4121 W SANTA MONICA BLVD 90029
Certificate Information: 4121 W SANTA MONICA BLVD 90029
- Application / Permit
- 15010-10006-03531
- Plan Check / Job No.
- B19LA11507
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (5) Apartment
- Work Description
- SUPPLEMENTAL TO PERMIT # 15010-10000-03531 TO REVISE THE PLANS: T.I . TO RETAIL LEVEL IMPROVEMENTS TO INCLUDE, RELOCATING EXTERIOR WALLS & STOREFRONT & ALLOCATING NEW SQUARE FOOTAGE BUT REDUCING OVERALL RETAIL S.F ,RELOCATING RESIDENTIAL EGRESS STAIR 01 AT RETAIL LEVEL ONLY. RELOCATE BICYCLE PARKING AT P1 LEVEL. OMIT COURTESY STAIR 04 FROM RESIDENTIAL LEVEL TO RETAIL LEVEL.
- Permit Issued
- Issued on 9/26/2019
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | GARO TELMI |
| Corrections Issued | 6/17/2019 | GARO TELMI |
| Quality Review Completed | 6/20/2019 | CHAD DOI |
| Building Plans Picked Up | 6/24/2019 | APPLICANT |
| Applicant returned to address corrections | 7/1/2019 | GARO TELMI |
| Plan Check Approved | 9/24/2019 | GARO TELMI |
| Issued | 9/26/2019 | LADBS |
| Permit Finaled | 2/20/2020 | DANIEL MC AULIFFE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 7/25/2019 | GEORGE SUCHAND |
| "D" conditions | Cleared | 7/29/2019 | RICHARD REASER |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/29/2019 | ERIK BEASLEY |
| ZA Case | Cleared | 7/29/2019 | RICHARD REASER |
| DAS Clearance | Cleared | 7/31/2019 | GARO TELMI |
| Green Code | Cleared | 7/31/2019 | GARO TELMI |
| Low Impact Development | Cleared | 8/1/2019 | ORVAL HERNANDEZ-MARCI |
| Fire Marshall Fire Life Safety | Cleared | 9/24/2019 | PEJMAN NOORI |
Contact Information
| Architect | Shubin, Russell James; Lic. No.: C19250 | 3834 WILLAT AVENUE CULVER CITY, CA 90232 |
| Contractor | Owner-Builder | , |
Inspector Information
| RONALD JIMENEZ, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN YAKUBYAN, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN QUACH, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 2/20/2020 | Permit Finaled | DANIEL MC AULIFFE |
| Footing/Foundation/Slab | 2/20/2020 | Approved | DANIEL MC AULIFFE |
| Reinforced Concrete Frame | 2/20/2020 | Approved | DANIEL MC AULIFFE |
| Smoke Detectors | 2/20/2020 | Approved | DANIEL MC AULIFFE |
| Wood Frame | 2/20/2020 | Approved | DANIEL MC AULIFFE |