1624 N NORMANDIE AVE A-E 90027

Certificate Information: 1624 N NORMANDIE AVE A-E 90027

Application / Permit
15010-20000-04442
Plan Check / Job No.
B15VN16264
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 2- story irregular shape five unit apartment building over 1- level of basement garage. The proposed structure shall be fully sprinklered per NFPA-13R requirements. Maximum buildng height is limitted to 30'-0" as measured from adjacent lowest grade to top of parapet wall. See comments.
Permit Issued
Issued on 6/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2015 APPLICANT
Assigned to Plan Check Engineer 1/14/2016 ARMEN SARKISIAN
Corrections Issued 1/28/2016 ARMEN SARKISIAN
Quality Review Completed 1/29/2016 STEVEN KIM
Building Plans Picked Up 2/1/2016 APPLICANT
Disabled Access Plans Picked Up 2/1/2016 APPLICANT
Green Plans Picked Up 2/1/2016 APPLICANT
Applicant returned to address corrections 5/11/2016 ARMEN SARKISIAN
Applicant returned to address corrections 6/23/2016 ARMEN SARKISIAN
Applicant returned to address corrections 10/26/2017 ARMEN SARKISIAN
Applicant returned to address corrections 6/6/2018 HAYATO TSUCHIYA
Applicant returned to address corrections 6/13/2018 HAYATO TSUCHIYA
Applicant returned to address corrections 6/29/2018 HAYATO TSUCHIYA
Applicant returned to address corrections 9/10/2018 HAYATO TSUCHIYA
Applicant returned to address corrections 11/30/2018 HAYATO TSUCHIYA
Plan Check Approved 5/24/2019 HAYATO TSUCHIYA
Issued 6/5/2019 LADBS
CofO in Progress 7/22/2024 DAVID BURKHEAD
Permit Finaled 7/22/2024 ERNESTO CORRAL
CofO Issued 7/22/2024 ERNESTO CORRAL
Permit Finaled 7/22/2024 ERNESTO CORRAL

Permit Application Clearance Information

Permit Cleared 9/13/2016 YESENIA DIAZ
Address approval Cleared 5/4/2017 CARLA VALLADARES
Low Impact Development Cleared 8/22/2017 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 10/26/2017 STEVE MELGAR
Sewer availability Cleared 10/26/2017 STEVE MELGAR
Roof/Waste drainage to street Cleared 12/18/2017 NAZILA NOORIFAR
Specific Plan Cleared 5/30/2018 NURI CHO
DAS Clearance Cleared 6/12/2018 NORLITO MEDRANO
Highway dedication Cleared 8/14/2018 MARKOS PEREZ-BRAN
Green Code Cleared 8/28/2018 MICHAEL AYERS
Certificate of Compliance Cleared 9/17/2018 DAISY BENICIA
Driveway location Cleared 11/26/2018 EDUARDO HERMOSO
Hydrant and Access approval Cleared 11/26/2018 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 12/6/2018 SHEILA GERSHON
Miscellaneous Cleared 12/6/2018 SHEILA GERSHON
Miscellaneous Cleared 12/6/2018 SHEILA GERSHON
Opn space landscape/Water mgmt Cleared 12/6/2018 SHEILA GERSHON
Miscellaneous Cleared 12/19/2018 SHEILA GERSHON

Contact Information

Architect Jazayeri, Siavash; Lic. No.: C22240 20230 WELLS DR      WOODLAND HILLS, CA 91364
Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786
Engineer Pirbadian, Amir; Lic. No.: C72413 5435 BALBOA BLVD 212      ENCINO, CA 91436
Engineer Vidal, Juan Alonso; Lic. No.: GE861 15331 DOGWOOD ST      WESTMINSTER, CA 92683

