21425 W VANOWEN ST 91303

Certificate Information: 21425 W VANOWEN ST 91303

Application / Permit
15010-10000-03622
Plan Check / Job No.
B15LA14259
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
New 6 story with 1 level of basement, 174 units apartment building.
Permit Issued
Issued on 8/17/2017
Issuing Office
Valley
Current Status
CofO Issued on 6/24/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2015 APPLICANT
Assigned to Plan Check Engineer 11/12/2015 JOE VO
Corrections Issued 11/28/2015 JOE VO
Disabled Access Plans Picked Up 12/4/2015 APPLICANT
Quality Review Completed 12/7/2015 JAMESON LEE
Building Plans Picked Up 12/8/2015 APPLICANT
Green Plans Picked Up 12/11/2015 APPLICANT
Applicant returned to address corrections 4/18/2017 JOE VO
Plan Check Approved 7/5/2017 JOE VO
Issued 8/17/2017 LADBS
TCO Issued (Expire Date: 06-23-2020) 12/26/2019 RICKEY JACKSON
CofO in Progress 5/29/2020 JEFFREY DURAN
No Progress 6/8/2020 JEFFREY DURAN
TCO Issued (Expire Date: 12-08-2020) 6/11/2020 JEFFREY DURAN
CofO in Progress 6/24/2020 JEFFREY DURAN
Permit Finaled 6/24/2020 RICKEY JACKSON
CofO Issued 6/24/2020 RICKEY JACKSON
Permit Finaled 6/24/2020 RICKEY JACKSON

Permit Application Clearance Information

CPC Cleared 11/1/2016 DENNIS CHEW
ZA Case Cleared 11/1/2016 DENNIS CHEW
ZI Cleared 11/1/2016 DENNIS CHEW
Address approval Cleared 11/18/2016 HOWARD COOPER
Eng Process Fee Ord 176,300 Cleared 12/21/2016 JAMES KHO
Hydrant and Access approval Cleared 12/22/2016 JOHN DALLAS
Excavation more than 5-ft deep Cleared 1/10/2017 CALOSHA APPROVED
Project located in CRA area Cleared 1/12/2017 JIM URQUHART
Sewer availability Cleared 1/18/2017 LEE GUILBEAUX
Fire Marshall Fire Life Safety Cleared 2/2/2017 DAVE MYERS
DAS Clearance Cleared 2/17/2017 EDDIE GARIN
Green Code Cleared 2/27/2017 ROLLIN GETTLE III
Driveway location Cleared 3/3/2017 ALBERT ISAGULIAN
Internal circulation Cleared 3/6/2017 VICENTE CORDERO
Highway dedication Cleared 3/16/2017 JOE VO
"Q" conditions Cleared 3/29/2017 TRACY WILLIAMS
Frnt yard landscape/Water mgmt Cleared 3/29/2017 TRACY WILLIAMS
Opn space landscape/Water mgmt Cleared 3/29/2017 TRACY WILLIAMS
Site Plan review Cleared 3/29/2017 TRACY WILLIAMS
Low Impact Development Cleared 4/20/2017 RYAN HUDSON
Stormwater Pollution Mitigatn Cleared 4/20/2017 RYAN HUDSON
Permit Cleared 4/24/2017 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/24/2017 LEE GUILBEAUX
Building over 3-story or 36-ft Cleared 5/18/2017 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 6/6/2017 WARREN LIU
ZA Case Cleared 6/9/2017 TRACY WILLIAMS
Encroachment in public way Cleared 7/5/2017 BERTRAM MOKLEBUST
Specific Plan Cleared 8/17/2017 TRACY WILLIAMS

Contact Information

Architect Stockton, Kenneth; Lic. No.: C19870 26500 W AGOURA RD. PMB # 844      CALABASAS, CA 91302
Contractor Cobalt Construction Company; Lic. No.: 369903-B 2259 WARD AVENUE SUITE 200      SIMI VALLEY, CA 93065
Engineer Choi, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804
Engineer Walter, Scott John; Lic. No.: GE2476 14428 HAMLIN ST STE 200      VAN NUYS, CA 91401

