22119 W MARTINEZ ST 91364

Certificate Information: 22119 W MARTINEZ ST 91364

Application / Permit
15010-20000-04289
Plan Check / Job No.
B15VN15826
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 46'-2" X 76'-4" 2-STORY SFD W/ ATTACHED 2-CAR GARAGE PER ENGINEERING
Permit Issued
Issued on 10/5/2016
Issuing Office
Valley
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2015 APPLICANT
Assigned to Plan Check Engineer 12/10/2015 JENNIFER LEE
Corrections Issued 12/15/2015 JENNIFER LEE
Quality Review Completed 12/15/2015 STEVEN KIM
Building Plans Picked Up 12/21/2015 APPLICANT
Green Plans Picked Up 12/21/2015 APPLICANT
Plan Check Approved 6/27/2016 JENNIFER LEE
Issued 10/5/2016 LADBS
CofO in Progress 7/7/2022 PETER FOLLING
Permit Finaled 8/1/2022 JOHN JANSON
CofO Issued 8/1/2022 JOHN JANSON
Permit Finaled 8/1/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/5/2016 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/5/2016 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/5/2016 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/5/2016 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 2/5/2016 LEE GUILBEAUX
Permit Cleared 2/5/2016 LEE GUILBEAUX
Low Impact Development Cleared 4/14/2016 AMMAR ELTAWIL
Eng Process Fee Ord 176,300 Cleared 4/22/2016 ROBERT SAMONTE
Hydrant and Access approval Cleared 4/22/2016 JOHN DALLAS
Roof/Waste drainage to street Cleared 4/22/2016 ROBERT SAMONTE
Sewer availability Cleared 4/22/2016 ROBERT SAMONTE
Green Code Cleared 5/16/2016 RICHARD DOCKUS
GPI Written Notices Cleared 6/23/2016 JENNIFER LEE
Grading Pre-Inspection Cleared 6/23/2016 JENNIFER LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Gorgy, Moheb Shohdy; Lic. No.: C53260 1545 VICTORY BLVD STE 102      GLENDALE, CA 91201
Engineer Jitechian, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/25/2017 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 9/7/2017 Conditional Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2018 Corrections Issued MICHAEL TEMPLE
Deputy Wood Construction 2/9/2018 No Access for Inspection MICHAEL TEMPLE
PLUMBING-Rough 4/5/2018 Partial Inspection MICHAEL TEMPLE
Sewer 4/5/2018 Approved MICHAEL TEMPLE
PLUMBING-Rough 4/19/2018 Conditional Approval MICHAEL TEMPLE
Pre-Inspection 6/18/2018 Corrections Issued MICHAEL TEMPLE
Pre-Inspection 10/26/2020 No Access for Inspection DAVID SANDOVAL
Pre-Inspection 12/15/2020 Partial Approval TROY SANDERS
HVAC-Rough 2/3/2021 Corrections Issued PAUL CHOPP
HVAC-Rough 8/11/2021 Not Ready for Inspection PETER FOLLING
Interior/Exterior Lathing 9/13/2021 Partial Approval PETER FOLLING
HVAC-Rough 10/19/2021 Approved RONALD COWAN
Pre-Inspection 12/1/2021 No Access for Inspection PETER FOLLING
Insulation 12/17/2021 Corrections Issued PETER FOLLING
Insulation 2/1/2022 Corrections Issued PETER FOLLING
PLUMBING-Rough 2/1/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 2/28/2022 Approved PETER FOLLING
Green Building Rough 2/28/2022 Approved PETER FOLLING
Rough-Elec/Plmb/HVAC 2/28/2022 Approved PETER FOLLING
Shower Pan 2/28/2022 Approved PETER FOLLING
Verify Sprinkler Sign Off 2/28/2022 Approved PETER FOLLING
Drywall Nailing 3/8/2022 Not Ready for Inspection PETER FOLLING
Interior/Exterior Lathing 3/8/2022 Approved PETER FOLLING
Drywall Nailing 3/11/2022 Approved ROBERT GOLD
Insulation 3/11/2022 Approved ROBERT GOLD
Excavation/Setback/Form/Re-Bar 3/30/2022 Approved PETER FOLLING
Final 3/30/2022 Not Ready for Inspection PETER FOLLING
Green Building Final 3/30/2022 Not Ready for Inspection PETER FOLLING
SGSOV-Seismic Gas S/O Valve 3/30/2022 SGSOV Not Ready PETER FOLLING
Service/Power Release 3/30/2022 Not Ready for Inspection PETER FOLLING
Smoke Detectors 3/30/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Final 5/19/2022 Corrections Issued PETER FOLLING
HVAC-Final 5/19/2022 Corrections Issued PETER FOLLING
PLUMBING-Final 5/19/2022 Approved PETER FOLLING
ELECTRICAL-Final 6/9/2022 Not Ready for Inspection PETER FOLLING
HVAC-Final 6/9/2022 Approved PETER FOLLING
Final 6/24/2022 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 6/24/2022 Approved PETER FOLLING
Green Building Final 6/24/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Not Ready PETER FOLLING
Service/Power Release 6/24/2022 Not Ready for Inspection PETER FOLLING
Smoke Detectors 6/24/2022 Approved PETER FOLLING
Final 7/6/2022 OK to Issue CofO PETER FOLLING
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Approved PETER FOLLING
Service/Power Release 7/6/2022 Approved PETER FOLLING