8269 W ARIA DR 90034
Certificate Information: 8269 W ARIA DR 90034
- Application / Permit
- 15010-30000-01534
- Plan Check / Job No.
- B15WL02163
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New single family home with attached garage as part of a small lot subdivision
- Permit Issued
- Issued on 4/24/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/27/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2015 | APPLICANT |
| Green Plans Picked Up | 5/22/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2015 | SHANGQIN XIE |
| Corrections Issued | 6/9/2015 | SHANGQIN XIE |
| Quality Review Completed | 6/18/2015 | SHAHEN AKELYAN |
| Building Plans Picked Up | 6/30/2015 | APPLICANT |
| Applicant returned to address corrections | 7/21/2015 | SHANGQIN XIE |
| Applicant returned to address corrections | 9/24/2015 | SHANGQIN XIE |
| Applicant returned to address corrections | 10/27/2015 | SHANGQIN XIE |
| Plan Check Approved | 11/2/2015 | SHANGQIN XIE |
| No Progress | 11/3/2015 | SHANGQIN XIE |
| Plan Check Approved | 11/24/2015 | SHANGQIN XIE |
| Issued | 4/24/2018 | LADBS |
| CofO in Progress | 8/11/2020 | EVAN COOPER |
| CofO Issued | 8/27/2020 | VINCENT COTTON |
| Permit Finaled | 8/27/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/29/2015 | ROBERT DUFF |
| Miscellaneous | Cleared | 9/29/2015 | ANDY RODRIGUEZ |
| Miscellaneous | Cleared | 10/14/2015 | PHONG NGUYEN |
| Miscellaneous | Cleared | 10/14/2015 | PHONG NGUYEN |
| Roof/Waste drainage to street | Cleared | 10/14/2015 | PHONG NGUYEN |
| Sewer availability | Cleared | 10/14/2015 | PHONG NGUYEN |
| Low Impact Development | Cleared | 10/16/2015 | VIJAY DESAI |
| Green Code | Cleared | 10/27/2015 | SHANGQIN XIE |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2015 | HISASHI KOBAYAKAWA |
Contact Information
| Architect | Leavitt, Derek Chase; Lic. No.: C31212 | 425 MARINE STREET # 6 SANTA MONICA, CA 90405 |
| Contractor | Owner-Builder | , |
| Engineer | Chan, Christopher Charles; Lic. No.: C30282 | 2567 SO SALEROSO DR ROWLAND HEIGHTS, CA 91748 |
| Engineer | Eosakul, Dissakorn; Lic. No.: S5226 | 8363 EDGE WOOD ST CHINO, CA 91708 |
| Engineer | Foroughi, Mohammad Hossein; Lic. No.: C66179 | PO BOX 643079 LOS ANGELES, CA 90064 |
| Engineer | Ho, Damon Tehcheng; Lic. No.: C71956 | 1935 RANCHO HILLS DR CHINO HILLS, CA 91709 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 10/18/2018 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 10/18/2018 | Corrections Issued | ROBERT VORHIS |
| PLUMBING-Rough | 10/18/2018 | Partial Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 10/25/2018 | Partial Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 10/25/2018 | Corrections Issued | ROBERT VORHIS |
| PLUMBING-Rough | 10/25/2018 | Corrections Issued | ROBERT VORHIS |
| ELECTRICAL-Rough | 10/31/2018 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 10/31/2018 | Corrections Issued | ROBERT VORHIS |
| PLUMBING-Rough | 10/31/2018 | Partial Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/2/2018 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 11/20/2018 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2018 | Partial Approval | MICHAEL TEMPLE |
| Green Building Rough | 12/21/2018 | Not Ready for Inspection | MICHAEL TEMPLE |
| Verify Sprinkler Sign Off | 12/21/2018 | Not Ready for Inspection | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2019 | Partial Approval | ROBERT VORHIS |
| Wood Frame | 1/9/2019 | Partial Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2019 | Partial Inspection | ROBERT VORHIS |
| Wood Frame | 2/19/2019 | Partial Inspection | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2019 | Partial Approval | ROBERT VORHIS |
| Deputy Wood Construction | 3/21/2019 | Corrections Issued | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2019 | No Access for Inspection | RONALD WEBER |
| Floor/Roof Diaphrgm/Shear Wall | 3/27/2019 | Partial Approval | ROBERT VORHIS |
| Drywall Nailing | 4/5/2019 | Partial Approval | ROBERT VORHIS |
| Green Building Rough | 4/5/2019 | Not Ready for Inspection | ROBERT VORHIS |
| ELECTRICAL-Rough | 5/1/2019 | Approved | ROBERT VORHIS |
| HVAC-Rough | 5/1/2019 | Approved | ROBERT VORHIS |
| PLUMBING-Rough | 5/1/2019 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 5/8/2019 | Approved | ROBERT VORHIS |
| Green Building Rough | 5/8/2019 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 5/8/2019 | Partial Approval | ROBERT VORHIS |
| Verify Sprinkler Sign Off | 5/8/2019 | Approved | ROBERT VORHIS |
| Insulation | 5/28/2019 | Approved | ROBERT VORHIS |
| Drywall Nailing | 6/17/2019 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 6/17/2019 | Approved | ROBERT VORHIS |
| Special/Order Compliance | 9/13/2019 | Corrections Issued | EVAN COOPER |
| Special/Order Compliance | 9/16/2019 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 9/17/2019 | Not Ready for Inspection | EVAN COOPER |
| Special/Order Compliance | 9/18/2019 | Partial Approval | EVAN COOPER |
| Special/Order Compliance | 9/18/2019 | Partial Inspection | ROBERT SHELLY |
| Sewer | 2/10/2020 | Approved | EVAN COOPER |
| Gas Test | 2/13/2020 | Approved | EVAN COOPER |
| Special/Order Compliance | 2/21/2020 | Partial Inspection | EVAN COOPER |
| ELECTRICAL-Final | 4/27/2020 | Partial Approval | EVAN COOPER |
| Gas Test | 4/27/2020 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/27/2020 | Approved | EVAN COOPER |
| Service/Power Release | 5/28/2020 | Approved | EVAN COOPER |
| Final | 8/3/2020 | Conditional Approval | EVAN COOPER |
| Green Building Final | 8/3/2020 | Approved | EVAN COOPER |
| HVAC-Final | 8/3/2020 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/3/2020 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/3/2020 | Approved | EVAN COOPER |
| Structural Steel Frame | 8/3/2020 | Approved | EVAN COOPER |