1942 N BRONSON AVE 90068

Certificate Information: 1942 N BRONSON AVE 90068

Application / Permit
15010-20000-02630
Plan Check / Job No.
B15VN09765
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
NEW DETACHED 1-CAR GARAGE 14'0" X 18'0".
Permit Issued
Issued on 10/22/2015
Issuing Office
Valley
Current Status
CofO Issued on 4/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2015 APPLICANT
Assigned to Plan Check Engineer 7/23/2015 JEFFREY TANGONAN
Corrections Issued 7/23/2015 JEFFREY TANGONAN
Plan Check Approved 10/1/2015 JOSE RODRIGUEZ
Issued 10/22/2015 LADBS
CofO in Progress 1/24/2024 BRIAN SULLIVAN
Permit Finaled 4/25/2024 RONALD MYRICK
CofO Issued 4/25/2024 RONALD MYRICK
Permit Finaled 4/25/2024 RONALD MYRICK

Permit Application Clearance Information

CPC Cleared 8/5/2015 RALPH AVILA
Grading Pre-Inspection Cleared 8/5/2015 DAVID FONSECA
Eng Process Fee Ord 176,300 Cleared 8/18/2015 HOWARD COOPER
Roof/Waste drainage to street Cleared 8/18/2015 HOWARD COOPER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/18/2016 Partial Approval RUBEN SALAS
Footing/Foundation/Slab 5/12/2017 Approved CRAIG VAUGHAN
Green Building Rough 11/2/2020 Not Ready for Inspection BRIAN SULLIVAN
Wood Frame 11/2/2020 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 12/13/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Wood Frame 12/13/2022 Not Ready for Inspection JOAQUIN GREENOUGH
Final 10/5/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 10/5/2023 Approved JOAQUIN GREENOUGH
Green Building Rough 10/5/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 10/5/2023 Approved JOAQUIN GREENOUGH
Wood Frame 10/5/2023 Approved JOAQUIN GREENOUGH
Final 1/23/2024 OK to Issue CofO BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved BRIAN SULLIVAN