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/18/2020 Partial Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 8/3/2021 Not Ready for Inspection DANIEL MC AULIFFE
Footing/Foundation/Slab 8/3/2021 Not Ready for Inspection DANIEL MC AULIFFE
Excavation/Setback/Form/Re-Bar 8/12/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 8/12/2021 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 8/17/2021 Partial Approval EDWIN GREGORYONA
Excavation/Setback/Form/Re-Bar 10/4/2021 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 10/4/2021 Partial Approval DANIEL MC AULIFFE
Wall Anchors 10/4/2021 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 10/6/2021 Approved DANIEL MC AULIFFE
Footing/Foundation/Slab 10/18/2021 Partial Approval DANIEL MC AULIFFE
Green Building Rough 11/8/2021 Not Ready for Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 11/8/2021 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 11/8/2021 Partial Inspection DANIEL MC AULIFFE
Deputy Wood Construction 11/19/2021 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 11/22/2021 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 12/6/2021 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 No Access for Inspection RAFAEL ESPINOZA
Green Building Rough 12/8/2021 Not Ready for Inspection DANIEL MC AULIFFE
Verify Sprinkler Sign Off 12/8/2021 Not Ready for Inspection DANIEL MC AULIFFE
Wood Frame 12/8/2021 Partial Approval DANIEL MC AULIFFE
Deputy Wood Construction 12/21/2021 Conditional Approval DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval DAVID BURKHEAD
Insulation 1/11/2022 Not Ready for Inspection DANIEL MC AULIFFE
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Partial Approval DANIEL MC AULIFFE
Insulation 1/21/2022 Not Ready for Inspection DANIEL MC AULIFFE
Green Building Rough 5/4/2022 Not Ready for Inspection DAVID BURKHEAD
Verify Sprinkler Sign Off 5/4/2022 Not Ready for Inspection DAVID BURKHEAD
Wood Frame 5/4/2022 Not Ready for Inspection DAVID BURKHEAD
Pre-Inspection 5/9/2022 Partial Approval TED RIES
Insulation 5/16/2022 Partial Approval TED RIES
Deputy Wood Construction 5/25/2022 Partial Approval EDWIN GREGORYONA
Green Building Rough 5/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/25/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 5/25/2022 Partial Inspection EDWIN GREGORYONA
Deputy Wood Construction 5/31/2022 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval DAVID BURKHEAD
Green Building Rough 7/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 7/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 7/18/2022 Not Ready for Inspection EDWIN GREGORYONA
Special/Order Compliance 7/20/2022 Approved EDWIN GREGORYONA
Green Building Rough 7/27/2022 Approved EDWIN GREGORYONA
Insulation 7/27/2022 Approved EDWIN GREGORYONA
Verify Sprinkler Sign Off 7/27/2022 Approved EDWIN GREGORYONA
Wood Frame 7/27/2022 Approved EDWIN GREGORYONA
Drywall Nailing 8/3/2022 Partial Approval DAVID BURKHEAD
Interior/Exterior Lathing 8/3/2022 Approved DAVID BURKHEAD
Drywall Nailing 8/8/2022 Partial Approval DAVID BURKHEAD
Drywall Nailing 8/11/2022 Approved DAVID BURKHEAD
Deputy Reinf. Concrete 10/24/2022 Approved DAVID BURKHEAD
Footing/Foundation/Slab 10/24/2022 Partial Approval DAVID BURKHEAD
Deputy Reinf. Concrete 11/30/2022 Conditional Approval MICHAEL ROSENBERG
Masonry Wall/Backfill 11/30/2022 Partial Approval DAVID BURKHEAD
Final 9/13/2023 Corrections Issued DAVID BURKHEAD
Footing/Foundation/Slab 9/13/2023 Approved DAVID BURKHEAD
Green Building Final 9/13/2023 Not Ready for Inspection DAVID BURKHEAD
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved DAVID BURKHEAD
Smoke Detectors 9/13/2023 Approved DAVID BURKHEAD
Structural Steel Frame 9/13/2023 Conditional Approval DAVID BURKHEAD
Final 9/18/2023 Corrections Issued DAVID BURKHEAD
Green Building Final 9/18/2023 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 9/18/2023 Not Ready for Inspection DAVID BURKHEAD
Final 9/22/2023 Corrections Issued DAVID BURKHEAD
Green Building Final 9/22/2023 Not Ready for Inspection DAVID BURKHEAD
Structural Steel Frame 9/22/2023 Not Ready for Inspection DAVID BURKHEAD
Final 6/5/2024 Partial Inspection RAFAEL ESPINOZA
Green Building Final 6/5/2024 Approved RAFAEL ESPINOZA
Structural Steel Frame 6/5/2024 Approved RAFAEL ESPINOZA
Final 7/19/2024 OK to Issue CofO DAVID BURKHEAD