10842 W VICTORY BLVD 1-6 91606

Certificate Information: 10842 W VICTORY BLVD 1-6 91606

Application / Permit
15010-10000-04022
Plan Check / Job No.
B15LA15608
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 4 STORY TYPE IIIA 6 UNIT APARTMENT BUILDING. "COMPLY WITH DEPARTMENT ORDER effective date 09/11/2012. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 3/9/2018
Issuing Office
Valley
Current Status
CofO Corrected on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2015 APPLICANT
Assigned to Plan Check Engineer 12/10/2015 DOUGLAS NAKATANI
Corrections Issued 1/11/2016 ROSHANAK VARJAVAND
Quality Review Completed 1/25/2016 GARO TELMI
Building Plans Picked Up 1/28/2016 APPLICANT
Green Plans Picked Up 1/28/2016 APPLICANT
Applicant returned to address corrections 6/14/2016 ROSHANAK VARJAVAND
Applicant returned to address corrections 6/23/2016 ROSHANAK VARJAVAND
Applicant returned to address corrections 11/15/2016 ROSHANAK VARJAVAND
Disabled Access Plans Picked Up 2/2/2017 APPLICANT
Applicant returned to address corrections 2/9/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 3/7/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 3/21/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 3/29/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 4/4/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 4/18/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 8/9/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 8/22/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 10/20/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 10/30/2017 ROSHANAK VARJAVAND
Applicant returned to address corrections 1/16/2018 DOUGLAS NAKATANI
Plan Check Approved 1/23/2018 DOUGLAS NAKATANI
Issued 3/9/2018 LADBS
CofO in Progress 2/14/2025 JOHN KITCKO
CofO Issued-Status Void 4/1/2025 RICKEY JACKSON
Permit Finaled-Status Void 4/1/2025 RICKEY JACKSON
Re-Activate Permit 5/28/2025 RICKEY JACKSON
Permit Finaled 5/29/2025 RICKEY JACKSON
CofO Corrected 5/29/2025 RICKEY JACKSON
Permit Finaled 5/29/2025 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 4/19/2016 ROBERT SAMONTE
Hydrant and Access approval Cleared 5/12/2016 JOHN CONNEALLY
Opn space landscape/Water mgmt Cleared 5/12/2016 VINCENT QUITORIANO
ZA Case Cleared 5/12/2016 VINCENT QUITORIANO
ZA Case Cleared 5/12/2016 VINCENT QUITORIANO
Eng Process Fee Ord 176,300 Cleared 5/13/2016 ERIK MUNOZ
Sewer availability Cleared 5/13/2016 ERIK MUNOZ
Roof/Waste drainage to street Cleared 7/19/2016 LEE GUILBEAUX
Driveway location Cleared 4/17/2017 COLLINS ALLAN
Internal circulation Cleared 4/17/2017 COLLINS ALLAN
Low Impact Development Cleared 5/11/2017 MARTIN FRAGOSO
Frnt yard landscape/Water mgmt Cleared 5/12/2017 STEVEN WECHSLER
Miscellaneous Cleared 5/12/2017 STEVEN WECHSLER
Green Code Cleared 6/15/2017 DONALD CRICHLOW
DAS Clearance Cleared 6/16/2017 SHINE LIN
Fire Marshall Fire Life Safety Cleared 10/20/2017 DAVE MYERS
Highway dedication Cleared 11/1/2017 MARKOS PEREZ-BRAN
Permit Cleared 11/6/2017 LEE GUILBEAUX
Building over 3-story or 36-ft Cleared 11/17/2017 CALOSHA APPROVED
Hold Cleared 11/17/2017 CHARLES CHANG

Contact Information

Contractor Owner-Builder       ,
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

