846-852 N CORONADO ST 90026

Certificate Information: 846-852 N CORONADO ST 90026

Application / Permit
15010-10000-03972
Plan Check / Job No.
B15LA15492
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3 STORY SINGLE FAMILY DWELLING WITH ATTACHED 2 CAR GARAGE. SMALL LOT SUBDIVISION, LOT 4
Permit Issued
Issued on 4/12/2017
Issuing Office
Metro
Current Status
CofO Issued on 1/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2015 APPLICANT
Assigned to Plan Check Engineer 11/24/2015 GARO TELMI
Corrections Issued 11/30/2015 GARO TELMI
Quality Review Completed 12/7/2015 BILL STUTSMAN
Building Plans Picked Up 12/18/2015 APPLICANT
Green Plans Picked Up 12/18/2015 APPLICANT
Applicant returned to address corrections 1/12/2016 GARO TELMI
Applicant returned to address corrections 1/22/2016 GARO TELMI
Applicant returned to address corrections 12/20/2016 GARO TELMI
Applicant returned to address corrections 3/28/2017 GARO TELMI
Plan Check Approved 4/10/2017 GARO TELMI
Issued 4/12/2017 LADBS
CofO in Progress 12/23/2021 SCOTT FINNILA
Permit Finaled 1/5/2022 RONALD MYRICK
CofO Issued 1/5/2022 RONALD MYRICK
Permit Finaled 1/5/2022 RONALD MYRICK

Permit Application Clearance Information

ZA Case Cleared 12/23/2016 EDBER MACEDO
Eng Process Fee Ord 176,300 Cleared 12/28/2016 CELINA MORENO
Low Impact Development Cleared 12/28/2016 SAM NAVID
Address approval Cleared 1/3/2017 SEVAK ISAKHAYAN
Drainage to Storm Drain Cleared 1/19/2017 ARMENIA AGUILAR
Highway dedication Cleared 1/19/2017 ARMENIA AGUILAR
Miscellaneous Cleared 1/19/2017 ARMENIA AGUILAR
Permit Cleared 1/19/2017 ARMENIA AGUILAR
Roof/Waste drainage to street Cleared 1/19/2017 ARMENIA AGUILAR
Sewer availability Cleared 1/26/2017 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 2/3/2017 GRACIELA ACOSTA
Miscellaneous Cleared 2/3/2017 GRACIELA ACOSTA
Miscellaneous Cleared 2/3/2017 GRACIELA ACOSTA
Tract Map conditions Cleared 2/3/2017 GRACIELA ACOSTA
Work Adjacent to Public Way Cleared 2/28/2017 RAVIL MANAPOV
Construction near power lines Cleared 3/15/2017 WALTER RAMIREZ
Hydrant and Access approval Cleared 3/15/2017 ROBERT DUFF
Green Code Cleared 3/24/2017 DONALD CRICHLOW
Building over 3-story or 36-ft Cleared 4/10/2017 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/10/2017 CALOSHA APPROVED
Grading Pre-Inspection Cleared 4/10/2017 GARO TELMI

Contact Information

Architect Maly, Farzin; Lic. No.: C33731 PO BOX 57002      SHERMAN OAKS, CA 91413
Engineer Carrizosa, Richard Garcia; Lic. No.: C25828 1505 LYNDHURST AVE      HACIENDA HEIGHTS, CA 917452932
Engineer Irvine, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD      PASADENA, CA 91107
Engineer Khedekar, Avinash Rameshchandr; Lic. No.: S1982 21930 MARYLEE ST 104      WOODLAND HILLS, CA 91367

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/30/2017 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 11/13/2017 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 12/7/2017 Partial Approval SCOTT FINNILA
Masonry Wall/Backfill 12/8/2017 Corrections Issued SCOTT FINNILA
Deputy Shotcrete 12/11/2017 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 12/11/2017 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 1/17/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 1/19/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 2/6/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 2/21/2018 Approved MICHAEL FAUNCE
Footing/Foundation/Slab 2/22/2018 Conditional Approval DOMINIC DANERI
Deputy Reinf. Concrete 2/26/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 3/9/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 3/9/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 3/19/2018 Partial Approval SCOTT FINNILA
Underground Mechanical 3/30/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/10/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/13/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/30/2018 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/30/2018 Not Ready for Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/3/2018 Conditional Approval SCOTT FINNILA
Underground Mechanical 5/3/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/17/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/23/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/15/2018 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/26/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 7/2/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/21/2018 Partial Approval SCOTT FINNILA
Drywall Nailing 9/24/2018 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/24/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 10/23/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/14/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 11/15/2018 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 11/16/2018 Corrections Issued SCOTT FINNILA
Gas Test 12/4/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 12/5/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/14/2018 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 12/14/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 12/20/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/20/2018 Partial Approval SCOTT FINNILA
HVAC-Rough 1/2/2019 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/4/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 4/11/2019 Partial Inspection SCOTT FINNILA
Insulation 4/22/2019 Partial Approval SCOTT FINNILA
PLUMBING-Rough 4/22/2019 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 4/29/2019 Conditional Approval SCOTT FINNILA
PLUMBING-Rough 4/29/2019 Approved SCOTT FINNILA
HVAC-Rough 5/9/2019 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 5/23/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 6/19/2019 Partial Approval SCOTT FINNILA
Green Building Rough 6/19/2019 Partial Approval SCOTT FINNILA
Verify Sprinkler Sign Off 6/19/2019 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 6/26/2019 Partial Approval SCOTT FINNILA
Green Building Rough 6/26/2019 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 6/26/2019 Approved SCOTT FINNILA
HVAC-Rough 7/16/2019 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 7/22/2019 Approved SCOTT FINNILA
Green Building Rough 7/22/2019 Approved SCOTT FINNILA
HVAC-Rough 7/22/2019 Approved SCOTT FINNILA
Insulation 7/30/2019 Approved SCOTT FINNILA
Deputy Wood Construction 8/2/2019 Partial Approval SCOTT FINNILA
Insulation 8/9/2019 Approved SCOTT FINNILA
Drywall Nailing 8/21/2019 Conditional Approval SCOTT FINNILA
Shower Pan 10/4/2019 Approved SCOTT FINNILA
Underground Mechanical 3/12/2020 Order to Comply Issued SCOTT FINNILA
Gas Test 4/6/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 4/6/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 4/21/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 4/23/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 6/3/2020 Conditional Approval SCOTT FINNILA
Service/Power Release 8/13/2020 Partial Inspection DONALD CRICHLOW
Green Building Final 10/26/2021 Corrections Issued DONALD CRICHLOW
ELECTRICAL-Final 11/5/2021 Corrections Issued SCOTT FINNILA
Gas Test 11/5/2021 Approved SCOTT FINNILA
Service/Power Release 11/5/2021 Approved SCOTT FINNILA
Verify Rec and Parks Fee Memo 11/5/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 11/16/2021 Partial Approval SCOTT FINNILA
HVAC-Final 11/16/2021 Approved SCOTT FINNILA
PLUMBING-Final 11/16/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 11/29/2021 Partial Inspection SCOTT FINNILA
PLUMBING-Final 11/29/2021 Approved SCOTT FINNILA
Service/Power Release 11/29/2021 Partial Inspection SCOTT FINNILA
Green Building Final 12/7/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 12/8/2021 Approved SCOTT FINNILA
Footing/Foundation/Slab 12/20/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/20/2021 SGSOV Approved SCOTT FINNILA
Smoke Detectors 12/20/2021 Approved SCOTT FINNILA
Final 12/23/2021 OK to Issue CofO SCOTT FINNILA