1942 N BRONSON AVE 90068
Certificate Information: 1942 N BRONSON AVE 90068
- Application / Permit
- 15010-20000-02630
- Plan Check / Job No.
- B15VN09765
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED 1-CAR GARAGE 14'0" X 18'0".
- Permit Issued
- Issued on 10/22/2015
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2015 | JEFFREY TANGONAN |
| Corrections Issued | 7/23/2015 | JEFFREY TANGONAN |
| Plan Check Approved | 10/1/2015 | JOSE RODRIGUEZ |
| Issued | 10/22/2015 | LADBS |
| CofO in Progress | 1/24/2024 | BRIAN SULLIVAN |
| Permit Finaled | 4/25/2024 | RONALD MYRICK |
| CofO Issued | 4/25/2024 | RONALD MYRICK |
| Permit Finaled | 4/25/2024 | RONALD MYRICK |
Permit Application Clearance Information
| CPC | Cleared | 8/5/2015 | RALPH AVILA |
| Grading Pre-Inspection | Cleared | 8/5/2015 | DAVID FONSECA |
| Eng Process Fee Ord 176,300 | Cleared | 8/18/2015 | HOWARD COOPER |
| Roof/Waste drainage to street | Cleared | 8/18/2015 | HOWARD COOPER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/18/2016 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 5/12/2017 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 11/2/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 11/2/2020 | Corrections Issued | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 12/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 10/5/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 10/5/2023 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 10/5/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 10/5/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 10/5/2023 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 10/5/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 1/23/2024 | OK to Issue CofO | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Approved | BRIAN SULLIVAN |