8839 W HOLLYWOOD BLVD 90069

Certificate Information: 8839 W HOLLYWOOD BLVD 90069

Application / Permit
15010-10001-03614
Plan Check / Job No.
B18LA24830
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental To 15010-10000-03614. Revise retaining wall and pile details.
Permit Issued
Issued on 1/16/2019
Issuing Office
Metro
Current Status
Permit Finaled on 12/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/16/2018 APPLICANT
Assigned to Plan Check Engineer 11/16/2018 DEAN RYAN REYES
Corrections Issued 11/20/2018 DEAN RYAN REYES
Applicant returned to address corrections 12/18/2018 DEAN RYAN REYES
Plan Check Approved 1/16/2019 DEAN RYAN REYES
Issued 1/16/2019 LADBS
Permit Finaled 12/11/2025 SCOTT FINNILA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Abrahamian, Zaven; Lic. No.: C41672 237 S LAMER ST      BURBANK, CA 91506
Engineer Martirossyan, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/3/2019 Partial Approval RAUL BARAJAS
Deputy Steel/Welding 7/10/2019 Approved RAUL BARAJAS
Deputy Steel/Welding 7/11/2019 Approved RAUL BARAJAS
Deputy Steel/Welding 7/12/2019 Approved RAUL BARAJAS
Deputy Steel/Welding 7/16/2019 Approved RAUL BARAJAS
Deputy Steel/Welding 7/17/2019 Approved RAUL BARAJAS
Reinforced Concrete Frame 9/25/2019 Corrections Issued RAUL BARAJAS
Deputy Shotcrete 9/30/2019 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 10/7/2019 Partial Inspection RAUL BARAJAS
Deputy Reinf. Concrete 1/15/2020 Conditional Approval RAUL BARAJAS
Deputy Reinf. Concrete 3/17/2020 No Access for Inspection RAUL BARAJAS
Footing/Foundation/Slab 7/30/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 8/19/2020 Partial Inspection RAUL BARAJAS
Footing/Foundation/Slab 9/17/2020 No Access for Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 9/18/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 10/7/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 11/17/2020 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 12/29/2020 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 1/7/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 1/13/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 1/15/2021 Not Ready for Inspection RAUL BARAJAS
Footing/Foundation/Slab 1/20/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 2/2/2021 Corrections Issued RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/3/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 2/4/2021 Not Ready for Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/9/2021 Partial Inspection RAUL BARAJAS
Deputy Steel/Welding 3/17/2021 Conditional Approval THOMAS LOGRASSO
Final 3/11/2024 Not Ready for Inspection RAUL BARAJAS
Final 12/11/2025 Permit Finaled SCOTT FINNILA