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/24/2017 Partial Inspection JEFFREY DURAN
Pre-Inspection 10/24/2017 Approved JEFFREY DURAN
Pre-Inspection 11/20/2017 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 11/29/2017 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/30/2017 Approved JEFFREY DURAN
Footing/Foundation/Slab 11/30/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/1/2017 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/4/2017 Approved JEFFREY DURAN
Deputy Reinf. Concrete 12/5/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/5/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/5/2017 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/5/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/6/2017 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 12/6/2017 Conditional Approval JEFFREY DURAN
Green Building Rough 12/6/2017 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 12/6/2017 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 12/6/2017 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 12/7/2017 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 12/7/2017 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/7/2017 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 12/8/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/8/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/8/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/11/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/11/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/11/2017 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 12/12/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/12/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/12/2017 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/13/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/13/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/13/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/14/2017 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 12/14/2017 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 12/15/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/15/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/15/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/18/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/18/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/18/2017 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 12/19/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/19/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/19/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/20/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/20/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/20/2017 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/21/2017 Approved JEFFREY DURAN
Deputy Shotcrete 12/21/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/21/2017 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/27/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/27/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/28/2017 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/28/2017 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/29/2017 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 12/29/2017 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/2/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/2/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 1/3/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/3/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/3/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/4/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/4/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/4/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/5/2018 Approved JEFFREY DURAN
Deputy Shotcrete 1/5/2018 Approved JEFFREY DURAN
Deputy Drilled-In Anchors 1/19/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/22/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/22/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/23/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/23/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 1/24/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/24/2018 Not Ready for Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/25/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/26/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/29/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/2/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 2/6/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/6/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/7/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/13/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 2/14/2018 Corrections Issued JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/14/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 2/15/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/20/2018 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/20/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/21/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/21/2018 Partial Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/22/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/23/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 2/26/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/26/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/27/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 2/27/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/27/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 2/28/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 2/28/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/28/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 2/28/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 2/28/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 2/28/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 3/1/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/1/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/2/2018 No Access for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 3/2/2018 No Access for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 3/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/5/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/6/2018 Approved JEFFREY DURAN
Footing/Foundation/Slab 3/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/7/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/7/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/7/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 3/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/8/2018 Approved JEFFREY DURAN
Green Building Rough 3/8/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 3/8/2018 Conditional Approval JEFFREY DURAN
Verify Sprinkler Sign Off 3/8/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 3/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/9/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/15/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 3/16/2018 Approved JEFFREY DURAN
