599 W AVENUE 28 UNIT 6 90065

Certificate Information: 599 W AVENUE 28 UNIT 6 90065

Application / Permit
15010-20000-04668
Plan Check / Job No.
B15VN16824
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New 3- story irregular shape single family dwelling with attached 2- car garage in a Small Lot Subdivision pursuant to Tract Map No. *******. The proposed structure shall be fully sprinklered per NFPA-13D requirements. Affordable Housing Project.
Permit Issued
Issued on 4/6/2018
Issuing Office
Metro
Current Status
CofO Issued on 2/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2015 APPLICANT
Assigned to Plan Check Engineer 12/30/2015 ARMEN SARKISIAN
Corrections Issued 1/4/2016 ARMEN SARKISIAN
Quality Review Completed 1/5/2016 STEVEN KIM
Building Plans Picked Up 1/12/2016 APPLICANT
Green Plans Picked Up 1/12/2016 APPLICANT
Applicant returned to address corrections 6/19/2017 ARMEN SARKISIAN
Applicant returned to address corrections 7/27/2017 ARMEN SARKISIAN
Applicant returned to address corrections 3/14/2018 ZAW HAN
Plan Check Approved 4/5/2018 Zaw Han
Issued 4/6/2018 LADBS
CofO in Progress 2/4/2022 ALEJANDRO DE ARTOLA
Permit Finaled 2/14/2022 DEROLD HAUFF
Permit Finaled 2/14/2022 DEROLD HAUFF
CofO Issued 2/14/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/16/2016 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/16/2016 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 8/30/2017 SARAH GOLDMAN
Miscellaneous Cleared 8/30/2017 SARAH GOLDMAN
Miscellaneous Cleared 8/30/2017 SARAH GOLDMAN
ZA Case Cleared 8/30/2017 SARAH GOLDMAN
ZA Case Cleared 8/30/2017 SARAH GOLDMAN
ZI Cleared 10/11/2017 NOAH MCCOY
Green Code Cleared 11/7/2017 ARMEN SARKISIAN
Work Adjacent to Public Way Cleared 12/14/2017 RAVIL MANAPOV
DCP conditions approval Cleared 1/19/2018 LOUIE MILLER
Housing density bonus Cleared 1/19/2018 LOUIE MILLER
Low Impact Development Cleared 2/16/2018 MARTIN FRAGOSO
Sewer availability Cleared 3/7/2018 MICHAEL CASTILLO
Roof/Waste drainage to street Cleared 3/19/2018 ADRIAN SANCHEZ
Permit Cleared 3/20/2018 ZEMAMU GEBREWOLD
Highway dedication Cleared 3/22/2018 ADRIAN SANCHEZ
Driveway location Cleared 4/5/2018 COLLINS ALLAN
Hydrant and Access approval Cleared 4/5/2018 JOHN DALLAS
Miscellaneous Cleared 4/5/2018 FIPE LEILUA
Supp. Use District POD/CDO/TDO Cleared 4/5/2018 FIPE LEILUA

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B 10236 LAKEWOOD BLVD STE B      DOWNEY, CA 90241
Engineer Nguyen, Lam Thanh; Lic. No.: C36957 12277 BAJA PANORAMA      SANTA ANA, CA 92705

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 7/23/2018 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/27/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 9/6/2018 Approved SCOTT FINNILA
Drywall Nailing 11/2/2018 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/6/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 11/9/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 12/14/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/28/2018 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 1/23/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/30/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/20/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 3/27/2019 Corrections Issued SCOTT FINNILA
HVAC-Rough 3/29/2019 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 3/29/2019 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 4/1/2019 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 4/1/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Partial Approval SCOTT FINNILA
Shower Pan 6/10/2019 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/17/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/27/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 7/9/2019 Approved SCOTT FINNILA
Green Building Rough 7/11/2019 Approved SCOTT FINNILA
HVAC-Rough 7/11/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 7/15/2019 Approved SCOTT FINNILA
ELECTRICAL-Rough 7/15/2019 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 7/15/2019 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/24/2019 Approved SCOTT FINNILA
HVAC-Rough 7/24/2019 Approved SCOTT FINNILA
Insulation 7/24/2019 Approved SCOTT FINNILA
Drywall Nailing 8/26/2019 Approved SCOTT FINNILA
Interior/Exterior Lathing 8/26/2019 Partial Approval SCOTT FINNILA
Interior/Exterior Lathing 9/4/2019 Conditional Approval MICHAEL FAUNCE
Interior/Exterior Lathing 9/13/2019 Partial Approval SCOTT FINNILA
Sewer 12/19/2019 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 4/16/2021 Partial Inspection SCOTT FINNILA
PLUMBING-Final 4/16/2021 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 7/9/2021 Corrections Issued SCOTT FINNILA
Gas Test 7/9/2021 Approved SCOTT FINNILA
Service/Power Release 7/9/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 8/2/2021 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 9/17/2021 Corrections Issued SCOTT FINNILA
HVAC-Final 9/17/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Final 9/17/2021 Corrections Issued SCOTT FINNILA
Service/Power Release 9/17/2021 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Final 12/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 12/15/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Approved ALEJANDRO DE ARTOLA
Smoke Detectors 12/15/2021 Approved ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 12/15/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/21/2021 Approved ALEJANDRO DE ARTOLA
Final 12/21/2021 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 12/21/2021 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 12/21/2021 Approved ALEJANDRO DE ARTOLA
Service/Power Release 12/21/2021 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 12/27/2021 Approved SCOTT FINNILA
Service/Power Release 12/27/2021 Approved SCOTT FINNILA
Final 12/30/2021 Corrections Issued SCOTT FINNILA
Green Building Final 12/30/2021 Approved SCOTT FINNILA
Final 1/14/2022 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Final 1/20/2022 Conditional Approval ALEJANDRO DE ARTOLA
Final 1/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 1/20/2022 Conditional Approval ALEJANDRO DE ARTOLA
PLUMBING-Final 1/20/2022 Conditional Approval ALEJANDRO DE ARTOLA
Final 1/28/2022 Partial Inspection SCOTT FINNILA
Final 2/3/2022 OK to Issue CofO ALEJANDRO DE ARTOLA