21425 W VANOWEN ST 91303
Certificate Information: 21425 W VANOWEN ST 91303
- Application / Permit
- 15010-10007-03622
- Plan Check / Job No.
- B18LA18332
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL PERMIT FOR ARCH. AND STRUCTURAL REVISIONS. SEE DELTA 3.1.4, 5, 6 & 7 ON PLANS. (THERE SHALL BE NO CHANGES TO BUILDING HEIGHT, FLOOR AREA OR OVERALL DIMENSIONS. NO CHANGES TO THE NUMBER OF REQUIRED PARKING)
- Permit Issued
- Issued on 9/10/2018
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 12/27/2019
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 9/4/2018 | JOE VO |
| Issued | 9/10/2018 | LADBS |
| Permit Finaled | 12/27/2019 | JEFFREY DURAN |
Permit Application Clearance Information
| DAS Clearance | Cleared | 8/29/2018 | JOE VO |
| Green Code | Cleared | 8/29/2018 | JOE VO |
| Project located in CRA area | Cleared | 8/29/2018 | JIM URQUHART |
| Fire Marshall Fire Life Safety | Cleared | 8/31/2018 | OSCAR SALGADO JR |
| Low Impact Development | Cleared | 8/31/2018 | RYAN HUDSON |
| Specific Plan | Cleared | 8/31/2018 | TRACY WILLIAMS |
| ZA Case | Cleared | 8/31/2018 | TRACY WILLIAMS |
Contact Information
| Architect | Stockton, Kenneth; Lic. No.: C19870 | 26500 W AGOURA RD. PMB # 844 CALABASAS, CA 91302 |
| Contractor | Cobalt Construction Company; Lic. No.: 369903-B | 2259 WARD AVENUE SUITE 200 SIMI VALLEY, CA 93065 |
| Engineer | Choi, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
| Engineer | Walter, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 1/14/2019 | Partial Approval | DANIEL VARNUM |
| Insulation | 1/18/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 1/23/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 1/25/2019 | Partial Approval | DANIEL VARNUM |
| Insulation | 1/28/2019 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 1/30/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 1/31/2019 | Not Ready for Inspection | DANIEL VARNUM |
| Insulation | 1/31/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 2/5/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/11/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 2/13/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 2/13/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 2/13/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/15/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Insulation | 2/15/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/20/2019 | Partial Approval | DANNY RODRIGUEZ |
| Wood Frame | 2/20/2019 | Not Ready for Inspection | DANNY RODRIGUEZ |
| Drywall Nailing | 2/21/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 2/21/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 2/21/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/22/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 2/22/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Wood Frame | 2/22/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Drywall Nailing | 2/25/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 2/25/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/26/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 2/26/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 2/27/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 2/28/2019 | Partial Approval | ALAN NOVAK |
| Light Gage Steel Frame | 2/28/2019 | Partial Approval | ALAN NOVAK |
| Drywall Nailing | 3/4/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 3/4/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Insulation | 3/4/2019 | Partial Approval | JEFFREY DURAN |
| Interior/Exterior Lathing | 3/4/2019 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 3/4/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Drywall Nailing | 3/6/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 3/6/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 3/6/2019 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 3/6/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 3/7/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 3/7/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 3/8/2019 | Conditional Approval | CAMERON CHABAN |
| Insulation | 3/8/2019 | Not Ready for Inspection | CAMERON CHABAN |
| Interior/Exterior Lathing | 3/8/2019 | Conditional Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 3/8/2019 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 3/8/2019 | Not Ready for Inspection | CAMERON CHABAN |
| Drywall Nailing | 3/12/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 3/12/2019 | Partial Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 3/12/2019 | Conditional Approval | JEFFREY DURAN |
| Drywall Nailing | 3/13/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 3/13/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 3/14/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 3/14/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Light Gage Steel Frame | 3/14/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 3/18/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 3/18/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 3/18/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Drywall Nailing | 3/20/2019 | Partial Approval | ROBERT COLE |
| Insulation | 3/20/2019 | Partial Approval | ROBERT COLE |
| Light Gage Steel Frame | 3/20/2019 | Partial Approval | ROBERT COLE |
| Wood Frame | 3/20/2019 | Not Ready for Inspection | ROBERT COLE |
| Drywall Nailing | 3/21/2019 | Conditional Approval | CAMERON CHABAN |
| Insulation | 3/21/2019 | Conditional Approval | CAMERON CHABAN |
| Masonry Wall/Backfill | 3/21/2019 | Conditional Approval | CAMERON CHABAN |
| Interior/Exterior Lathing | 3/22/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 3/27/2019 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 3/27/2019 | Partial Approval | ROBERT COLE |
| Insulation | 3/27/2019 | Partial Inspection | ROBERT COLE |
| Interior/Exterior Lathing | 3/27/2019 | Conditional Approval | CAMERON CHABAN |
| Interior/Exterior Lathing | 3/27/2019 | Partial Inspection | ROBERT COLE |
| Wood Frame | 3/27/2019 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 3/27/2019 | Not Ready for Inspection | ROBERT COLE |
| Drywall Nailing | 3/29/2019 | Partial Approval | ROBERT COLE |