Green Building Rough 3/16/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 3/16/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 3/16/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 3/19/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/19/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 3/20/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 3/20/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 3/21/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/23/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 3/23/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 3/23/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/27/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 3/27/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 3/28/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/28/2018 Conditional Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 3/28/2018 Partial Approval ROBERT COLE
Green Building Rough 3/28/2018 Not Ready for Inspection ROBERT COLE
Reinforced Masonry Frame 3/28/2018 Not Ready for Inspection ROBERT COLE
Verify Sprinkler Sign Off 3/28/2018 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Concrete 3/29/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 3/29/2018 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/29/2018 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 3/29/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Concrete 3/30/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 3/30/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 4/2/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/2/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/3/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 4/3/2018 Approved JEFFREY DURAN
Green Building Rough 4/3/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 4/3/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 4/3/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 4/4/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 4/4/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 4/5/2018 Approved JEFFREY DURAN
Deputy Reinf. Masonry 4/5/2018 Approved JEFFREY DURAN
Green Building Rough 4/5/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 4/5/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 4/5/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 4/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/9/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/9/2018 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 4/10/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/10/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/11/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 4/16/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 4/17/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/18/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 4/19/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/19/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/20/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/23/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/23/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/24/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/25/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/26/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 4/27/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/30/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/30/2018 Partial Inspection JEFFREY DURAN
Deputy Reinf. Concrete 5/4/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 5/4/2018 Conditional Approval JEFFREY DURAN
Pre-Inspection 5/7/2018 Not Ready for Inspection JEFFREY DURAN
Light Gage Steel Frame 5/8/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 5/9/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 5/9/2018 Not Ready for Inspection JEFFREY DURAN
Light Gage Steel Frame 5/9/2018 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 5/9/2018 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 5/10/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 5/11/2018 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/14/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 5/14/2018 Partial Approval JEFFREY DURAN
Green Building Rough 5/14/2018 Not Ready for Inspection JEFFREY DURAN
Reinforced Masonry Frame 5/14/2018 Partial Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 5/14/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Masonry 5/15/2018 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 5/15/2018 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 5/15/2018 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 5/16/2018 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 5/16/2018 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 5/18/2018 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 5/22/2018 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 5/24/2018 Conditional Approval JAMES STEPHENS
Floor/Roof Diaphrgm/Shear Wall 5/25/2018 Not Ready for Inspection CAMERON CHABAN
Deputy Steel/Welding 5/31/2018 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 5/31/2018 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 5/31/2018 Conditional Approval CAMERON CHABAN
Special/Order Compliance 6/1/2018 Corrections Issued JEFFREY DURAN
Deputy Steel/Welding 6/4/2018 Conditional Approval JEFFREY DURAN
Special/Order Compliance 6/4/2018 Partial Inspection JEFFREY DURAN
Deputy Wood Construction 6/7/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 6/11/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 6/11/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2018 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 6/14/2018 Conditional Approval CAMERON CHABAN
Deputy Reinf. Masonry 6/14/2018 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 6/14/2018 Conditional Approval CAMERON CHABAN
Masonry Wall/Backfill 6/14/2018 Conditional Approval CAMERON CHABAN
Structural Steel Frame 6/14/2018 Partial Inspection CAMERON CHABAN
Deputy Reinf. Masonry 6/18/2018 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 6/18/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 6/18/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 6/19/2018 Conditional Approval ROBERT COLE
Deputy Steel/Welding 6/19/2018 Conditional Approval ROBERT COLE
Drywall Nailing 6/19/2018 Partial Inspection ROBERT COLE
Deputy Steel/Welding 6/20/2018 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 6/21/2018 Approved JEFFREY DURAN
Deputy Wood Construction 6/21/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 6/21/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/21/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 6/28/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 6/29/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 6/29/2018 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 7/5/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 7/9/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 7/11/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 7/17/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 7/20/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 7/24/2018 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 7/24/2018 Not Ready for Inspection JEFFREY DURAN
