1041 W LEIGHTON AVE 90037

Certificate Information: 1041 W LEIGHTON AVE 90037

Application / Permit
15010-20000-04607
Plan Check / Job No.
B15VN17118
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY, 4-UNITS APARTMENTS, TYPE V-A , FULLY SPRINKLER NFPA-13R (max 4 habitable rooms/ unit or cup req'd per city planning)
Permit Issued
Issued on 6/16/2017
Issuing Office
Metro
Current Status
CofO Issued on 3/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2015 APPLICANT
Disabled Access Plans Picked Up 1/13/2016 APPLICANT
Assigned to Plan Check Engineer 1/21/2016 SAM CHANG
Green Plans Picked Up 1/25/2016 APPLICANT
Corrections Issued 1/26/2016 SAM CHANG
Quality Review Completed 1/27/2016 STEVEN KIM
Building Plans Picked Up 1/27/2016 APPLICANT
Applicant returned to address corrections 3/4/2016 SAM CHANG
Applicant returned to address corrections 4/19/2017 SAM CHANG
Plan Check Approved 5/10/2017 SAM CHANG
Issued 6/16/2017 LADBS
TCO Issued (Expire Date: 05-13-2023) 11/14/2022 WINSTON DUNNING
CofO in Progress 3/10/2023 JAMES POWERS
Permit Finaled 3/10/2023 ERNESTO CORRAL
CofO Issued 3/10/2023 ERNESTO CORRAL
Permit Finaled 3/10/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/30/2016 ROBERT SAMONTE
Permit Cleared 3/30/2016 ROBERT SAMONTE
Eng Process Fee Ord 176,300 Cleared 4/6/2016 AVALYN KAMACHI
Hydrant and Access approval Cleared 4/6/2016 ROBERT DUFF
Project located in CRA area Cleared 4/6/2016 JIM URQUHART
Sewer availability Cleared 4/6/2016 AVALYN KAMACHI
CPC Cleared 5/18/2016 CASSANDRA ZWEEP
CPC Cleared 5/18/2016 CASSANDRA ZWEEP
Grading in hillside Cleared 5/18/2016 CASSANDRA ZWEEP
ZA Case Cleared 5/18/2016 CASSANDRA ZWEEP
ZI Cleared 2/15/2017 DAISY BENICIA
DAS Clearance Cleared 2/27/2017 SAM CHANG
Green Code Cleared 3/2/2017 MICHAEL AYERS
Frnt yard landscape/Water mgmt Cleared 3/17/2017 DANALYNN DOMINGUEZ
Low Impact Development Cleared 3/30/2017 SAM NAVID
Roof/Waste drainage to street Cleared 4/21/2017 ERIK MUNOZ

Contact Information

Contractor Air Max Inc; Lic. No.: 1015725-B 2907 EAST OCEAN BLVD      LONG BEACH, CA 90803
Engineer Babakhanian, Oksen; Lic. No.: S3500 6854 FOOTHILL BLVD      TUJUNGA, CA 91042

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/18/2017 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/11/2017 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/15/2017 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 9/22/2017 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/22/2017 Not Ready for Inspection JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 9/25/2017 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 9/27/2017 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 10/3/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/3/2017 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/4/2017 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/4/2017 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/6/2017 No Access for Inspection JOEY BUCHANAN
Deputy Reinf. Concrete 10/11/2017 Partial Approval JAMES POWERS
Final 5/3/2018 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/8/2018 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/10/2019 Partial Approval JAMES POWERS
Deputy Steel/Welding 4/5/2019 Partial Approval JAMES POWERS
Green Building Rough 5/15/2019 Partial Approval JAMES POWERS
Insulation 5/15/2019 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/15/2019 Not Ready for Inspection JAMES POWERS
Wood Frame 5/15/2019 Partial Approval JAMES POWERS
Drywall Nailing 3/6/2020 Partial Approval JAMES POWERS
Drywall Nailing 3/17/2020 Partial Approval JAMES POWERS
Final 7/15/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/15/2022 Approved JAMES POWERS
Green Building Final 7/15/2022 Approved JAMES POWERS
Green Building Rough 7/15/2022 Order to Comply Issued JAMES POWERS
SGSOV-Seismic Gas S/O Valve 7/15/2022 SGSOV Approved JAMES POWERS
Smoke Detectors 7/15/2022 Order to Comply Issued JAMES POWERS
Verify Sprinkler Sign Off 7/15/2022 Not Ready for Inspection JAMES POWERS
Wood Frame 7/15/2022 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 7/26/2022 Partial Approval JAMES POWERS
Final 11/10/2022 OK for TCO JAMES POWERS
Green Building Rough 11/10/2022 Approved JAMES POWERS
Smoke Detectors 11/10/2022 Approved JAMES POWERS
Verify Sprinkler Sign Off 11/10/2022 Approved JAMES POWERS
Wood Frame 11/10/2022 Approved JAMES POWERS
Final 12/19/2022 Partial Approval JAMES POWERS
Final 3/10/2023 OK to Issue CofO JAMES POWERS