4121 W SANTA MONICA BLVD 90029

Certificate Information: 4121 W SANTA MONICA BLVD 90029

Application / Permit
15010-10003-03531
Plan Check / Job No.
B18LA06231
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
SUPPLEMENTAL TO PERMIT#15010-10000-03531 TO REVISE PLANS . ADDITION OF 2 NEW LEVELS OF TYPE III-A , 41 UNITS APARTMENT ( TOC, TIER 3) ABOVE (E) 2 STORY RETAIL & PARKING OVER ONE LEVEL SUBTERRANEAN PARKING GARAGE & CHANGE OF USE OF ONE (E) RETAIL & CHANGE OF LAYOT OF (E) 2ND FLOOR RETAIL . (TOC)
Permit Issued
Issued on 8/23/2018
Issuing Office
Metro
Current Status
Permit Finaled on 2/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/30/2018 APPLICANT
Assigned to Plan Check Engineer 4/12/2018 GARO TELMI
Green Plans Picked Up 4/17/2018 APPLICANT
Corrections Issued 4/25/2018 GARO TELMI
Quality Review Completed 4/25/2018 JOHN FRANCIA
Building Plans Picked Up 4/30/2018 APPLICANT
Disabled Access Plans Picked Up 5/3/2018 APPLICANT
Applicant returned to address corrections 5/16/2018 GARO TELMI
Applicant returned to address corrections 5/17/2018 GARO TELMI
Applicant returned to address corrections 5/31/2018 GARO TELMI
Applicant returned to address corrections 6/11/2018 GARO TELMI
Applicant returned to address corrections 6/18/2018 GARO TELMI
Plan Check Approved 8/22/2018 GARO TELMI
Issued 8/23/2018 LADBS
Permit Finaled 2/20/2020 DANIEL MC AULIFFE

Permit Application Clearance Information

Address approval Cleared 4/24/2018 MICHAEL CASTILLO
Highway dedication Cleared 4/24/2018 MICHAEL CASTILLO
Permit Cleared 4/24/2018 MICHAEL CASTILLO
Encroachment in public way Cleared 5/11/2018 FATIMA GUERRA
Comm Cor/Mini-Mall Cleared 5/14/2018 SOPHIE GABEL-SCHEINBAU
Comm Cor/Mini-Mall Cleared 5/14/2018 SOPHIE GABEL-SCHEINBAU
Miscellaneous Cleared 5/14/2018 NORALI MARTINEZ
ZA Case Cleared 5/14/2018 SOPHIE GABEL-SCHEINBAU
ZI Cleared 5/14/2018 SOPHIE GABEL-SCHEINBAU
Eng Process Fee Ord 176,300 Cleared 5/22/2018 PAMELA TENEZA
Hydrant and Access approval Cleared 5/22/2018 JOHN CONNEALLY
Sewer availability Cleared 5/22/2018 PAMELA TENEZA
Driveway location Cleared 5/23/2018 JOHNATHAN YU
Internal circulation Cleared 5/23/2018 JOHNATHAN YU
Miscellaneous Cleared 6/6/2018 ZEMAMU GEBREWOLD
Building over 3-story or 36-ft Cleared 6/14/2018 CALOSHA APPROVED
Flood clearance Cleared 6/14/2018 SYLVIA DHIMDIS
Grading Pre-Inspection Cleared 6/14/2018 BARTON HOLMES
Green Code Cleared 6/21/2018 COLIN LOREDO
Low Impact Development Cleared 6/21/2018 MITESH PATEL
Roof/Waste drainage to street Cleared 6/21/2018 STEVE MELGAR
Stormwater Pollution Mitigatn Cleared 6/21/2018 MITESH PATEL
DCP conditions approval Cleared 7/27/2018 KENNETH LE
Density Bonus 12.22.A.31 Cleared 7/27/2018 KENNETH LE
DAS Clearance Cleared 8/1/2018 EDDIE GARIN
"D" conditions Cleared 8/3/2018 DANALYNN DOMINGUEZ
Fire Marshall Fire Life Safety Cleared 8/22/2018 PEJMAN NOORI

