|
PLUMBING-Rough
|
3/21/2019
|
Approved
|
RONALD COWAN
|
|
Green Building Rough
|
3/28/2019
|
Approved
|
DANNY TOLENTINO
|
|
HVAC-Rough
|
3/28/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
ELECTRICAL-Rough
|
3/29/2019
|
Partial Inspection
|
DANNY TOLENTINO
|
|
ELECTRICAL-Rough
|
4/2/2019
|
Corrections Issued
|
DANNY TOLENTINO
|
|
ELECTRICAL-Rough
|
4/5/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
ELECTRICAL-Rough
|
4/19/2019
|
Corrections Issued
|
DANNY TOLENTINO
|
|
ELECTRICAL-Rough
|
4/23/2019
|
Approved
|
DANNY TOLENTINO
|
|
BUILDING-Rough-Frame
|
5/1/2019
|
Corrections Issued
|
DANNY TOLENTINO
|
|
Verify Sprinkler Sign Off
|
5/1/2019
|
Not Ready for Inspection
|
DANNY TOLENTINO
|
|
Footing/Foundation/Slab
|
6/20/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
Reinforced Concrete Frame
|
6/27/2019
|
Partial Approval
|
DANNY TOLENTINO
|
|
BUILDING-Rough-Frame
|
7/2/2019
|
Approved
|
DANNY TOLENTINO
|
|
HVAC-Rough
|
7/2/2019
|
Approved
|
DANNY TOLENTINO
|
|
Verify Sprinkler Sign Off
|
7/2/2019
|
Approved
|
DANNY TOLENTINO
|
|
Insulation
|
7/18/2019
|
Approved
|
RICHARD STEINBACH
|
|
Drywall Nailing
|
7/22/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Drywall Nailing
|
7/31/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Shower Pan
|
9/3/2019
|
Approved
|
RICHARD STEINBACH
|
|
Footing/Foundation/Slab
|
9/4/2019
|
Approved
|
RAUL BARAJAS
|
|
PLUMBING-Rough
|
9/4/2019
|
Approved
|
RAUL BARAJAS
|
|
Deputy Steel/Welding
|
9/9/2019
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Structural Steel Frame
|
9/11/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Interior/Exterior Lathing
|
9/25/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Interior/Exterior Lathing
|
10/23/2019
|
Approved
|
ROBERT CORNELL
|
|
Deputy Steel/Welding
|
11/4/2019
|
Conditional Approval
|
RICHARD STEINBACH
|
|
Interior/Exterior Lathing
|
12/17/2019
|
Partial Approval
|
RICHARD STEINBACH
|
|
Interior/Exterior Lathing
|
12/26/2019
|
Approved
|
ROBERT CORNELL
|
|
Interior/Exterior Lathing
|
2/4/2020
|
Not Ready for Inspection
|
ROBERT CORNELL
|
|
Interior/Exterior Lathing
|
2/5/2020
|
Approved
|
ROBERT CORNELL
|
|
Special/Order Compliance
|
4/14/2020
|
Approved
|
CHRISTOPHER DELLEFIELD
|
|
ELECTRICAL-Rough
|
4/29/2020
|
Partial Inspection
|
RAUL BARAJAS
|
|
Service/Power Release
|
5/12/2020
|
Partial Inspection
|
RAUL BARAJAS
|
|
Gas Test
|
5/28/2020
|
Approved
|
CHRISTOPHER DELLEFIELD
|
|
Service/Power Release
|
6/12/2020
|
Partial Inspection
|
RAUL BARAJAS
|
|
Deputy Steel/Welding
|
7/15/2020
|
Conditional Approval
|
CHRISTOPHER DELLEFIELD
|
|
Deputy Steel/Welding
|
7/17/2020
|
Conditional Approval
|
RAUL BARAJAS
|
|
Service/Power Release
|
7/21/2020
|
Approved
|
RAUL BARAJAS
|
|
PLUMBING-Final
|
7/30/2020
|
Partial Approval
|
RAUL BARAJAS
|
|
HVAC-Final
|
8/6/2020
|
Corrections Issued
|
RAUL BARAJAS
|
|
HVAC-Final
|
8/20/2020
|
Conditional Approval
|
RAUL BARAJAS
|
|
Green Building Final
|
9/9/2020
|
Corrections Issued
|
DAVID FEILER
|
|
HVAC-Final
|
9/15/2020
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
ELECTRICAL-Final
|
9/18/2020
|
Corrections Issued
|
RAUL BARAJAS
|
|
Green Building Final
|
10/26/2020
|
Approved
|
RAUL BARAJAS
|
|
Final
|
1/11/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
1/11/2021
|
SGSOV Not Ready
|
RAUL BARAJAS
|
|
Smoke Detectors
|
1/11/2021
|
Not Ready for Inspection
|
RAUL BARAJAS
|
|
Final
|
2/3/2021
|
Corrections Issued
|
RAUL BARAJAS
|
|
SGSOV-Seismic Gas S/O Valve
|
2/3/2021
|
SGSOV Approved
|
RAUL BARAJAS
|
|
Smoke Detectors
|
2/3/2021
|
Approved
|
RAUL BARAJAS
|
|
Final
|
2/5/2021
|
Partial Approval
|
RAUL BARAJAS
|