8269 W ARIA DR 90034

Certificate Information: 8269 W ARIA DR 90034

Application / Permit
15010-30000-01534
Plan Check / Job No.
B15WL02163
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New single family home with attached garage as part of a small lot subdivision
Permit Issued
Issued on 4/24/2018
Issuing Office
Metro
Current Status
CofO Issued on 8/27/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2015 APPLICANT
Green Plans Picked Up 5/22/2015 APPLICANT
Assigned to Plan Check Engineer 5/27/2015 SHANGQIN XIE
Corrections Issued 6/9/2015 SHANGQIN XIE
Quality Review Completed 6/18/2015 SHAHEN AKELYAN
Building Plans Picked Up 6/30/2015 APPLICANT
Applicant returned to address corrections 7/21/2015 SHANGQIN XIE
Applicant returned to address corrections 9/24/2015 SHANGQIN XIE
Applicant returned to address corrections 10/27/2015 SHANGQIN XIE
Plan Check Approved 11/2/2015 SHANGQIN XIE
No Progress 11/3/2015 SHANGQIN XIE
Plan Check Approved 11/24/2015 SHANGQIN XIE
Issued 4/24/2018 LADBS
CofO in Progress 8/11/2020 EVAN COOPER
CofO Issued 8/27/2020 VINCENT COTTON
Permit Finaled 8/27/2020 VINCENT COTTON

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/29/2015 ROBERT DUFF
Miscellaneous Cleared 9/29/2015 ANDY RODRIGUEZ
Miscellaneous Cleared 10/14/2015 PHONG NGUYEN
Miscellaneous Cleared 10/14/2015 PHONG NGUYEN
Roof/Waste drainage to street Cleared 10/14/2015 PHONG NGUYEN
Sewer availability Cleared 10/14/2015 PHONG NGUYEN
Low Impact Development Cleared 10/16/2015 VIJAY DESAI
Green Code Cleared 10/27/2015 SHANGQIN XIE
Eng Process Fee Ord 176,300 Cleared 11/2/2015 HISASHI KOBAYAKAWA

Contact Information

Architect Leavitt, Derek Chase; Lic. No.: C31212 425 MARINE STREET # 6      SANTA MONICA, CA 90405
Contractor Owner-Builder       ,
Engineer Chan, Christopher Charles; Lic. No.: C30282 2567 SO SALEROSO DR      ROWLAND HEIGHTS, CA 91748
Engineer Eosakul, Dissakorn; Lic. No.: S5226 8363 EDGE WOOD ST      CHINO, CA 91708
Engineer Foroughi, Mohammad Hossein; Lic. No.: C66179 PO BOX 643079      LOS ANGELES, CA 90064
Engineer Ho, Damon Tehcheng; Lic. No.: C71956 1935 RANCHO HILLS DR      CHINO HILLS, CA 91709

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/18/2018 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 10/18/2018 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 10/18/2018 Partial Inspection ROBERT VORHIS
ELECTRICAL-Rough 10/25/2018 Partial Inspection ROBERT VORHIS
Footing/Foundation/Slab 10/25/2018 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 10/25/2018 Corrections Issued ROBERT VORHIS
ELECTRICAL-Rough 10/31/2018 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 10/31/2018 Corrections Issued ROBERT VORHIS
PLUMBING-Rough 10/31/2018 Partial Approval ROBERT VORHIS
Footing/Foundation/Slab 11/2/2018 Partial Approval DAVID HEINE
Footing/Foundation/Slab 11/20/2018 Approved ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 12/21/2018 Partial Approval MICHAEL TEMPLE
Green Building Rough 12/21/2018 Not Ready for Inspection MICHAEL TEMPLE
Verify Sprinkler Sign Off 12/21/2018 Not Ready for Inspection MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 1/9/2019 Partial Approval ROBERT VORHIS
Wood Frame 1/9/2019 Partial Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 2/19/2019 Partial Inspection ROBERT VORHIS
Wood Frame 2/19/2019 Partial Inspection ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 3/15/2019 Partial Approval ROBERT VORHIS
Deputy Wood Construction 3/21/2019 Corrections Issued ROBERT SHELLY
Floor/Roof Diaphrgm/Shear Wall 3/22/2019 No Access for Inspection RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 3/27/2019 Partial Approval ROBERT VORHIS
Drywall Nailing 4/5/2019 Partial Approval ROBERT VORHIS
Green Building Rough 4/5/2019 Not Ready for Inspection ROBERT VORHIS
ELECTRICAL-Rough 5/1/2019 Approved ROBERT VORHIS
HVAC-Rough 5/1/2019 Approved ROBERT VORHIS
PLUMBING-Rough 5/1/2019 Approved ROBERT VORHIS
BUILDING-Rough-Frame 5/8/2019 Approved ROBERT VORHIS
Green Building Rough 5/8/2019 Approved ROBERT VORHIS
Interior/Exterior Lathing 5/8/2019 Partial Approval ROBERT VORHIS
Verify Sprinkler Sign Off 5/8/2019 Approved ROBERT VORHIS
Insulation 5/28/2019 Approved ROBERT VORHIS
Drywall Nailing 6/17/2019 Approved ROBERT VORHIS
Interior/Exterior Lathing 6/17/2019 Approved ROBERT VORHIS
Special/Order Compliance 9/13/2019 Corrections Issued EVAN COOPER
Special/Order Compliance 9/16/2019 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 9/17/2019 Not Ready for Inspection EVAN COOPER
Special/Order Compliance 9/18/2019 Partial Approval EVAN COOPER
Special/Order Compliance 9/18/2019 Partial Inspection ROBERT SHELLY
Sewer 2/10/2020 Approved EVAN COOPER
Gas Test 2/13/2020 Approved EVAN COOPER
Special/Order Compliance 2/21/2020 Partial Inspection EVAN COOPER
ELECTRICAL-Final 4/27/2020 Partial Approval EVAN COOPER
Gas Test 4/27/2020 Approved EVAN COOPER
PLUMBING-Final 4/27/2020 Approved EVAN COOPER
Service/Power Release 5/28/2020 Approved EVAN COOPER
Final 8/3/2020 Conditional Approval EVAN COOPER
Green Building Final 8/3/2020 Approved EVAN COOPER
HVAC-Final 8/3/2020 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Approved EVAN COOPER
Smoke Detectors 8/3/2020 Approved EVAN COOPER
Structural Steel Frame 8/3/2020 Approved EVAN COOPER