7310 N ETON AVE #1 - #9 91303

Certificate Information: 7310 N ETON AVE #1 - #9 91303

Application / Permit
15010-20000-02175
Plan Check / Job No.
B15VN07767
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Fully sprinklered 36' x 120', 4 story, 9 unit apartment with garage on 1st floor
Permit Issued
Issued on 12/12/2018
Issuing Office
Valley
Current Status
CofO Issued on 9/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2015 APPLICANT
Assigned to Plan Check Engineer 6/25/2015 STEVEN KIM
Disabled Access Plans Picked Up 7/2/2015 APPLICANT
Green Plans Picked Up 7/2/2015 APPLICANT
Corrections Issued 7/7/2015 STEVEN KIM
Quality Review Completed 7/10/2015 TIEN JEN WANG
Building Plans Picked Up 7/13/2015 APPLICANT
Applicant returned to address corrections 7/31/2015 STEVEN KIM
Applicant returned to address corrections 9/15/2015 STEVEN KIM
Applicant returned to address corrections 9/25/2015 STEVEN KIM
Plan Check Approved 10/6/2015 STEVEN KIM
Issued 12/12/2018 LADBS
Permit Expired-Status Void 1/18/2019 ROBERT COLE
Re-Activate Permit 1/31/2019 ROBERT COLE
TCO Issued (Expire Date: 12-19-2022) 6/22/2022 JEFFREY DURAN
CofO in Progress 9/19/2022 CAMERON CHABAN
Permit Finaled 9/29/2022 RICKEY JACKSON
CofO Issued 9/29/2022 RICKEY JACKSON
Permit Finaled 9/29/2022 RICKEY JACKSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/14/2015 LEE GUILBEAUX
Highway dedication Cleared 7/14/2015 LEE GUILBEAUX
DAS Clearance Cleared 8/20/2015 FARUK SEZER
Hydrant and Access approval Cleared 8/24/2015 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 9/9/2015 RICK TORRES
Green Code Cleared 9/9/2015 MICHAEL AYERS
Low Impact Development Cleared 9/29/2015 AMMAR ELTAWIL
Permit Cleared 9/29/2015 RICHARD SOUTHERLAND
Roof/Waste drainage to street Cleared 10/1/2015 RICHARD SOUTHERLAND
Sewer availability Cleared 10/5/2015 JOHN LIN
Permit Cleared 6/23/2017 CARLA VALLADARES
Roof/Waste drainage to street Cleared 6/23/2017 CARLA VALLADARES
Fire Marshall Fire Life Safety Cleared 8/2/2017 DOMINIQUE MEDINA
Low Impact Development Cleared 9/20/2017 SAM NAVID
Fire Marshall Fire Life Safety Cleared 1/8/2018 DOMINIQUE MEDINA
Sewer availability Cleared 1/30/2018 KENNETH PHAM
Frnt yard landscape/Water mgmt Cleared 2/2/2018 TOM HENRY
DAS Clearance Cleared 2/8/2018 STEVEN KIM
Hydrant and Access approval Cleared 2/8/2018 ROBERT DUFF
Opn space landscape/Water mgmt Cleared 2/14/2018 DENNIS CHEW
Green Code Cleared 2/22/2018 STEVEN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Gharai, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Jitechian, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 1/17/2019 Permit Expired-Status Void ROBERT COLE
Excavation/Setback/Form/Re-Bar 4/16/2019 Partial Inspection ROBERT COLE
Excavation/Setback/Form/Re-Bar 4/23/2019 Partial Approval ROBERT COLE
Reinforced Concrete Frame 6/4/2019 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 6/5/2019 Conditional Approval ROBERT COLE
Reinforced Concrete Frame 6/7/2019 Partial Approval ROBERT COLE
Footing/Foundation/Slab 6/19/2019 Partial Approval ROBERT COLE
Footing/Foundation/Slab 10/17/2019 Corrections Issued ROBERT COLE
Reinforced Concrete Frame 10/17/2019 Not Ready for Inspection ROBERT COLE
Footing/Foundation/Slab 10/21/2019 Partial Inspection ROBERT COLE
Reinforced Concrete Frame 10/21/2019 Partial Inspection ROBERT COLE
