11005 W BELLAGIO PL 90077
Certificate Information: 11005 W BELLAGIO PL 90077
- Application / Permit
- 15010-10000-04320
- Plan Check / Job No.
- B15LA16666
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SINGLE FAMILY RESIDENCE with NFPA 13D FIRE SPRINKLERS
- Permit Issued
- Issued on 9/6/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2015 | APPLICANT |
| Green Plans Picked Up | 12/7/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2015 | ERIC CABRERA |
| Corrections Issued | 12/20/2015 | ERIC CABRERA |
| Quality Review Completed | 12/29/2015 | GARO TELMI |
| Building Plans Picked Up | 12/29/2015 | APPLICANT |
| Applicant returned to address corrections | 3/22/2016 | ERIC CABRERA |
| Plan Check Approved | 8/24/2016 | ERIC CABRERA |
| Issued | 9/6/2016 | LADBS |
| CofO in Progress | 4/19/2023 | CARLOS MATAMOROS |
| Permit Finaled | 4/26/2023 | DANIEL ORRANTE |
| CofO Issued | 4/26/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 1/4/2016 | KARAN PATEL |
| BHO/Hillside ordinance | Cleared | 1/4/2016 | KARAN PATEL |
| Highway dedication | Cleared | 1/4/2016 | KARAN PATEL |
| Permit | Cleared | 1/4/2016 | KARAN PATEL |
| Sewer availability | Cleared | 1/4/2016 | KARAN PATEL |
| Work Adjacent to Public Way | Cleared | 1/4/2016 | DAVID PEREZ |
| BHO/Hillside ordinance | Cleared | 1/8/2016 | HUGO RICO |
| BHO/Hillside ordinance | Cleared | 1/8/2016 | HUGO RICO |
| BHO/Hillside ordinance | Cleared | 1/8/2016 | HUGO RICO |
| Highway dedication | Cleared | 1/8/2016 | HUGO RICO |
| Miscellaneous | Cleared | 1/8/2016 | HUGO RICO |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2016 | ARNULFO NUNO |
| Miscellaneous | Cleared | 1/15/2016 | VINCENT QUITORIANO |
| ZI | Cleared | 1/15/2016 | VINCENT QUITORIANO |
| GPI Written Notices | Cleared | 3/22/2016 | ERIC CABRERA |
| Grading Pre-Inspection | Cleared | 3/22/2016 | ERIC CABRERA |
| Green Code | Cleared | 3/24/2016 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 4/12/2016 | MARTIN FRAGOSO |
| Excavation more than 5-ft deep | Cleared | 4/19/2016 | CALOSHA APPROVED |
| Hydrant and Access approval | Cleared | 4/26/2016 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 6/24/2016 | ADRIAN SANCHEZ |
| Construction within easement | Cleared | 9/1/2016 | LUCIO FERRER |
| Permit | Cleared | 9/6/2016 | NIRAV PATEL |
Contact Information
| Contractor | Tyler Development Corporation; Lic. No.: 451882-B | 1932 COTNER AVE LOS ANGELES, CA 90025 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
| Engineer | Peck, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
| Geologist | Hollingsworth, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/14/2017 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/17/2017 | Partial Inspection | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/18/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/19/2017 | Conditional Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 4/19/2017 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/20/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 4/21/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 5/23/2017 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 5/26/2017 | Partial Approval | THOMAS FINNILA |
| Deputy Shotcrete | 6/12/2017 | Conditional Approval | THOMAS FINNILA |
| Reinforced Concrete Frame | 6/13/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Shotcrete | 6/14/2017 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 6/22/2017 | Partial Approval | THOMAS FINNILA |
| Reinforced Concrete Frame | 6/22/2017 | Partial Approval | THOMAS FINNILA |
| Deputy Shotcrete | 6/23/2017 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 7/14/2017 | Partial Approval | THOMAS FINNILA |
| Reinforced Concrete Frame | 7/25/2017 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 8/7/2017 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/12/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/14/2017 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/19/2017 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 9/25/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 9/28/2017 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/4/2017 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/13/2017 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/23/2017 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 10/26/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 10/27/2017 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/7/2017 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 11/9/2017 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/16/2017 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 12/5/2017 | Partial Approval | DANIEL ORRANTE |
| Special/Order Compliance | 12/23/2017 | Partial Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 1/23/2018 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/1/2018 | Partial Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 2/2/2018 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 2/5/2018 | Partial Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 2/7/2018 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/15/2018 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 2/28/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 3/1/2018 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/3/2018 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/4/2018 | Approved | MATT KELLERMAN |
| Deputy Reinf. Concrete | 4/4/2018 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/9/2018 | No Access for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/10/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/11/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/24/2018 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/24/2018 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/2/2018 | Partial Approval | ANTHONY ANDERSON |
| Piling/Pier/Caisson | 5/21/2018 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 5/25/2018 | Partial Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 5/29/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 5/31/2018 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/7/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 6/11/2018 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/13/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/17/2018 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/17/2018 | Not Ready for Inspection | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/23/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/24/2018 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 8/7/2018 | Conditional Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/8/2018 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 8/9/2018 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 9/11/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/12/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Reinf. Concrete | 9/13/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/13/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Piling/Pier/Caisson | 9/13/2018 | Partial Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/14/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/17/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/18/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/19/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/20/2018 | Partial Approval | JOHN LUMB |
