7101 W MACAPA DR 90068
Certificate Information: 7101 W MACAPA DR 90068
- Application / Permit
- 15010-20000-04094
- Plan Check / Job No.
- B15VN15168
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW REC ROOM WITH ATT DECK AND BATHROOM WHICH SHOWER IS ACCEESSABLE FROM OUTSIDE. DECK ABOVE REC ROOM. CONSTRUCTION ON PILES.
- Permit Issued
- Issued on 10/25/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2015 | RODNEY SAMIIAN |
| Corrections Issued | 1/5/2016 | RODNEY SAMIIAN |
| Quality Review Completed | 1/5/2016 | STEVEN KIM |
| Building Plans Picked Up | 1/8/2016 | APPLICANT |
| Green Plans Picked Up | 1/20/2016 | APPLICANT |
| Applicant returned to address corrections | 3/15/2016 | RODNEY SAMIIAN |
| Plan Check Approved | 9/20/2016 | RODNEY SAMIIAN |
| Issued | 10/25/2016 | LADBS |
| CofO in Progress | 4/10/2024 | BRIAN SULLIVAN |
| Permit Finaled | 4/15/2024 | RONALD MYRICK |
| CofO Issued | 4/15/2024 | RONALD MYRICK |
| Permit Finaled | 4/15/2024 | RONALD MYRICK |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/8/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/8/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/8/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/8/2016 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2016 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 1/8/2016 | JOHN DALLAS |
| Sewer availability | Cleared | 1/8/2016 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/8/2016 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 8/9/2016 | MICHAEL SCADUTO |
| Roof/Waste drainage to street | Cleared | 8/16/2016 | IRENE CHIA |
| Miscellaneous | Cleared | 9/13/2016 | NORALI MARTINEZ |
| Specific Plan | Cleared | 9/13/2016 | NORALI MARTINEZ |
| Green Code | Cleared | 9/20/2016 | ROLLIN GETTLE III |
Contact Information
| Contractor | Glynn Designbuild Inc; Lic. No.: 841188-B | 20944 WAVEVIEW DRIVE TOPANGA, CA 90290 |
| Engineer | Irvine, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD PASADENA, CA 91107 |
| Engineer | Resnick, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 12/30/2016 | Not Ready for Inspection | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 1/3/2017 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/13/2017 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 4/24/2017 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/24/2017 | Partial Approval | BRIAN SULLIVAN |
| Deputy Shotcrete | 4/27/2017 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/12/2017 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 5/12/2017 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/18/2017 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/19/2017 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/20/2017 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/21/2017 | Conditional Approval | BRIAN SULLIVAN |
| Structural Steel Frame | 6/27/2017 | Not Ready for Inspection | LUIS BARRALES |
| Structural Steel Frame | 6/30/2017 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2017 | Partial Approval | BRIAN SULLIVAN |
| Gas Test | 9/28/2017 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 9/28/2017 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/11/2017 | Not Ready for Inspection | BRIAN SULLIVAN |
| Sewer | 10/11/2017 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 10/11/2017 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/17/2017 | Partial Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 10/17/2017 | Partial Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/24/2017 | Partial Approval | BRIAN SULLIVAN |
| Sewer | 10/24/2017 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/24/2018 | Conditional Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/24/2018 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 1/29/2018 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/14/2018 | Not Ready for Inspection | BRIAN SULLIVAN |
| Shower Pan | 2/16/2018 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/22/2018 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 2/22/2018 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 2/22/2018 | Approved | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 2/22/2018 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 3/2/2018 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/2/2018 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/28/2018 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 3/30/2018 | Partial Approval | BRIAN SULLIVAN |
| Final | 3/12/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/12/2021 | Approved | BRIAN SULLIVAN |
| Green Building Final | 3/12/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 3/12/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Service/Power Release | 3/12/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Smoke Detectors | 3/12/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Final | 3/28/2024 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 3/28/2024 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 3/28/2024 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 3/28/2024 | Approved | BRIAN SULLIVAN |
| Final | 4/10/2024 | OK to Issue CofO | BRIAN SULLIVAN |