16503 W NAPA ST 91343

Certificate Information: 16503 W NAPA ST 91343

Application / Permit
15010-20000-00767
Plan Check / Job No.
B15VN02645
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Carport
Work Description
New 22'-0" x 18'-6" detached 2-car carport.
Permit Issued
Issued on 4/10/2015
Issuing Office
Valley
Current Status
CofO Issued on 10/31/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/4/2015 APPLICANT
Green Plans Picked Up 3/18/2015 APPLICANT
Assigned to Plan Check Engineer 3/19/2015 KRIKOR MANOUKIAN
Corrections Issued 3/31/2015 KRIKOR MANOUKIAN
Quality Review Completed 4/3/2015 HERNAN ARREOLA
Building Plans Picked Up 4/3/2015 APPLICANT
Plan Check Approved 4/9/2015 KRIKOR MANOUKIAN
Issued 4/10/2015 LADBS
CofO in Progress 10/27/2020 MICHAEL TEMPLE
CofO Issued 10/31/2020 MICHAEL SMITH
Permit Finaled 10/31/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/10/2015 CHRISTINE KEUSHGUERIAN
Roof/Waste drainage to street Cleared 4/10/2015 CHRISTINE KEUSHGUERIAN
Public Works-Highway Ded. Cleared 4/10/2015 CHRISTINE KEUSHGUERIAN
Public Works-Open Permits Cleared 4/10/2015 CHRISTINE KEUSHGUERIAN
Public Works-Sewers Cleared 4/10/2015 CHRISTINE KEUSHGUERIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/5/2015 Corrections Issued PIERRE VEGA
Footing/Foundation/Slab 8/31/2015 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 9/25/2015 No Access for Inspection JACK KARGODORIAN
Footing/Foundation/Slab 9/29/2015 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2015 Partial Approval COREY HUPP
Wood Frame 10/21/2015 Partial Approval COREY HUPP
Final 1/31/2017 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/31/2017 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 1/31/2017 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 1/31/2017 Not Ready for Inspection JACK KARGODORIAN
Final 2/2/2017 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/2/2017 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 2/2/2017 Not Ready for Inspection JACK KARGODORIAN
Wood Frame 2/2/2017 Partial Inspection JACK KARGODORIAN
Final 9/30/2020 Partial Approval JENNIFER RABUCHIN
Smoke Detectors 9/30/2020 Approved JENNIFER RABUCHIN
Wood Frame 9/30/2020 Approved JENNIFER RABUCHIN
Final 10/6/2020 OK to Issue CofO JENNIFER RABUCHIN
Final 10/13/2020 Partial Approval JENNIFER RABUCHIN