| Interior/Exterior Lathing | 3/29/2019 | Partial Approval | ROBERT COLE |
| Light Gage Steel Frame | 3/29/2019 | Not Ready for Inspection | ROBERT COLE |
| Drywall Nailing | 4/1/2019 | Partial Approval | ROBERT COLE |
| Insulation | 4/1/2019 | Not Ready for Inspection | ROBERT COLE |
| Drywall Nailing | 4/2/2019 | Partial Approval | DANIEL VARNUM |
| Masonry Wall/Backfill | 4/2/2019 | Conditional Approval | DANIEL VARNUM |
| Drywall Nailing | 4/3/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Light Gage Steel Frame | 4/3/2019 | Corrections Issued | JEFFREY DURAN |
| Wood Frame | 4/3/2019 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 4/4/2019 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 4/5/2019 | Partial Approval | DANIEL VARNUM |
| Masonry Wall/Backfill | 4/5/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 4/8/2019 | Not Ready for Inspection | CAMERON CHABAN |
| Insulation | 4/8/2019 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 4/9/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 4/10/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 4/10/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 4/10/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 4/12/2019 | Partial Inspection | DANIEL VARNUM |
| Insulation | 4/12/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 4/15/2019 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2019 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/16/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 4/17/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 4/17/2019 | Partial Approval | JEFFREY DURAN |
| Interior/Exterior Lathing | 4/17/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 4/19/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 4/19/2019 | Partial Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 4/19/2019 | Partial Approval | JEFFREY DURAN |
| T-Bar Ceiling | 4/19/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 4/22/2019 | Partial Approval | DANIEL VARNUM |
| Insulation | 4/22/2019 | Not Ready for Inspection | DANIEL VARNUM |
| Drywall Nailing | 4/23/2019 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/24/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 4/25/2019 | Partial Approval | DANIEL VARNUM |
| Interior/Exterior Lathing | 4/29/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 4/30/2019 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2019 | Approved | DANIEL VARNUM |
| Drywall Nailing | 5/2/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 5/6/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 5/8/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 5/9/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Drywall Nailing | 5/16/2019 | Partial Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 5/22/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 5/22/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 5/23/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 5/23/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 5/28/2019 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 5/28/2019 | Partial Approval | DANIEL VARNUM |
| Wood Frame | 5/29/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 5/30/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 6/4/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 6/6/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Insulation | 6/6/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 6/10/2019 | Not Ready for Inspection | JEFFREY DURAN |
| Insulation | 6/10/2019 | Partial Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 6/10/2019 | Partial Approval | JEFFREY DURAN |
| Insulation | 6/12/2019 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 6/12/2019 | Partial Approval | DANIEL VARNUM |
| T-Bar Ceiling | 6/13/2019 | Partial Approval | JEFFREY DURAN |
| Wood Frame | 6/13/2019 | Partial Inspection | JEFFREY DURAN |
| Drywall Nailing | 6/17/2019 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 6/18/2019 | Not Ready for Inspection | DANIEL VARNUM |
| Drywall Nailing | 6/21/2019 | Partial Approval | ROBERT COLE |
| Drywall Nailing | 6/24/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 6/26/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 6/27/2019 | Partial Approval | JEFFREY DURAN |
| Interior/Exterior Lathing | 7/8/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 7/15/2019 | Partial Approval | MILLARD ARDOIN |
| Drywall Nailing | 8/1/2019 | Partial Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 8/1/2019 | Partial Approval | JEFFREY DURAN |
| Drywall Nailing | 8/5/2019 | Partial Approval | JEFFREY DURAN |
| Pre-Inspection | 10/3/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 10/4/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 10/8/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 10/10/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 10/15/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 10/17/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 10/22/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 10/24/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 10/28/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 10/29/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 10/30/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 10/31/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 11/4/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 11/5/2019 | Partial Inspection | ROBERT COLE |
| Special/Order Compliance | 11/6/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 11/13/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 11/18/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 11/20/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 11/21/2019 | Partial Approval | ROBERT COLE |
| Special/Order Compliance | 12/2/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 12/3/2019 | Partial Approval | JEFFREY DURAN |
| Final | 12/4/2019 | Partial Inspection | JEFFREY DURAN |
| Special/Order Compliance | 12/10/2019 | Partial Approval | JEFFREY DURAN |
| Special/Order Compliance | 12/17/2019 | Approved | JEFFREY DURAN |
| Final | 12/27/2019 | Permit Finaled | JEFFREY DURAN |