18913 W GAULT ST 2 91335

Certificate Information: 18913 W GAULT ST 2 91335

Application / Permit
15010-20000-04403
Plan Check / Job No.
B15VN16175
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD / GARAGE - PLAN B SMALL LOT SUBDIVISION PURSUANT TO VESTING TENENATIVE TRACT MAP NO. 73200--SL. A CERTIFICATE OF OCCUPANCY (TEMP. OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
Permit Issued
Issued on 1/29/2018
Issuing Office
Valley
Current Status
CofO Issued on 5/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2015 APPLICANT
Green Plans Picked Up 1/4/2016 APPLICANT
Assigned to Plan Check Engineer 1/14/2016 RODNEY SAMIIAN
Corrections Issued 1/25/2016 RODNEY SAMIIAN
Quality Review Completed 1/29/2016 STEVEN KIM
Building Plans Picked Up 1/29/2016 APPLICANT
Applicant returned to address corrections 3/31/2016 RODNEY SAMIIAN
Applicant returned to address corrections 6/16/2016 RODNEY SAMIIAN
Applicant returned to address corrections 6/30/2016 RODNEY SAMIIAN
Applicant returned to address corrections 6/28/2017 RODNEY SAMIIAN
Applicant returned to address corrections 7/11/2017 RODNEY SAMIIAN
Plan Check Approved 12/19/2017 RODNEY SAMIIAN
Issued 1/29/2018 LADBS
CofO in Progress 5/16/2022 SEAN WIRCH
Permit Finaled 5/17/2022 MICHAEL SMITH
CofO Issued 5/17/2022 MICHAEL SMITH
Permit Finaled 5/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/17/2016 LEE GUILBEAUX
Hydrant and Access approval Cleared 4/1/2016 JOHN DALLAS
Address approval Cleared 6/29/2016 HOWARD COOPER
Green Code Cleared 7/8/2016 MICHAEL AYERS
Sewer availability Cleared 9/30/2016 ERIK MUNOZ
Low Impact Development Cleared 10/11/2016 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 10/12/2016 LEE GUILBEAUX
Permit Cleared 10/4/2017 KENNETH PHAM
"Q" conditions Cleared 11/17/2017 SARAH GOLDMAN
"T" removal Cleared 11/17/2017 SARAH GOLDMAN
Miscellaneous Cleared 11/17/2017 SARAH GOLDMAN
Miscellaneous Cleared 11/17/2017 SARAH GOLDMAN
ZI Cleared 11/17/2017 SARAH GOLDMAN
Miscellaneous Cleared 12/4/2017 SARAH GOLDMAN
Miscellaneous Cleared 12/8/2017 KENNETH PHAM
Miscellaneous Cleared 12/19/2017 EDUARDO PEDROZA
Hold Cleared 2/14/2018 PRECY SANCHEZ

Contact Information

Contractor Yaghoubi M Corp; Lic. No.: 972773-B 6459 LUBAO AVENUE      WOODLAND HILLS, CA 91367
Engineer , ; Lic. No.: GE861       ,
Engineer Gharai, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

HENRY KIM, (818) 774-4334 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/28/2019 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 3/29/2019 Partial Approval DONALD SUNSERI
Underground Mechanical 4/15/2019 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/8/2019 Corrections Issued DONALD SUNSERI
Excavation/Setback/Form/Re-Bar 5/9/2019 Approved DONALD SUNSERI
Footing/Foundation/Slab 5/9/2019 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 6/10/2019 Partial Approval DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 7/23/2019 Partial Approval DONALD SUNSERI
ELECTRICAL-Rough 7/29/2019 Not Ready for Inspection DONALD SUNSERI
HVAC-Rough 7/29/2019 Approved DONALD SUNSERI
PLUMBING-Rough 7/31/2019 Approved JOSEPH SAGEN
ELECTRICAL-Rough 8/7/2019 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 8/8/2019 Not Ready for Inspection JOSEPH SAGEN
Green Building Rough 8/8/2019 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 8/8/2019 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 8/16/2019 Approved JOSEPH SAGEN
Drywall Nailing 8/21/2019 Approved DONALD SUNSERI
Shower Pan 9/24/2019 Approved DONALD SUNSERI
ELECTRICAL-Final 7/29/2020 Not Ready for Inspection SEAN WIRCH
HVAC-Final 7/29/2020 Not Ready for Inspection SEAN WIRCH
PLUMBING-Final 7/29/2020 Not Ready for Inspection SEAN WIRCH
Service/Power Release 7/29/2020 Not Ready for Inspection SEAN WIRCH
Service/Power Release 12/15/2020 Not Ready for Inspection JOSEPH SAGEN
Service/Power Release 12/24/2020 Approved SEAN WIRCH
Underground Mechanical 3/1/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 4/12/2021 Not Ready for Inspection JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 4/12/2021 SGSOV Not Ready JOSEPH SAGEN
Underground Mechanical 4/12/2021 Partial Approval JOSEPH SAGEN
ELECTRICAL-Final 6/18/2021 Not Ready for Inspection JOSEPH SAGEN
Gas Test 6/18/2021 Approved JOSEPH SAGEN
Green Building Final 6/18/2021 Not Ready for Inspection JOSEPH SAGEN
HVAC-Final 6/18/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Final 6/18/2021 Not Ready for Inspection JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 6/18/2021 SGSOV Approved JOSEPH SAGEN
Smoke Detectors 6/18/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Final 7/7/2021 Approved JOSEPH SAGEN
HVAC-Final 7/7/2021 Approved JOSEPH SAGEN
PLUMBING-Final 7/7/2021 Approved JOSEPH SAGEN
Final 5/17/2022 OK to Issue CofO SEAN WIRCH
Green Building Final 5/17/2022 Approved SEAN WIRCH
Smoke Detectors 5/17/2022 Approved SEAN WIRCH