1324 N QUINTERO ST 90026
Certificate Information: 1324 N QUINTERO ST 90026
- Application / Permit
- 15010-10001-04644
- Plan Check / Job No.
- B16LA15345
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT FOR EARLY START - FOUNDATION ONLY PERMIT. <PLAN CHECK FEES PAID UNDER 15010-10000-04644>
- Permit Issued
- Issued on 10/17/2016
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 8/2/2019
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/13/2016 | APPLICANT |
| Plan Check Approved | 10/17/2016 | LAWRENCE QUIRANTE |
| Issued | 10/17/2016 | LADBS |
| Permit Finaled | 8/2/2019 | SCOTT FINNILA |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/11/2016 | JOHNNY KAZARIAN |
| Green Code | Cleared | 1/11/2016 | JOHN KLARIN |
| Permit | Cleared | 10/5/2016 | CARLOS CUEVA |
| Roof/Waste drainage to street | Cleared | 10/5/2016 | CARLOS CUEVA |
| Miscellaneous | Cleared | 10/11/2016 | CARLOS CUEVA |
| Tract Map conditions | Cleared | 10/11/2016 | ERIC CLAROS |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2016 | ROCHELLE DUNGCA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lothrop, Shawn Duane; Lic. No.: S5627 | 29970 TECHNOLOGY DRIVE SUITE 212 MURRIETA, CA 92563 |
| Engineer | Wert, David Charles; Lic. No.: C46901 | 1599 HIGHWAY 100 PACIFIC, MO 63069 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 11/8/2016 | Corrections Issued | SCOTT FINNILA |
| Deputy Reinf. Concrete | 11/9/2016 | Partial Approval | SCOTT FINNILA |
| Piling/Pier/Caisson | 11/14/2016 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/30/2016 | Partial Approval | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/2/2016 | Partial Approval | SCOTT FINNILA |
| Piling/Pier/Caisson | 12/2/2016 | Partial Approval | SCOTT FINNILA |
| Structural Steel Frame | 12/8/2016 | Corrections Issued | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2016 | Not Ready for Inspection | SCOTT FINNILA |
| Green Building Rough | 12/13/2016 | Not Ready for Inspection | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 12/13/2016 | Not Ready for Inspection | SCOTT FINNILA |
| Wood Frame | 12/13/2016 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 6/27/2017 | Partial Inspection | SCOTT FINNILA |
| Excavation/Setback/Form/Re-Bar | 12/14/2017 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 12/15/2017 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 4/10/2019 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/10/2019 | Approved | SCOTT FINNILA |
| Green Building Final | 4/10/2019 | Approved | SCOTT FINNILA |
| Green Building Rough | 4/10/2019 | Approved | SCOTT FINNILA |
| Smoke Detectors | 4/10/2019 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 4/10/2019 | Approved | SCOTT FINNILA |
| Wood Frame | 4/10/2019 | Approved | SCOTT FINNILA |
| Final | 7/26/2019 | Partial Approval | SCOTT FINNILA |
| Final | 8/2/2019 | Permit Finaled | SCOTT FINNILA |