Wood Frame 7/24/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Wood Construction 7/26/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 7/31/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 8/3/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 8/7/2018 Conditional Approval JAMES STEPHENS
Deputy Wood Construction 8/9/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 8/16/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 8/20/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 8/21/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 8/28/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 8/29/2018 Approved JEFFREY DURAN
Deputy Wood Construction 9/10/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/11/2018 Approved JEFFREY DURAN
Wood Frame 9/11/2018 Partial Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2018 Partial Inspection JEFFREY DURAN
Wood Frame 9/12/2018 Partial Inspection JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2018 Partial Inspection JEFFREY DURAN
Wood Frame 9/13/2018 Partial Inspection JEFFREY DURAN
Deputy Wood Construction 9/17/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2018 Partial Approval JEFFREY DURAN
Wood Frame 9/17/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 9/19/2018 Approved JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2018 Partial Approval JEFFREY DURAN
Wall Anchors 9/19/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 9/21/2018 Approved JEFFREY DURAN
Insulation 9/21/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/24/2018 Partial Approval JEFFREY DURAN
Wood Frame 9/24/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 9/25/2018 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2018 Partial Approval JEFFREY DURAN
Wood Frame 9/26/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 9/27/2018 Approved JEFFREY DURAN
Drywall Nailing 9/27/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 9/27/2018 Conditional Approval JEFFREY DURAN
Insulation 9/27/2018 Not Ready for Inspection JEFFREY DURAN
Wood Frame 9/27/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/2/2018 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 10/9/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 10/10/2018 Partial Approval JEFFREY DURAN
Insulation 10/10/2018 Partial Approval JEFFREY DURAN
Insulation 10/11/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 10/12/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/12/2018 Not Ready for Inspection JEFFREY DURAN
Insulation 10/12/2018 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 10/12/2018 Partial Inspection JEFFREY DURAN
Drywall Nailing 10/16/2018 Partial Inspection JEFFREY DURAN
Insulation 10/16/2018 Partial Inspection JEFFREY DURAN
Deputy Wood Construction 10/17/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/19/2018 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 10/22/2018 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/23/2018 Partial Approval JEFFREY DURAN
Wood Frame 10/23/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 10/24/2018 Conditional Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/25/2018 Partial Approval JEFFREY DURAN
Insulation 10/25/2018 Not Ready for Inspection JEFFREY DURAN
Wood Frame 10/25/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2018 Not Ready for Inspection JEFFREY DURAN
Insulation 10/26/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 11/2/2018 Approved JEFFREY DURAN
Insulation 11/2/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 11/5/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/7/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/9/2018 Partial Approval JEFFREY DURAN
Insulation 11/9/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 11/13/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 11/14/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 11/14/2018 Partial Approval JEFFREY DURAN
Insulation 11/14/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/15/2018 Partial Approval JEFFREY DURAN
Insulation 11/15/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 11/16/2018 Partial Approval JEFFREY DURAN
Insulation 11/16/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/20/2018 Not Ready for Inspection ROBERT COLE
Insulation 11/20/2018 Partial Approval ROBERT COLE
Floor/Roof Diaphrgm/Shear Wall 11/21/2018 Partial Inspection ROBERT COLE
Drywall Nailing 11/26/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/27/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 11/28/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/28/2018 Partial Approval JEFFREY DURAN
Insulation 11/28/2018 Partial Approval JEFFREY DURAN
Floor/Roof Diaphrgm/Shear Wall 11/29/2018 Not Ready for Inspection JEFFREY DURAN
Insulation 11/29/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/3/2018 Approved JEFFREY DURAN
Wood Frame 12/3/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 12/4/2018 Partial Approval JEFFREY DURAN
Deputy Wood Construction 12/5/2018 Approved JEFFREY DURAN
Drywall Nailing 12/5/2018 Partial Approval JEFFREY DURAN
Wood Frame 12/5/2018 Partial Approval JEFFREY DURAN
Special/Order Compliance 12/6/2018 Corrections Issued JEFFREY DURAN
Wood Frame 12/6/2018 Partial Approval JEFFREY DURAN
Insulation 12/7/2018 Not Ready for Inspection ROBERT COLE
Drywall Nailing 12/12/2018 Partial Approval JEFFREY DURAN
Insulation 12/12/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 12/13/2018 Approved JEFFREY DURAN
Insulation 12/17/2018 Conditional Approval JEFFREY DURAN
Drywall Nailing 12/20/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 12/21/2018 Partial Approval JEFFREY DURAN
Drywall Nailing 12/24/2018 Corrections Issued JEFFREY DURAN
Deputy Wood Construction 4/17/2019 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 4/30/2019 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 8/19/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/18/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/20/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/23/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 9/24/2019 Conditional Approval JEFFREY DURAN
Special/Order Compliance 5/27/2020 Conditional Approval JEFFREY DURAN
Final 5/29/2020 OK to Issue CofO JEFFREY DURAN
Footing/Foundation/Slab 5/29/2020 Approved JEFFREY DURAN
Green Building Final 5/29/2020 Approved JEFFREY DURAN
Green Building Rough 5/29/2020 Approved JEFFREY DURAN
Reinforced Concrete Frame 5/29/2020 Approved JEFFREY DURAN
Reinforced Masonry Frame 5/29/2020 Approved JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 5/29/2020 SGSOV Approved JEFFREY DURAN
Smoke Detectors 5/29/2020 Approved JEFFREY DURAN
Verify Sprinkler Sign Off 5/29/2020 Approved JEFFREY DURAN