1375 N VINE ST BLG A 90028

Certificate Information: 1375 N VINE ST BLG A 90028

Application / Permit
15010-10022-04706
Plan Check / Job No.
B19LA05551
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
SUPPLEMENTAL TO 15010-10000-04706, POST TENSION CABLES BLDG A LEVEL 6+ROOF
Permit Issued
Issued on 4/16/2019
Issuing Office
Metro
Current Status
Permit Finaled on 11/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2019 APPLICANT
Assigned to Plan Check Engineer 3/28/2019 LARRY LEE
Corrections Issued 4/9/2019 LARRY LEE
Quality Review Completed 4/9/2019 CHARLES CHANG
Building Plans Picked Up 4/10/2019 APPLICANT
Plan Check Approved 4/16/2019 LARRY LEE
Issued 4/16/2019 LADBS
Permit Finaled 11/18/2020 DAVID BURKHEAD

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Hathaway Dinwiddie Construction Company; Lic. No.: 729664-B 275 BATTERY STREET SUITE 300      SAN FRANCISCO, CA 941113330

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Reinforced Concrete Frame 4/29/2019 Partial Approval JEFF BYTHEWAY
Structural Steel Frame 4/30/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 5/2/2019 Partial Approval JEFF BYTHEWAY
Drywall Nailing 5/3/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 5/3/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 5/7/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 5/9/2019 Partial Approval JEFF BYTHEWAY
Pre-Inspection 5/10/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 5/15/2019 Partial Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 5/17/2019 Partial Approval JEFF BYTHEWAY
Reinforced Concrete Frame 5/22/2019 Not Ready for Inspection JEFF BYTHEWAY