1227 N ROBERTO LANE 90077
Certificate Information: 1227 N ROBERTO LANE 90077
- Application / Permit
- 15010-20004-01126
- Plan Check / Job No.
- B24VN05897
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO PERMIT #15010-20000-01126 TO REVISE BLDG DESIGN TO CURRENT CODE & COMPLETE WORK AT 55%. REMOVE ELEVATOR SHAFT AT ROOFTOP DECK AND TO REVISE THE OVERALL BUILDING HEIGHT/ROOF PITCH TO COMPLY WITH CURRENT CODE.
- Permit Issued
- Issued on 12/17/2024
- Issuing Office
- Valley
- Current Status
- Issued on 12/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2024 | PETER MOSESIAN |
| Corrections Issued | 5/8/2024 | PETER MOSESIAN |
| Quality Review Completed | 5/10/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/14/2024 | APPLICANT |
| Plan Check Approved | 12/17/2024 | PETER MOSESIAN |
| Issued | 12/17/2024 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/16/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/16/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/16/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/16/2024 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/16/2024 | DINAH GARIN |
| Sewer availability | Cleared | 5/16/2024 | DINAH GARIN |
| ZA Case | Cleared | 5/20/2024 | MATHEW QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2024 | KIMBERLY HERNANDEZ |
| Hydrant and Access approval | Cleared | 12/3/2024 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales, Cesar Del Valle; Lic. No.: C76612 | 415 S OXFORD AVE APT 208 LOS ANGELES, CA 90020 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/23/2025 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 6/23/2025 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 6/23/2025 | Partial Inspection | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 7/17/2025 | Partial Approval | STEPHANIE SWANSON |
| Gas Test | 7/21/2025 | Partial Approval | CHRISTOPHER WILSON |
| Underground Mechanical | 7/21/2025 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 7/24/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 2/27/2026 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/27/2026 | Approved | CHRISTOPHER WILSON |