DEANDRE HOFFMAN, (818) 374-1182 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2019 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 2/27/2019 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 8/22/2019 Partial Inspection JOHN KITCKO
Footing/Foundation/Slab 2/13/2020 Partial Approval JOHN KITCKO
Footing/Foundation/Slab 3/5/2020 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 3/10/2020 Corrections Issued JOHN KITCKO
Pre-Inspection 3/10/2020 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 3/16/2020 Partial Approval JOHN KITCKO
Pre-Inspection 3/23/2020 Partial Approval JOHN KITCKO
Pre-Inspection 4/27/2020 Partial Approval JOHN KITCKO
Green Building Rough 5/6/2020 Partial Approval JOHN KITCKO
Pre-Inspection 5/6/2020 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 5/6/2020 Not Ready for Inspection JOHN KITCKO
Wood Frame 5/6/2020 Partial Approval JOHN KITCKO
Pre-Inspection 6/2/2020 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 6/4/2020 Partial Inspection JOHN KITCKO
Pre-Inspection 6/23/2020 Partial Approval JOHN KITCKO
Green Building Rough 7/14/2020 Partial Approval JOHN KITCKO
Pre-Inspection 7/14/2020 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 7/14/2020 Not Ready for Inspection JOHN KITCKO
Wood Frame 7/14/2020 Partial Inspection JOHN KITCKO
Pre-Inspection 8/6/2020 Approved HAMID PISHEHVAR
Green Building Rough 8/27/2020 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 8/27/2020 Not Ready for Inspection JOHN KITCKO
Wood Frame 8/27/2020 Not Ready for Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/7/2020 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 2/22/2021 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 2/22/2021 Partial Inspection JOHN KITCKO
Interior/Exterior Lathing 3/17/2021 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 3/17/2021 Corrections Issued JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 3/19/2021 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 5/11/2021 Partial Inspection JOHN KITCKO
Pre-Inspection 5/11/2021 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 5/21/2021 Partial Approval JOHN KITCKO
Pre-Inspection 5/21/2021 Partial Approval JOHN KITCKO
Insulation 6/15/2021 Corrections Issued JOHN KITCKO
Interior/Exterior Lathing 6/15/2021 Partial Approval JOHN KITCKO
Pre-Inspection 6/15/2021 Not Ready for Inspection JOHN KITCKO
Insulation 6/21/2021 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 6/21/2021 Partial Approval JOHN KITCKO
Pre-Inspection 6/21/2021 Corrections Issued JOHN KITCKO
Insulation 7/7/2021 Partial Approval JOHN KITCKO
Pre-Inspection 7/7/2021 Not Ready for Inspection JOHN KITCKO
Green Building Rough 8/4/2021 Partial Approval JOHN KITCKO
Insulation 8/4/2021 Not Ready for Inspection JOHN KITCKO
Interior/Exterior Lathing 8/4/2021 Approved JOHN KITCKO
Pre-Inspection 8/4/2021 Not Ready for Inspection JOHN KITCKO
Verify Sprinkler Sign Off 8/4/2021 Not Ready for Inspection JOHN KITCKO
Wood Frame 8/4/2021 Not Ready for Inspection JOHN KITCKO
Green Building Rough 8/6/2021 Approved JOHN KITCKO
Insulation 8/6/2021 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 8/6/2021 Conditional Approval JOHN KITCKO
Verify Sprinkler Sign Off 8/6/2021 Approved JOHN KITCKO
Wood Frame 8/6/2021 Conditional Approval JOHN KITCKO
Insulation 8/23/2021 Partial Inspection JOHN KITCKO
Pre-Inspection 8/23/2021 Partial Inspection JOHN KITCKO
Drywall Nailing 9/7/2021 No Access for Inspection JOHN KITCKO
Pre-Inspection 9/7/2021 No Access for Inspection JOHN KITCKO
Drywall Nailing 9/9/2021 Not Ready for Inspection JOHN KITCKO
Pre-Inspection 9/9/2021 Not Ready for Inspection JOHN KITCKO
Drywall Nailing 9/14/2021 Partial Approval JOHN KITCKO
Drywall Nailing 10/12/2021 Partial Approval JOHN KITCKO
Drywall Nailing 10/20/2021 Partial Approval JOHN KITCKO
Special/Order Compliance 5/12/2022 Partial Inspection JOHN KITCKO
Pre-Inspection 11/22/2022 Partial Approval JOHN KITCKO
Special/Order Compliance 9/12/2023 No Access for Inspection JOHN KITCKO
Special/Order Compliance 9/14/2023 Partial Inspection JOHN KITCKO
Drywall Nailing 10/2/2024 Approved JOHN KITCKO
Final 10/2/2024 Corrections Issued JOHN KITCKO
Footing/Foundation/Slab 10/2/2024 Approved JOHN KITCKO
Green Building Final 10/2/2024 Not Ready for Inspection JOHN KITCKO
Reinforced Masonry Frame 10/2/2024 Approved JOHN KITCKO
SGSOV-Seismic Gas S/O Valve 10/2/2024 SGSOV Approved JOHN KITCKO
Smoke Detectors 10/2/2024 Approved JOHN KITCKO
Structural Steel Frame 10/2/2024 Approved JOHN KITCKO
Wood Frame 10/2/2024 Approved JOHN KITCKO
Final 10/16/2024 Not Ready for Inspection JOHN KITCKO
Green Building Final 10/16/2024 Not Ready for Inspection JOHN KITCKO
Final 11/15/2024 Not Ready for Inspection JOHN KITCKO
Green Building Final 11/15/2024 Approved JOHN KITCKO
Final 2/14/2025 OK to Issue CofO JOHN KITCKO