Contact Information

Architect Shubin, Russell James; Lic. No.: C19250 3834 WILLAT AVENUE      CULVER CITY, CA 90232
Contractor Owner-Builder       ,
Engineer Funk, David Lyle; Lic. No.: S5421 619 BERYL ST      REDONDO BEACH, CA 90277
Engineer Knur, Reinard Thomas; Lic. No.: GE2755 1435 MONCADO DR      GLENDALE, CA 91207

Inspector Information

DAVID BURKHEAD, (213) 482-7294 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 8/24/2018 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 8/24/2018 Partial Approval TED RIES
Green Building Rough 8/24/2018 Not Ready for Inspection TED RIES
Reinforced Concrete Frame 8/24/2018 Partial Approval TED RIES
Deputy Reinf. Concrete 8/28/2018 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 8/29/2018 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 8/29/2018 Partial Approval TED RIES
Footing/Foundation/Slab 8/29/2018 Partial Approval TED RIES
Deputy Reinf. Concrete 8/30/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 8/31/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/4/2018 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 9/4/2018 Partial Approval TED RIES
Footing/Foundation/Slab 9/4/2018 Partial Approval TED RIES
Deputy Reinf. Concrete 9/5/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/6/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/7/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/12/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/13/2018 Approved TED RIES
Deputy Steel/Welding 9/13/2018 Approved TED RIES
Deputy Reinf. Concrete 9/14/2018 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 9/14/2018 Partial Approval TED RIES
Deputy Reinf. Concrete 9/18/2018 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 9/18/2018 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 9/19/2018 Approved JEFF BYTHEWAY
Deputy Shotcrete 9/19/2018 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 9/20/2018 Conditional Approval TED RIES
Deputy Reinf. Concrete 9/21/2018 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 10/4/2018 Partial Approval TED RIES
Deputy Reinf. Concrete 10/10/2018 Approved TED RIES
Deputy Reinf. Concrete 10/30/2018 Approved TED RIES
Excavation/Setback/Form/Re-Bar 10/30/2018 Not Ready for Inspection TED RIES
Deputy Reinf. Concrete 10/31/2018 Approved TED RIES
Deputy Reinf. Concrete 11/1/2018 Approved TED RIES
Excavation/Setback/Form/Re-Bar 11/2/2018 Partial Approval TED RIES
Deputy Reinf. Concrete 11/5/2018 Approved TED RIES
Deputy Wood Construction 12/28/2018 Approved TED RIES
Floor/Roof Diaphrgm/Shear Wall 12/28/2018 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 1/3/2019 Partial Inspection TED RIES
Floor/Roof Diaphrgm/Shear Wall 2/1/2019 Corrections Issued TED RIES
Deputy Wood Construction 2/8/2019 Approved JEFF BYTHEWAY
Wall Anchors 2/8/2019 Partial Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 2/20/2019 Partial Approval TED RIES
Green Building Rough 2/25/2019 Not Ready for Inspection JEFF BYTHEWAY
Wood Frame 2/25/2019 Partial Approval JEFF BYTHEWAY
Deputy Wood Construction 2/26/2019 Approved TED RIES
Floor/Roof Diaphrgm/Shear Wall 2/26/2019 Partial Approval TED RIES
Deputy Wood Construction 2/27/2019 Approved TED RIES
Deputy Wood Construction 2/28/2019 Approved TED RIES
Deputy Wood Construction 3/1/2019 Approved TED RIES
Deputy Wood Construction 3/5/2019 Approved TED RIES
Wood Frame 3/5/2019 Partial Approval TED RIES
Deputy Wood Construction 3/6/2019 Approved TED RIES
Deputy Wood Construction 3/7/2019 No Access for Inspection TED RIES
Deputy Wood Construction 3/8/2019 Conditional Approval TED RIES
Deputy Wood Construction 3/11/2019 Conditional Approval TED RIES
