12310 W 10TH HELENA DR 90049
Certificate Information: 12310 W 10TH HELENA DR 90049
- Application / Permit
- 15010-20000-03388
- Plan Check / Job No.
- B15VN12768
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- (N) 19' X 33'8" POOL HOUSE. SPRINKLERS
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Current Status
- CofO Issued on 12/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2015 | HERNAN ARREOLA |
| Corrections Issued | 10/19/2015 | HERNAN ARREOLA |
| Quality Review Completed | 10/19/2015 | STEVEN KIM |
| Building Plans Picked Up | 10/19/2015 | APPLICANT |
| Green Plans Picked Up | 10/23/2015 | APPLICANT |
| Plan Check Approved | 1/15/2016 | HERNAN ARREOLA |
| Issued | 1/25/2021 | APPLICANT |
| CofO in Progress | 8/3/2022 | ANDREW NAVE |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
| CofO Issued | 12/13/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/13/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 11/9/2015 | HERMAN VAN BUREN |
| ZI | Cleared | 11/9/2015 | HERMAN VAN BUREN |
| Eng Process Fee Ord 176,300 | Cleared | 11/10/2015 | RAVIL MANAPOV |
| Sewer availability | Cleared | 11/10/2015 | RAVIL MANAPOV |
| Low Impact Development | Cleared | 12/9/2015 | IDA MEISAMI-FARD |
| Roof/Waste drainage to street | Cleared | 12/10/2015 | ARMENIA HERNANDEZ |
| Green Code | Cleared | 12/29/2015 | RICHARD DOCKUS |
Contact Information
| Architect | Ward, Charles L Iii; Lic. No.: C32266 | 418 S JUNE ST LOS ANGELES, CA 90020 |
| Contractor | Mg Home Repair Llc; Lic. No.: 985830-B | 11150 W OLYMPIC BLVD STE 600 LOS ANGELES, CA 90064 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
| Geologist | Byer, John W; Lic. No.: EG883 | 1649 PUEBLA DRIVE GLENDALE, CA 91207 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/26/2021 | Partial Inspection | JOHN KIDWELL |
| Piling/Pier/Caisson | 3/19/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Piling/Pier/Caisson | 3/22/2021 | Approved | PIERRE VEGA |
| Deputy Reinf. Concrete | 3/23/2021 | Corrections Issued | JOHN KIDWELL |
| Underground Mechanical | 5/20/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Reinf. Concrete | 5/25/2021 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 6/11/2021 | Approved | JOHN KIDWELL |
| Deputy Shotcrete | 6/14/2021 | Conditional Approval | ROBERT SHELLY |
| Deputy Drilled-In Anchors | 6/30/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 7/1/2021 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 7/20/2021 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 7/27/2021 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Corrections Issued | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 7/30/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/30/2021 | Conditional Approval | JOHN KIDWELL |
| Green Building Rough | 8/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 8/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Deputy Wood Construction | 9/14/2021 | No Access for Inspection | KENNETH NAGLE |
| ELECTRICAL-Rough | 9/29/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Rough | 9/29/2021 | Approved | JOHN KIDWELL |
| Structural Steel Frame | 9/29/2021 | Partial Approval | JOHN KIDWELL |
| Wood Frame | 9/29/2021 | Partial Approval | JOHN KIDWELL |
| Insulation | 10/12/2021 | Corrections Issued | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 10/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 10/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Gunite | 10/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 10/26/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/8/2021 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 11/29/2021 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 11/29/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 11/29/2021 | Approved | STEPHANIE SWANSON |
| Shower Pan | 11/29/2021 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 12/2/2021 | Approved | JUAN VALENZUELA |
| Shower Pan | 12/2/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 1/20/2022 | Approved | JOHN KIDWELL |
| HVAC-Final | 1/20/2022 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 1/20/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 3/10/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Insulation | 3/14/2022 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 5/10/2022 | Approved | JOHN KIDWELL |
| Final | 5/10/2022 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 5/10/2022 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 5/10/2022 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 5/10/2022 | Approved | JOHN KIDWELL |
| Final | 8/3/2022 | OK to Issue CofO | ANDREW NAVE |
| Green Building Final | 8/3/2022 | Approved | ANDREW NAVE |