Sewer
|
11/1/2018
|
Approved
|
DONALD SUNSERI
|
|
Underground Mechanical
|
11/1/2018
|
Approved
|
DONALD SUNSERI
|
|
Excavation/Setback/Form/Re-Bar
|
2/11/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Footing/Foundation/Slab
|
2/11/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
METHANE-Barrier
|
2/11/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
METHANE-Subgrade
|
2/11/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Underground Mechanical
|
2/11/2019
|
Not Ready for Inspection
|
JOHN KIDWELL
|
|
Excavation/Setback/Form/Re-Bar
|
2/20/2019
|
Corrections Issued
|
DONALD SUNSERI
|
|
Footing/Foundation/Slab
|
2/21/2019
|
Approved
|
DONALD SUNSERI
|
|
Deputy Reinf. Concrete
|
2/22/2019
|
Approved
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/13/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/15/2019
|
Partial Approval
|
BRUCE ROZAK
|
|
Deputy Reinf. Concrete
|
3/18/2019
|
Approved
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/26/2019
|
Not Ready for Inspection
|
BRUCE ROZAK
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/27/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/28/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Deputy Drilled-In Anchors
|
4/2/2019
|
Approved
|
DONALD SUNSERI
|
|
Deputy Drilled-In Anchors
|
4/3/2019
|
Approved
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/4/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/9/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/16/2019
|
Corrections Issued
|
JOHN KIDWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/2/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/2/2019
|
Not Ready for Inspection
|
DONALD SUNSERI
|
|
PLUMBING-Rough
|
12/2/2019
|
Partial Approval
|
DONALD SUNSERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/13/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
PLUMBING-Rough
|
12/13/2019
|
Approved
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/17/2019
|
Partial Approval
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/19/2019
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
ELECTRICAL-Rough
|
1/8/2020
|
Approved
|
JOSEPH SAGEN
|
|
HVAC-Rough
|
1/8/2020
|
Approved
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/21/2020
|
Partial Approval
|
JOSEPH SAGEN
|
|
Interior/Exterior Lathing
|
1/31/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
BUILDING-Rough-Frame
|
2/6/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Green Building Rough
|
2/6/2020
|
Approved
|
JOSEPH SAGEN
|
|
Verify Sprinkler Sign Off
|
2/6/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
BUILDING-Rough-Frame
|
2/7/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Verify Sprinkler Sign Off
|
2/7/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/19/2020
|
Partial Approval
|
JOSEPH SAGEN
|
|
Interior/Exterior Lathing
|
2/19/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Verify Sprinkler Sign Off
|
2/19/2020
|
Approved
|
JOSEPH SAGEN
|
|
Insulation
|
2/20/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
BUILDING-Rough-Frame
|
2/25/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Insulation
|
2/25/2020
|
Partial Approval
|
JOSEPH SAGEN
|
|
BUILDING-Rough-Frame
|
2/27/2020
|
Approved
|
JOSEPH SAGEN
|
|
Drywall Nailing
|
3/5/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Interior/Exterior Lathing
|
3/9/2020
|
Partial Approval
|
JOSEPH SAGEN
|
|
Drywall Nailing
|
3/12/2020
|
Approved
|
JOSEPH SAGEN
|
|
Interior/Exterior Lathing
|
3/25/2020
|
Approved
|
JOSEPH SAGEN
|
|
Gas Test
|
5/14/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Gas Test
|
5/19/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Gas Test
|
5/28/2020
|
Approved
|
JOSEPH SAGEN
|
|
SGSOV-Seismic Gas S/O Valve
|
6/26/2020
|
SGSOV Approved
|
JOSEPH SAGEN
|
|
ELECTRICAL-Final
|
8/13/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
HVAC-Final
|
8/13/2020
|
Not Ready for Inspection
|
JOSEPH SAGEN
|
|
Pre-Inspection
|
8/13/2020
|
Partial Approval
|
JOSEPH SAGEN
|
|
Service/Power Release
|
2/11/2021
|
Approved
|
JOSEPH SAGEN
|
|
ELECTRICAL-Final
|
2/25/2022
|
Corrections Issued
|
HENRY KIM
|
|
HVAC-Final
|
2/25/2022
|
Corrections Issued
|
HENRY KIM
|
|
PLUMBING-Final
|
2/25/2022
|
Corrections Issued
|
HENRY KIM
|
|
ELECTRICAL-Final
|
4/7/2022
|
Corrections Issued
|
HENRY KIM
|
|
HVAC-Final
|
4/7/2022
|
Approved
|
HENRY KIM
|
|
PLUMBING-Final
|
4/7/2022
|
Approved
|
HENRY KIM
|
|
ELECTRICAL-Final
|
2/13/2023
|
Approved
|
HENRY KIM
|
|
Final
|
2/13/2023
|
Corrections Issued
|
HENRY KIM
|
|
Green Building Final
|
2/13/2023
|
Approved
|
HENRY KIM
|
|
Smoke Detectors
|
2/13/2023
|
Approved
|
HENRY KIM
|
|
Final
|
2/17/2023
|
OK to Issue CofO
|
HENRY KIM
|