Floor/Roof Diaphrgm/Shear Wall 3/11/2019 Partial Approval TED RIES
Deputy Wood Construction 3/12/2019 Approved TED RIES
Deputy Wood Construction 3/13/2019 Approved TED RIES
Deputy Wood Construction 3/14/2019 Approved TED RIES
Deputy Wood Construction 3/15/2019 Approved TED RIES
Wood Frame 3/19/2019 Partial Inspection TED RIES
Deputy Wood Construction 3/20/2019 Approved TED RIES
Special/Order Compliance 3/20/2019 Approved JEFF BYTHEWAY
Wood Frame 3/20/2019 Partial Approval TED RIES
Insulation 3/26/2019 Partial Approval TED RIES
Deputy Wood Construction 3/28/2019 Approved JEFF BYTHEWAY
Deputy Wood Construction 3/29/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 4/1/2019 Approved JEFF BYTHEWAY
Deputy Steel/Welding 4/2/2019 Conditional Approval LESLIE TRUJILLO
Wood Frame 4/2/2019 Partial Approval LESLIE TRUJILLO
Deputy Steel/Welding 4/3/2019 Approved TED RIES
Wood Frame 4/5/2019 Partial Approval TED RIES
Insulation 4/10/2019 Partial Approval TED RIES
Wood Frame 4/10/2019 Partial Approval TED RIES
Insulation 4/17/2019 Partial Approval TED RIES
Wood Frame 4/17/2019 Partial Approval TED RIES
Green Building Rough 4/23/2019 Approved TED RIES
Structural Steel Frame 4/23/2019 Partial Approval TED RIES
Drywall Nailing 5/7/2019 Partial Approval TED RIES
Drywall Nailing 5/22/2019 Partial Approval TED RIES
Interior/Exterior Lathing 5/28/2019 Partial Approval TED RIES
Pre-Inspection 7/1/2019 Partial Inspection DANIEL MC AULIFFE
Pre-Inspection 7/3/2019 Partial Inspection DANIEL MC AULIFFE
Deputy Drilled-In Anchors 8/6/2019 Approved DANIEL MC AULIFFE
Light Gage Steel Frame 8/6/2019 Not Ready for Inspection DANIEL MC AULIFFE
Deputy Drilled-In Anchors 8/15/2019 Approved JEFF BYTHEWAY
Light Gage Steel Frame 8/16/2019 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 8/22/2019 Conditional Approval DANIEL MC AULIFFE
Pre-Inspection 8/27/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 9/5/2019 Partial Inspection DANIEL MC AULIFFE
Structural Steel Frame 9/26/2019 Not Ready for Inspection DANIEL MC AULIFFE
Light Gage Steel Frame 9/27/2019 Partial Approval DANIEL MC AULIFFE
Drywall Nailing 10/3/2019 Partial Approval DANIEL MC AULIFFE
Light Gage Steel Frame 10/8/2019 Partial Inspection DANIEL MC AULIFFE
Light Gage Steel Frame 10/16/2019 Partial Inspection DANIEL MC AULIFFE
Drywall Nailing 11/8/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 11/18/2019 Partial Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/19/2019 Conditional Approval DANIEL MC AULIFFE
Deputy Reinf. Concrete 11/20/2019 Approved DANIEL MC AULIFFE
Light Gage Steel Frame 11/27/2019 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 12/3/2019 Partial Approval DANIEL MC AULIFFE
Footing/Foundation/Slab 12/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Green Building Final 12/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Concrete Frame 12/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Reinforced Masonry Frame 12/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Smoke Detectors 12/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Structural Steel Frame 12/5/2019 Not Ready for Inspection DANIEL MC AULIFFE
Final 12/9/2019 Not Ready for Inspection DANIEL MC AULIFFE
Pre-Inspection 12/10/2019 Partial Inspection DANIEL MC AULIFFE
Final 2/20/2020 Permit Finaled DANIEL MC AULIFFE
Footing/Foundation/Slab 2/20/2020 Approved DANIEL MC AULIFFE
Green Building Final 2/20/2020 Approved DANIEL MC AULIFFE
Reinforced Concrete Frame 2/20/2020 Approved DANIEL MC AULIFFE
Reinforced Masonry Frame 2/20/2020 Approved DANIEL MC AULIFFE
Smoke Detectors 2/20/2020 Approved DANIEL MC AULIFFE
Structural Steel Frame 2/20/2020 Approved DANIEL MC AULIFFE