| Deputy Steel/Welding | 9/21/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/24/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/25/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/26/2018 | Partial Approval | MATT KELLERMAN |
| Deputy Steel/Welding | 9/27/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 9/28/2018 | Approved | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/1/2018 | Partial Approval | JOHN LUMB |
| Deputy Steel/Welding | 10/2/2018 | Partial Approval | MATT KELLERMAN |
| Deputy Steel/Welding | 10/4/2018 | Partial Approval | MATT KELLERMAN |
| Deputy Steel/Welding | 10/5/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/9/2018 | Approved | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/10/2018 | Partial Approval | MATT KELLERMAN |
| Deputy Steel/Welding | 10/12/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/15/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/16/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/17/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/18/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/19/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/22/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/23/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/24/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/25/2018 | Conditional Approval | MATT KELLERMAN |
| Deputy Steel/Welding | 10/26/2018 | Partial Approval | MATT KELLERMAN |
| Deputy Steel/Welding | 10/29/2018 | Partial Approval | MATT KELLERMAN |
| Deputy Steel/Welding | 10/30/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 10/31/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 11/1/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 11/2/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Footing/Foundation/Slab | 11/5/2018 | Partial Approval | JOEL LAUNCHBAUGH |
| Deputy Wood Construction | 11/9/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Reinf. Concrete | 11/13/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Reinf. Concrete | 11/21/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 11/21/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Wood Construction | 11/30/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2018 | Partial Approval | JOEL LAUNCHBAUGH |
| Deputy Steel/Welding | 12/13/2018 | Conditional Approval | JOEL LAUNCHBAUGH |
| Deputy Wood Construction | 1/8/2019 | Conditional Approval | JOEL LAUNCHBAUGH |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2019 | Partial Approval | JOEL LAUNCHBAUGH |
| Footing/Foundation/Slab | 3/20/2019 | Partial Approval | ANTHONY MCDOWALL |
| HVAC-Rough | 4/11/2019 | Partial Approval | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 5/6/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Footing/Foundation/Slab | 5/6/2019 | Approved | ROBERT SHELLY |
| Green Building Rough | 5/6/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Verify Sprinkler Sign Off | 5/6/2019 | Not Ready for Inspection | ROBERT SHELLY |
| Deputy Reinf. Concrete | 5/7/2019 | Conditional Approval | ANTHONY MCDOWALL |
| Pre-Inspection | 6/14/2019 | Partial Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 6/19/2019 | Partial Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 6/19/2019 | Partial Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 7/2/2019 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Pre-Inspection | 7/22/2019 | Partial Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 9/20/2019 | Partial Approval | MATT KELLERMAN |
| PLUMBING-Rough | 9/27/2019 | Approved | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 10/2/2019 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 10/8/2019 | Partial Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 10/17/2019 | Corrections Issued | ANTHONY MCDOWALL |
| HVAC-Rough | 11/7/2019 | Corrections Issued | ANTHONY MCDOWALL |
| Special/Order Compliance | 11/7/2019 | Approved | MATTHEW NUCKOLLS |
| ELECTRICAL-Rough | 11/12/2019 | Approved | ANTHONY MCDOWALL |
| HVAC-Rough | 11/12/2019 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 11/15/2019 | Approved | ANTHONY MCDOWALL |
| Green Building Rough | 11/15/2019 | Approved | ANTHONY MCDOWALL |
| Insulation | 11/15/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Verify Sprinkler Sign Off | 11/15/2019 | Approved | ANTHONY MCDOWALL |
| Insulation | 12/4/2019 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 12/9/2019 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 12/12/2019 | Approved | ANTHONY MCDOWALL |
| Drywall Nailing | 1/13/2020 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 1/28/2020 | Approved | CARLOS MATAMOROS |
| Shower Pan | 1/31/2020 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 6/22/2020 | Not Required | CARLOS MATAMOROS |
| Service/Power Release | 3/11/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 4/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Service/Power Release | 4/22/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Service/Power Release | 4/26/2021 | Corrections Issued | CARLOS MATAMOROS |
| Service/Power Release | 8/4/2021 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 10/22/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Pool/Spa Cover | 6/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 7/7/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 8/1/2022 | Conditional Approval | PATRICK QUALEY |
| ELECTRICAL-Final | 8/5/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 8/5/2022 | Approved | CARLOS MATAMOROS |
| Gas Test | 8/12/2022 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 8/30/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 8/31/2022 | Conditional Approval | CARLOS MATAMOROS |
| PLUMBING-Final | 9/13/2022 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 10/25/2022 | Approved | CARLOS MATAMOROS |
| Final | 3/31/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 3/31/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/31/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 3/31/2023 | Approved | CARLOS MATAMOROS |
| Final | 4/6/2023 | Partial Approval | CARLOS MATAMOROS |
| Green Building Final | 4/6/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/6/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Final | 4/18/2023 | OK to Issue CofO | CARLOS MATAMOROS |