16680 W CHARMEL LANE 90272
Certificate Information: 16680 W CHARMEL LANE 90272
- Application / Permit
- 15010-20000-03022
- Plan Check / Job No.
- B15VN11395
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY SFD W/BASEMENT AND ATT. GARAGE (Tier 1).
- Permit Issued
- Issued on 6/26/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2015 | CHON CHIO KUO |
| Corrections Issued | 9/8/2015 | CHON CHIO KUO |
| Quality Review Completed | 9/11/2015 | TIEN JEN WANG |
| Building Plans Picked Up | 9/11/2015 | APPLICANT |
| Green Plans Picked Up | 9/11/2015 | APPLICANT |
| Applicant returned to address corrections | 6/2/2016 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/21/2016 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/31/2017 | CHON CHIO KUO |
| Applicant returned to address corrections | 3/20/2017 | CHON CHIO KUO |
| Applicant returned to address corrections | 4/6/2017 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/15/2017 | CHON CHIO KUO |
| Plan Check Approved | 6/14/2017 | CHON CHIO KUO |
| Issued | 6/26/2017 | LADBS |
| Permit Expired-Status Void | 2/7/2020 | RONALD MYRICK |
| Re-Activate Permit | 3/5/2020 | VINCENT COTTON |
| CofO in Progress | 1/13/2025 | EVAN COOPER |
| CofO Issued | 1/15/2025 | RICHARD STEINBACH |
| Permit Finaled | 1/15/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/4/2015 | RICHARD SOUTHERLAND |
| BHO/Hillside ordinance | Cleared | 12/4/2015 | RICHARD SOUTHERLAND |
| BHO/Hillside ordinance | Cleared | 12/4/2015 | RICHARD SOUTHERLAND |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2015 | RICHARD SOUTHERLAND |
| Hydrant and Access approval | Cleared | 12/4/2015 | JOHN DALLAS |
| Permit | Cleared | 12/4/2015 | RICHARD SOUTHERLAND |
| Sewer availability | Cleared | 12/4/2015 | RICHARD SOUTHERLAND |
| Low Impact Development | Cleared | 9/19/2016 | VIJAY DESAI |
| Green Code | Cleared | 10/12/2016 | MICHAEL AYERS |
| Roof/Waste drainage to street | Cleared | 11/9/2016 | JAMES KHO |
| Coastal Zone | Cleared | 1/18/2017 | RICK TORRES |
| Landscape for retaining wall | Cleared | 1/18/2017 | RICK TORRES |
| Excavation more than 5-ft deep | Cleared | 1/31/2017 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/31/2017 | CHON CHIO KUO |
| Grading Pre-Inspection | Cleared | 1/31/2017 | CHON CHIO KUO |
| Green Code | Cleared | 2/7/2017 | MICHAEL AYERS |
Contact Information
| Architect | Toufanian, Hamid; Lic. No.: C26445 | 2908 NEBRASKA AVENUE SANTA MONICA, CA 90404 |
| Contractor | Ecogreen Construction Incorporated; Lic. No.: 938218-B | 1719 STEWART ST SANTA MONICA, CA 904044021 |
| Engineer | Mani, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/6/2017 | Partial Inspection | VINCENT SCIPIONI |
| Pre-Inspection | 1/16/2019 | Corrections Issued | ANDREW NAVE |
| Pre-Inspection | 7/9/2019 | Corrections Issued | ANDREW NAVE |
| Special/Order Compliance | 2/6/2020 | Corrections Issued | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Corrections Issued | ANDREW NAVE |
| Piling/Pier/Caisson | 11/18/2021 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/13/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Piling/Pier/Caisson | 12/13/2021 | Corrections Issued | BRENDAN LOONEY |
| Piling/Pier/Caisson | 12/20/2021 | Approved | ANDREW NAVE |
| Deputy Reinf. Concrete | 12/21/2021 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 12/22/2021 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 1/7/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 1/10/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 1/12/2022 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 1/25/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 1/31/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 2/1/2022 | Conditional Approval | ANDREW NAVE |
| Underground Mechanical | 2/14/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 2/17/2022 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 2/24/2022 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/8/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/10/2022 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 3/14/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/16/2022 | Conditional Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 3/17/2022 | Approved | MICHAEL PELHAM |
| Underground Mechanical | 3/23/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/29/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 4/4/2022 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 4/4/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 4/5/2022 | Approved | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/10/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/26/2022 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 6/3/2022 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 6/16/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/24/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/9/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/26/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 9/26/2022 | Not Ready for Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 10/12/2022 | Partial Approval | TIMOTHY POWELL |
| PLUMBING-Rough | 10/24/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 11/14/2022 | Partial Inspection | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/23/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 1/19/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Conditional Approval | BRENDAN LOONEY |
| Special/Order Compliance | 2/6/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 3/13/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 3/13/2023 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 3/22/2023 | Partial Approval | BRENDAN LOONEY |
| HVAC-Rough | 4/3/2023 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 4/17/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 4/17/2023 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 4/24/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 6/22/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 6/22/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 6/22/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 9/14/2023 | Approved | EVAN COOPER |
| Green Building Rough | 9/14/2023 | Approved | EVAN COOPER |
| Shower Pan | 10/17/2023 | Approved | EVAN COOPER |
| Insulation | 10/25/2023 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 10/30/2023 | Approved | EVAN COOPER |
| Drywall Nailing | 12/5/2023 | Approved | EVAN COOPER |
| Final | 10/18/2024 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 10/18/2024 | Approved | EVAN COOPER |
| Green Building Final | 10/18/2024 | Approved | EVAN COOPER |
| Reinforced Concrete Frame | 10/18/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/18/2024 | SGSOV Not Ready | EVAN COOPER |
| Service/Power Release | 10/18/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 10/18/2024 | Approved | EVAN COOPER |
| Final | 10/22/2024 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 10/22/2024 | SGSOV Not Ready | EVAN COOPER |
| Pool/Spa Cover | 11/15/2024 | Approved | EVAN COOPER |
| Final | 12/3/2024 | Conditional Approval | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/3/2024 | SGSOV Approved | EVAN COOPER |
| Final | 12/12/2024 | Corrections Issued | EVAN COOPER |
| Final | 12/30/2024 | OK to Issue CofO | EVAN COOPER |