427 W 5TH ST 1-347 90013
Certificate Information: 427 W 5TH ST 1-347 90013
- Application / Permit
- 15010-10027-02769
- Plan Check / Job No.
- B20LA01797
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL PERMIT TO 15010-10000-02769 TO ADD DEMISING WALL AT CORE&SHELL COMMERICAL RESTURANT (NO CHANGE OF USE) (T.I. UNDER SEPERATE PERMITS)
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Current Status
- Permit Finaled on 2/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2020 | ARMEN JIVALAGIAN |
| Corrections Issued | 1/31/2020 | ARMEN JIVALAGIAN |
| Plan Check Approved | 7/10/2020 | ARMEN JIVALAGIAN |
| Issued | 10/5/2020 | APPLICANT |
| Building Plans Picked Up | 10/5/2020 | APPLICANT |
| Permit Finaled | 2/5/2021 | DANIEL COLLINS |
Permit Application Clearance Information
| DAS Clearance | Cleared | 1/31/2020 | ARMEN JIVALAGIAN |
| Miscellaneous | Cleared | 1/31/2020 | RICHARD REASER |
| ZA Case | Cleared | 1/31/2020 | RICHARD REASER |
| Redevelopment Project Area | Cleared | 2/5/2020 | GISELLE CORELLA |
| Food Service Establishment | Cleared | 6/26/2020 | RAMESHBHAIR PATEL |
| Green Code | Cleared | 6/30/2020 | ARMEN JIVALAGIAN |
Contact Information
| Contractor | Satoh Brothers International Inc; Lic. No.: 743636-B | 879 W 190TH STREET SUITE 935 GARDENA, CA 90248 |
| Engineer | Conaway, Johnny Ray; Lic. No.: C19689 | PO BOX 155 OAK VIEW, CA 93022 |
| Engineer | Youssef, Nabih Fouad Guirg; Lic. No.: S2026 | 550 S HOPE ST SUITE 1700 LOS ANGELES, CA 90017 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BAZERKANIAN, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/20/2020 | Partial Approval | NICK DANERI |
| Light Gage Steel Frame | 10/23/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 10/29/2020 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Partial Approval | NICK DANERI |
| Deputy Reinf. Concrete | 11/6/2020 | Conditional Approval | KATY RAMIREZ |
| Pre-Inspection | 12/2/2020 | Partial Approval | NICK DANERI |
| Final | 12/30/2020 | Not Ready for Inspection | NICK DANERI |
| Smoke Detectors | 12/30/2020 | Approved | NICK DANERI |
| Final | 2/3/2021 | Not Ready for Inspection | NICK DANERI |
| Final | 2/5/2021 | Permit Finaled | DANIEL COLLINS |