18636 W INGOMAR ST 91335

Certificate Information: 18636 W INGOMAR ST 91335

Application / Permit
15010-20000-01954
Plan Check / Job No.
B15VN06871
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD WITH ATTACHED 3- CAR GARAGE
Permit Issued
Issued on 7/24/2015
Issuing Office
Valley
Current Status
CofO in Progress on 12/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2015 APPLICANT
Assigned to Plan Check Engineer 6/10/2015 SHANGQIN XIE
Green Plans Picked Up 6/10/2015 APPLICANT
Corrections Issued 6/15/2015 SHANGQIN XIE
Quality Review Completed 6/19/2015 SHAHEN AKELYAN
Building Plans Picked Up 6/19/2015 APPLICANT
Plan Check Approved 7/23/2015 SHANGQIN XIE
Issued 7/24/2015 LADBS
CofO in Progress 12/17/2025 ARUTYUN MADATYAN

Permit Application Clearance Information

"T" removal Cleared 6/25/2015 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 6/25/2015 MIKE KOUYOUMDJIAN
Miscellaneous Cleared 6/25/2015 HERMINIGILDO AGUSTIN
Permit Cleared 6/25/2015 MIKE KOUYOUMDJIAN
Sewer availability Cleared 6/25/2015 MIKE KOUYOUMDJIAN
Tract Map conditions Cleared 6/25/2015 HERMINIGILDO AGUSTIN
Green Code Cleared 7/13/2015 MICKEY YAMASHITA
Hydrant and Access approval Cleared 7/21/2015 ROBERT DUFF
Low Impact Development Cleared 7/21/2015 VIJAY DESAI
Project located in CRA area Cleared 7/22/2015 JIM URQUHART
Roof/Waste drainage to street Cleared 7/22/2015 ARMEN DERMENJIAN

Contact Information

Contractor Joel & Co Construction; Lic. No.: 967864-B 11693 SAN VICENTE BLVD STE 913      LOS ANGELES, CA 90049
Engineer Pulido, Quintero Jose Luis; Lic. No.: C75631 9131 COLLETT AVENUE      NORTH HILLS, CA 91343

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/25/2015 Partial Approval JOEL WILLIAMS
Excavation/Setback/Form/Re-Bar 10/29/2015 Approved TIP WHITING
BUILDING-Rough-Frame 3/18/2016 Partial Approval JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 3/18/2016 Partial Approval JOHN HAYES
Green Building Rough 3/18/2016 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 3/18/2016 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/31/2016 Not Ready for Inspection DONALD GALLAGHER
Green Building Rough 3/31/2016 Not Ready for Inspection DONALD GALLAGHER
Verify Sprinkler Sign Off 3/31/2016 Not Ready for Inspection DONALD GALLAGHER
Interior/Exterior Lathing 4/15/2016 Partial Inspection DONALD GALLAGHER
Gas Test 7/25/2016 Approved DONALD GALLAGHER
PLUMBING-Rough 7/25/2016 Partial Approval DONALD GALLAGHER
PLUMBING-Rough 7/26/2016 Approved DONALD GALLAGHER
Floor/Roof Diaphrgm/Shear Wall 12/16/2016 Approved PETER FOLLING
Interior/Exterior Lathing 4/21/2017 Not Ready for Inspection FELIX ARROYO
ELECTRICAL-Rough 6/14/2017 No Access for Inspection FELIX ARROYO
Interior/Exterior Lathing 6/14/2017 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 7/28/2017 Approved JOHN COLEMAN
HVAC-Rough 7/28/2017 Approved JOHN COLEMAN
BUILDING-Rough-Frame 8/9/2017 Partial Approval CHARLES POWELL
Green Building Rough 8/9/2017 Approved CHARLES POWELL
Verify Sprinkler Sign Off 8/9/2017 Approved CHARLES POWELL
Insulation 2/1/2018 Not Ready for Inspection AJA COLLAY
Insulation 2/5/2018 Approved FELIX ARROYO
Service/Power Release 2/6/2018 Not Ready for Inspection FELIX ARROYO
Shower Pan 2/6/2018 Not Ready for Inspection FELIX ARROYO
Drywall Nailing 2/23/2018 Approved FELIX ARROYO
Shower Pan 2/23/2018 Approved FELIX ARROYO
Interior/Exterior Lathing 3/5/2018 Corrections Issued FELIX ARROYO
Interior/Exterior Lathing 3/12/2018 Not Ready for Inspection FELIX ARROYO
Interior/Exterior Lathing 4/2/2018 Approved PETER FOLLING
Special/Order Compliance 3/29/2019 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 11/7/2024 Approved ARUTYUN MADATYAN
Final 11/7/2024 Corrections Issued ARUTYUN MADATYAN
Footing/Foundation/Slab 11/7/2024 Approved ARUTYUN MADATYAN
Green Building Final 11/7/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 11/7/2024 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 11/7/2024 Approved ARUTYUN MADATYAN
Final 11/14/2024 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 11/14/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved ARUTYUN MADATYAN
ELECTRICAL-Final 12/9/2024 Approved ARUTYUN MADATYAN
Service/Power Release 12/9/2024 Approved ARUTYUN MADATYAN
HVAC-Final 12/11/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 12/11/2024 Approved ARUTYUN MADATYAN
Final 12/16/2025 OK to Issue CofO ARUTYUN MADATYAN