Excavation/Setback/Form/Re-Bar 10/24/2019 Not Ready for Inspection ROBERT COLE
Reinforced Concrete Frame 10/24/2019 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 12/17/2019 Not Ready for Inspection DANNY RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 12/20/2019 Partial Approval JEFF BYTHEWAY
Floor/Roof Diaphrgm/Shear Wall 1/23/2020 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Approval ROBERT COLE
Deputy Drilled-In Anchors 4/24/2020 Conditional Approval ROBERT COLE
Deputy Wood Construction 4/27/2020 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Corrections Issued ROBERT COLE
Deputy Wood Construction 4/28/2020 Conditional Approval ROBERT COLE
Deputy Wood Construction 4/29/2020 Conditional Approval ROBERT COLE
Special/Order Compliance 4/29/2020 Not Ready for Inspection ROBERT COLE
Deputy Wood Construction 4/30/2020 Approved HAMID PISHEHVAR
Floor/Roof Diaphrgm/Shear Wall 4/30/2020 Not Ready for Inspection HAMID PISHEHVAR
Deputy Wood Construction 5/1/2020 Conditional Approval ROBERT COLE
Deputy Wood Construction 5/4/2020 Conditional Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Corrections Issued ROBERT COLE
Insulation 6/19/2020 Not Ready for Inspection ROBERT COLE
Interior/Exterior Lathing 6/19/2020 Not Ready for Inspection ROBERT COLE
Insulation 6/23/2020 Partial Inspection ROBERT COLE
Special/Order Compliance 6/23/2020 Corrections Issued ROBERT COLE
Insulation 7/7/2020 Corrections Issued ROBERT COLE
T-Bar Ceiling 7/7/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 7/14/2020 Corrections Issued ROBERT COLE
Green Building Rough 7/14/2020 Not Ready for Inspection ROBERT COLE
Drywall Nailing 7/29/2020 Partial Inspection JEFFREY FULTON
Green Building Rough 7/29/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Rough 9/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Verify Sprinkler Sign Off 9/10/2020 Partial Inspection DANNY RODRIGUEZ
Wood Frame 9/10/2020 Not Ready for Inspection DANNY RODRIGUEZ
Green Building Rough 9/16/2020 Approved HAMID PISHEHVAR
Light Gage Steel Frame 9/16/2020 Approved HAMID PISHEHVAR
Verify Sprinkler Sign Off 9/16/2020 Approved HAMID PISHEHVAR
Wood Frame 9/16/2020 Approved HAMID PISHEHVAR
Insulation 10/1/2020 Partial Approval DANNY RODRIGUEZ
Insulation 10/7/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 10/9/2020 Partial Approval DANIEL VARNUM
Insulation 10/9/2020 Not Ready for Inspection DANIEL VARNUM
Insulation 10/14/2020 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 10/19/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 11/10/2020 Partial Approval DANNY RODRIGUEZ
Interior/Exterior Lathing 11/20/2020 Not Ready for Inspection DANNY RODRIGUEZ
Interior/Exterior Lathing 11/23/2020 Partial Approval DANNY RODRIGUEZ
Grading Pre-Inspection 4/28/2021 Not Ready for Inspection HAMID PISHEHVAR
Grading Pre-Inspection 3/3/2022 Not Ready for Inspection DANNY RODRIGUEZ
Pre-Inspection 4/29/2022 Partial Inspection CAMERON CHABAN
Pre-Inspection 6/17/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 9/16/2022 Approved CAMERON CHABAN
Final 9/16/2022 OK to Issue CofO CAMERON CHABAN
Footing/Foundation/Slab 9/16/2022 Approved CAMERON CHABAN
Green Building Final 9/16/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 9/16/2022 SGSOV Approved CAMERON CHABAN
Smoke Detectors 9/16/2022 Approved CAMERON CHABAN