5244 W SANCHEZ DR 90008
Certificate Information: 5244 W SANCHEZ DR 90008
- Application / Permit
- 15010-10000-04558
- Plan Check / Job No.
- B15LA17745
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Construction of a (N) two-story Single Family Dwelling with basement per ZA-2017-4794-ZAA.
- Permit Issued
- Issued on 2/11/2019
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 6/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2016 | CHRISTOPHER KOMANCHECK |
| Corrections Issued | 2/1/2016 | CHRISTOPHER KOMANCHECK |
| Green Plans Picked Up | 2/10/2016 | APPLICANT |
| Quality Review Completed | 2/17/2016 | KESETE HAREGOT |
| Building Plans Picked Up | 2/26/2016 | APPLICANT |
| Applicant returned to address corrections | 8/27/2018 | CHRISTOPHER KOMANCHECK |
| Plan Check Approved | 12/27/2018 | CHRISTOPHER KOMANCHECK |
| Issued | 2/11/2019 | LADBS |
| CofO in Progress | 5/13/2022 | ANTHONY EGSON |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
| CofO Issued | 6/23/2022 | DEROLD HAUFF |
| Permit Finaled | 6/23/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/28/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 11/28/2018 | MICHAEL CASTILLO |
| Hydrant and Access approval | Cleared | 12/12/2018 | GEORGE SUCHAND |
| Green Code | Cleared | 12/14/2018 | ROLLIN GETTLE III |
| Roof/Waste drainage to street | Cleared | 12/14/2018 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/14/2018 | ADRIAN SANCHEZ |
| ZA Case | Cleared | 12/14/2018 | DIANA JIMENEZ |
| Low Impact Development | Cleared | 12/17/2018 | JORGE MEJIA LEMUS |
Contact Information
| Architect | Wolen, Deborah Suzanne; Lic. No.: C29672 | 339 S ROBERTSON BLVD SUITE 103 BEVERLY HILLS, CA 90211 |
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
| Engineer | Robinson, Rory Anthony; Lic. No.: GE2491 | 963 EAST SANTA CLARA ST VENTURA, CA 93001 |
| Geologist | Robinson, Rory Anthony; Lic. No.: EG1902 | 963 EAST SANTA CLARA STREET VENTURA, CA 93001 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/11/2020 | Approved | COREY HUPP |
| Pre-Inspection | 7/17/2020 | Partial Inspection | COREY HUPP |
| Deputy Drilled-In Anchors | 9/2/2020 | Conditional Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 11/6/2020 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 11/13/2020 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 11/25/2020 | Partial Approval | DAVID FEILER |
| Green Building Rough | 11/25/2020 | Not Ready for Inspection | DAVID FEILER |
| Reinforced Concrete Frame | 11/25/2020 | Partial Approval | DAVID FEILER |
| Verify Sprinkler Sign Off | 11/25/2020 | Not Ready for Inspection | DAVID FEILER |
| Footing/Foundation/Slab | 1/6/2021 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 1/22/2021 | Corrections Issued | DAVID FEILER |
| Wood Frame | 1/27/2021 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 2/11/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2021 | Partial Approval | DAVID FEILER |
| Sewer | 4/6/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 5/6/2021 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 5/6/2021 | Partial Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2021 | Partial Approval | DAVID FEILER |
| Green Building Rough | 5/6/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 5/6/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 5/6/2021 | Partial Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 5/6/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 5/6/2021 | Partial Approval | DAVID FEILER |
| Deputy Wood Construction | 5/7/2021 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 5/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 5/7/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/7/2021 | Approved | FREDDIE RIVERA |
| Sewer | 5/7/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/14/2021 | Approved | DAVID FEILER |
| Gas Test | 5/14/2021 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 5/14/2021 | Partial Inspection | DAVID FEILER |
| Wood Frame | 5/14/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 5/17/2021 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 6/11/2021 | Approved | DAVID FEILER |
| Green Building Rough | 6/11/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 6/11/2021 | Partial Approval | DAVID FEILER |
| Verify Sprinkler Sign Off | 6/11/2021 | Approved | DAVID FEILER |
| Insulation | 6/17/2021 | Approved | DAVID FEILER |
| Drywall Nailing | 7/6/2021 | Approved | CALEB MEISTER |
| Shower Pan | 7/6/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 7/14/2021 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/24/2021 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 12/30/2021 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/30/2021 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 12/30/2021 | Approved | ANTHONY EGSON |
| HVAC-Final | 1/10/2022 | Approved | ANTHONY EGSON |
| Service/Power Release | 1/10/2022 | Approved | ANTHONY EGSON |
| Gas Test | 1/19/2022 | Approved | ANTHONY EGSON |
| Final | 1/25/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 1/25/2022 | Approved | ANTHONY EGSON |
| Green Building Final | 1/25/2022 | Approved | ANTHONY EGSON |
| Reinforced Concrete Frame | 1/25/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/25/2022 | Approved | ANTHONY EGSON |
| Final | 1/27/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 2/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Service/Power Release | 2/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 5/10/2022 | OK to Issue CofO | ANTHONY EGSON |