14401 W VALERIO ST 5 91405

Certificate Information: 14401 W VALERIO ST 5 91405

Application / Permit
15010-20000-02138
Plan Check / Job No.
B15VN07589
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SINGLE FAMILY DWELLING W/ GARAGE, BLDG TYPE "B". NEW SINGLE FAMILY DWELLING W/ GARAGE. SMALL LOT SUBDIVISION PURSUANT TO VESTING TENENATIVE TRACT MAP NO. 7248. A CERTIFICATE OF OCCUPANCY (TEMP. OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED.
Permit Issued
Issued on 10/25/2018
Issuing Office
Valley
Current Status
Issued on 10/25/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2015 APPLICANT
Assigned to Plan Check Engineer 7/9/2015 RODNEY SAMIIAN
Green Plans Picked Up 7/15/2015 APPLICANT
Corrections Issued 7/22/2015 RODNEY SAMIIAN
Quality Review Completed 7/23/2015 STEVEN KIM
Building Plans Picked Up 7/23/2015 APPLICANT
Applicant returned to address corrections 4/6/2016 RODNEY SAMIIAN
Applicant returned to address corrections 5/19/2016 RODNEY SAMIIAN
Applicant returned to address corrections 5/31/2016 RODNEY SAMIIAN
Applicant returned to address corrections 6/27/2016 RODNEY SAMIIAN
Applicant returned to address corrections 7/11/2016 RODNEY SAMIIAN
Applicant returned to address corrections 7/15/2016 RODNEY SAMIIAN
Applicant returned to address corrections 11/6/2017 RODNEY SAMIIAN
Applicant returned to address corrections 11/20/2017 RODNEY SAMIIAN
Applicant returned to address corrections 11/29/2017 RODNEY SAMIIAN
Applicant returned to address corrections 3/9/2018 RODNEY SAMIIAN
Applicant returned to address corrections 5/1/2018 RODNEY SAMIIAN
Plan Check Approved 9/26/2018 RODNEY SAMIIAN
Issued 10/25/2018 LADBS

Permit Application Clearance Information

Highway dedication Cleared 5/22/2018 EDUARDO PEDROZA
Address approval Cleared 5/23/2018 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 5/25/2018 JOHN LIN
Sewer availability Cleared 7/2/2018 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/3/2018 JOHN DALLAS
Low Impact Development Cleared 8/30/2018 MITESH PATEL
Miscellaneous Cleared 8/31/2018 MARKOS PEREZ-BRAN
Permit Cleared 8/31/2018 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 8/31/2018 MARKOS PEREZ-BRAN
Green Code Cleared 9/17/2018 BRYAN MEYER
Green Code Cleared 9/17/2018 RODNEY SAMIIAN
"Q" conditions Cleared 9/25/2018 DENNIS CHEW
"T" removal Cleared 9/25/2018 DENNIS CHEW
Miscellaneous Cleared 9/25/2018 DENNIS CHEW
Miscellaneous Cleared 9/25/2018 DENNIS CHEW
Tract Map conditions Cleared 9/25/2018 DENNIS CHEW

Contact Information

Contractor Owner-Builder       ,
Engineer Moreno, Hector M; Lic. No.: C66015 236 W. ORANGE SHOW ROAD STE 105      SAN BERNARDINO, CA 92408
Engineer Podegracz, Joseph David; Lic. No.: C78425 PO BOX 1083      FRAZIER PARK, CA 93225

Inspector Information

JOSEPH SAGEN, (818) 774-4353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/11/2019 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 2/11/2019 Not Ready for Inspection JOHN KIDWELL
METHANE-Barrier 2/11/2019 Not Ready for Inspection JOHN KIDWELL
METHANE-Subgrade 2/11/2019 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 2/11/2019 Not Ready for Inspection JOHN KIDWELL
Special/Order Compliance 2/14/2019 Partial Inspection JOHN KIDWELL
Footing/Foundation/Slab 2/20/2019 Corrections Issued DONALD SUNSERI
Footing/Foundation/Slab 2/21/2019 Approved DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 9/5/2019 Partial Approval JOSEPH SAGEN
PLUMBING-Rough 11/15/2019 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/2/2019 Not Ready for Inspection DONALD SUNSERI
PLUMBING-Rough 12/2/2019 Not Ready for Inspection DONALD SUNSERI
Floor/Roof Diaphrgm/Shear Wall 12/13/2019 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Rough 12/13/2019 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/17/2019 Partial Approval JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 12/19/2019 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Rough 1/8/2020 Approved JOSEPH SAGEN
HVAC-Rough 1/8/2020 Approved JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/13/2020 Not Ready for Inspection JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 1/21/2020 Partial Approval JOSEPH SAGEN
Interior/Exterior Lathing 1/31/2020 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 2/6/2020 Not Ready for Inspection JOSEPH SAGEN
Green Building Rough 2/6/2020 Approved JOSEPH SAGEN
Verify Sprinkler Sign Off 2/6/2020 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 2/7/2020 Not Ready for Inspection JOSEPH SAGEN
Verify Sprinkler Sign Off 2/7/2020 Not Ready for Inspection JOSEPH SAGEN
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Partial Approval JOSEPH SAGEN
Interior/Exterior Lathing 2/19/2020 Not Ready for Inspection JOSEPH SAGEN
Verify Sprinkler Sign Off 2/19/2020 Approved JOSEPH SAGEN
BUILDING-Rough-Frame 2/26/2020 Not Ready for Inspection JOSEPH SAGEN
Insulation 2/28/2020 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 3/4/2020 Not Ready for Inspection JOSEPH SAGEN
BUILDING-Rough-Frame 3/6/2020 Approved JOSEPH SAGEN
Interior/Exterior Lathing 3/9/2020 Partial Approval JOSEPH SAGEN
Drywall Nailing 3/17/2020 Approved JOSEPH SAGEN
Interior/Exterior Lathing 3/25/2020 Approved JOSEPH SAGEN
Gas Test 5/14/2020 Not Ready for Inspection JOSEPH SAGEN
Gas Test 5/19/2020 Not Ready for Inspection JOSEPH SAGEN
Underground Mechanical 5/26/2020 Partial Approval JOSEPH SAGEN
Gas Test 5/27/2020 Approved JOSEPH SAGEN
SGSOV-Seismic Gas S/O Valve 6/26/2020 SGSOV Approved JOSEPH SAGEN
ELECTRICAL-Final 8/13/2020 Not Ready for Inspection JOSEPH SAGEN
Pre-Inspection 8/13/2020 Partial Approval JOSEPH SAGEN
Service/Power Release 2/11/2021 Approved JOSEPH SAGEN
ELECTRICAL-Final 2/25/2022 Corrections Issued HENRY KIM
HVAC-Final 2/25/2022 Corrections Issued HENRY KIM
PLUMBING-Final 2/25/2022 Corrections Issued HENRY KIM
ELECTRICAL-Final 4/7/2022 Corrections Issued HENRY KIM
HVAC-Final 4/7/2022 Approved HENRY KIM
PLUMBING-Final 4/7/2022 Approved HENRY KIM
ELECTRICAL-Final 5/15/2023 Corrections Issued HENRY KIM
Final 5/15/2023 Corrections Issued HENRY KIM
Green Building Final 5/15/2023 Approved HENRY KIM
Smoke Detectors 5/15/2023 Approved HENRY KIM
ELECTRICAL-Final 5/18/2023 Approved HENRY KIM