2553 N SUMMITRIDGE DR 90210
Certificate Information: 2553 N SUMMITRIDGE DR 90210
- Application / Permit
- 15010-20000-03397
- Plan Check / Job No.
- B15VN12802
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- (N) 27'-0" x 30'-4" DETACHED ONE STORY PATIO COVER. FIRE SPRINKLER NFPA13D
- Permit Issued
- Issued on 6/29/2016
- Issuing Office
- Valley
- Current Status
- Issued on 6/29/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/22/2015 | APPLICANT |
| Green Plans Picked Up | 10/7/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2015 | MOURAD AZIZ |
| Corrections Issued | 10/14/2015 | MOURAD AZIZ |
| Quality Review Completed | 10/14/2015 | STEVEN KIM |
| Building Plans Picked Up | 10/14/2015 | APPLICANT |
| Applicant returned to address corrections | 2/4/2016 | MOURAD AZIZ |
| Applicant returned to address corrections | 2/17/2016 | MOURAD AZIZ |
| Applicant returned to address corrections | 2/23/2016 | MOURAD AZIZ |
| Applicant returned to address corrections | 3/16/2016 | MOURAD AZIZ |
| Applicant returned to address corrections | 6/10/2016 | MOURAD AZIZ |
| Applicant returned to address corrections | 6/23/2016 | MOURAD AZIZ |
| Plan Check Approved | 6/27/2016 | MOURAD AZIZ |
| Issued | 6/29/2016 | LADBS |
| Permit Expired-Status Void | 8/3/2018 | APPLICANT |
| Re-Activate Permit | 8/27/2018 | JOEL LAUNCHBAUGH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/9/2015 | MOURAD AZIZ |
| Grading Pre-Inspection | Cleared | 10/9/2015 | MOURAD AZIZ |
| Hydrant and Access approval | Cleared | 11/30/2015 | ROBERT DUFF |
| Miscellaneous | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Miscellaneous | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Private street | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Private street | Cleared | 12/23/2015 | SARAH HOUNSELL |
| Specific Plan | Cleared | 12/23/2015 | SARAH HOUNSELL |
| ZA Case | Cleared | 12/23/2015 | SARAH HOUNSELL |
| BHO/Hillside ordinance | Cleared | 1/12/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/12/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/12/2016 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 1/12/2016 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2016 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/12/2016 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 1/12/2016 | LEE GUILBEAUX |
| Green Code | Cleared | 1/13/2016 | MICHAEL AYERS |
Contact Information
| Engineer | Tsao, Tze-Tzong; Lic. No.: C46886 | 9428 ETON AVE STE M CHATSWORTH, CA 91311 |
| Engineer | Zhang, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
| Geologist | Schick, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/12/2017 | Not Ready for Inspection | DANIEL ORRANTE |
| Drywall Nailing | 6/12/2017 | Not Ready for Inspection | DANIEL ORRANTE |
| Final | 6/12/2017 | Not Ready for Inspection | DANIEL ORRANTE |
| Footing/Foundation/Slab | 6/12/2017 | Not Ready for Inspection | DANIEL ORRANTE |
| SGSOV-Seismic Gas S/O Valve | 6/12/2017 | SGSOV Not Ready | DANIEL ORRANTE |
| Service/Power Release | 6/12/2017 | Not Ready for Inspection | DANIEL ORRANTE |
| Smoke Detectors | 6/12/2017 | Not Ready for Inspection | DANIEL ORRANTE |
| Verify Sprinkler Sign Off | 6/12/2017 | Not Ready for Inspection | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 7/11/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Drywall Nailing | 7/11/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Final | 7/11/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Footing/Foundation/Slab | 7/11/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| SGSOV-Seismic Gas S/O Valve | 7/11/2018 | SGSOV Not Ready | JOEL LAUNCHBAUGH |
| Service/Power Release | 7/11/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Smoke Detectors | 7/11/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Verify Sprinkler Sign Off | 7/11/2018 | Partial Inspection | JOEL LAUNCHBAUGH |
| Special/Order Compliance | 11/10/2018 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/15/2018 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 3/7/2020 | Partial Inspection | CHRISTOPHER WILSON |