8856 W SKYLINE DR 90046

Certificate Information: 8856 W SKYLINE DR 90046

Application / Permit
15010-10000-04457
Plan Check / Job No.
B15LA17157
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 3/3/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 4/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2015 APPLICANT
Assigned to Plan Check Engineer 1/21/2016 MANUEL GARCIA
Green Plans Picked Up 1/21/2016 APPLICANT
Corrections Issued 1/29/2016 MANUEL GARCIA
Quality Review Completed 2/10/2016 GARO TELMI
Building Plans Picked Up 2/12/2016 APPLICANT
Applicant returned to address corrections 9/12/2016 MANUEL GARCIA
Applicant returned to address corrections 9/29/2016 MANUEL GARCIA
Applicant returned to address corrections 10/13/2016 MANUEL GARCIA
Applicant returned to address corrections 10/28/2016 MANUEL GARCIA
Plan Check Approved 3/3/2017 MANUEL GARCIA
Issued 3/3/2017 LADBS
CofO in Progress 4/4/2023 RAUL BARAJAS
Permit Finaled 4/7/2023 RONALD MYRICK
CofO Issued 4/7/2023 RONALD MYRICK
Permit Finaled 4/7/2023 RONALD MYRICK

Permit Application Clearance Information

Work Adjacent to Public Way Cleared 9/12/2016 HUGO RICO
Green Code Cleared 9/28/2016 JOHN KLARIN
Address approval Cleared 10/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 10/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 10/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 10/4/2016 RAVIL MANAPOV
Eng Process Fee Ord 176,300 Cleared 10/4/2016 RAVIL MANAPOV
Hydrant and Access approval Cleared 10/4/2016 ROBERT DUFF
Low Impact Development Cleared 10/4/2016 SAM NAVID
Permit Cleared 10/4/2016 RAVIL MANAPOV
Roof/Waste drainage to street Cleared 10/4/2016 RAVIL MANAPOV
Sewer availability Cleared 10/4/2016 RAVIL MANAPOV
BHO/Hillside ordinance Cleared 10/5/2016 CHEN ZHANG
GPI Written Notices Cleared 10/28/2016 MANUEL GARCIA
Grading Pre-Inspection Cleared 10/28/2016 MANUEL GARCIA
Miscellaneous Cleared 2/8/2017 TREVOR MARTIN
Specific Plan Cleared 2/8/2017 TREVOR MARTIN

Contact Information

Architect Getov, Pavel Panayotov; Lic. No.: C32093 3565 REDWOOD AVENUE      LOS ANGELES, CA 90066
Contractor Castle Rock Paving Systems; Lic. No.: 462007-A P O BOX 647      SAN PEDRO, CA 90733
Engineer Hollingsworth, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Levitas, Felix; Lic. No.: C62311 14550 HAYNES ST STE 300      VAN NUYS, CA 91411
Engineer Resnick, Bruce Daniel; Lic. No.: S3293 1927 PONTIUS AVE      LOS ANGELES, CA 90025
Engineer Roehl, Gary John; Lic. No.: C30826 3914 DEL AMO BLVD STE 921      TORRANCE, CA 90503
Geologist Hollingsworth, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2017 Partial Approval CRAIG VAUGHAN
Masonry Wall/Backfill 11/16/2017 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 6/18/2018 Partial Approval RAUL BARAJAS
Grounding or Bonding 7/17/2018 Not Ready for Inspection RONALD COWAN
Footing/Foundation/Slab 7/19/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 8/22/2018 No Access for Inspection RONALD COWAN
Footing/Foundation/Slab 8/23/2018 Partial Inspection RONALD COWAN
Footing/Foundation/Slab 9/17/2018 Partial Approval RONALD COWAN
Footing/Foundation/Slab 12/27/2018 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/3/2019 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 1/18/2019 Partial Approval RAUL BARAJAS
Footing/Foundation/Slab 2/12/2019 Corrections Issued DANNY TOLENTINO
Footing/Foundation/Slab 2/21/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/2/2019 Partial Approval DANNY TOLENTINO
Special/Order Compliance 5/15/2019 Approved DANNY TOLENTINO
Footing/Foundation/Slab 5/17/2019 Partial Approval DANNY TOLENTINO
Piling/Pier/Caisson 6/7/2019 Partial Approval DANNY TOLENTINO
Deputy Steel/Welding 6/12/2019 No Access for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 6/28/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 7/30/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 9/18/2019 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 12/20/2019 Conditional Approval RAUL BARAJAS
Green Building Rough 12/20/2019 Not Ready for Inspection RAUL BARAJAS
Verify Sprinkler Sign Off 12/20/2019 Not Ready for Inspection RAUL BARAJAS
PLUMBING-Rough 5/12/2020 Partial Approval RAUL BARAJAS
Shower Pan 8/17/2020 Approved RAUL BARAJAS
ELECTRICAL-Rough 9/1/2020 Partial Approval RAUL BARAJAS
HVAC-Rough 9/29/2020 Partial Approval RAUL BARAJAS
Wood Frame 10/19/2020 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 10/29/2020 Corrections Issued RAUL BARAJAS
Green Building Rough 10/29/2020 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 10/29/2020 Approved RAUL BARAJAS
BUILDING-Rough-Frame 12/7/2020 Partial Inspection RAUL BARAJAS
Drywall Nailing 1/11/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 6/8/2021 Corrections Issued RAUL BARAJAS
Pre-Inspection 8/18/2021 Corrections Issued RICHARD STEINBACH
Special/Order Compliance 8/18/2021 Corrections Issued RICHARD STEINBACH
ELECTRICAL-Rough 10/19/2021 Corrections Issued RAUL BARAJAS
Interior/Exterior Lathing 12/1/2021 Approved RAUL BARAJAS
Rough-Elec/Plmb/HVAC 12/1/2021 Corrections Issued RAUL BARAJAS
ELECTRICAL-Rough 12/8/2021 No Access for Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/13/2021 Partial Approval RAUL BARAJAS
Service/Power Release 6/28/2022 Approved RAUL BARAJAS
ELECTRICAL-Final 12/14/2022 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 12/20/2022 Corrections Issued RAUL BARAJAS
Final 12/20/2022 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 12/20/2022 Approved RAUL BARAJAS
Green Building Final 12/20/2022 Approved RAUL BARAJAS
Reinforced Concrete Frame 12/20/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/20/2022 SGSOV Not Ready RAUL BARAJAS
Service/Power Release 12/20/2022 Approved RAUL BARAJAS
Smoke Detectors 12/20/2022 Not Ready for Inspection RAUL BARAJAS
Structural Steel Frame 12/20/2022 Approved RAUL BARAJAS
HVAC-Final 2/21/2023 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/21/2023 SGSOV Approved RAUL BARAJAS
BUILDING-Rough-Frame 4/4/2023 Approved RAUL BARAJAS
Final 4/4/2023 OK to Issue CofO RAUL BARAJAS
Smoke Detectors 4/4/2023 Approved RAUL BARAJAS