5411 N ETIWANDA AVE 91356

Certificate Information: 5411 N ETIWANDA AVE 91356

Application / Permit
15010-10000-03591
Plan Check / Job No.
B15LA14076
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
New 3-Story Medical Office Building (Core and Shell)
Permit Issued
Issued on 7/18/2018
Issuing Office
Metro
Current Status
CofO Issued on 2/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2015 APPLICANT
Assigned to Plan Check Engineer 11/5/2015 ALLEN MANALANSAN
Corrections Issued 11/9/2015 ALLEN MANALANSAN
Quality Review Completed 11/20/2015 JOHN VASQUEZ
Building Plans Picked Up 11/20/2015 APPLICANT
Applicant returned to address corrections 12/21/2015 ALLEN MANALANSAN
Applicant returned to address corrections 3/24/2016 ALLEN MANALANSAN
Applicant returned to address corrections 4/4/2016 ALLEN MANALANSAN
Applicant returned to address corrections 4/12/2016 ALLEN MANALANSAN
Applicant returned to address corrections 4/14/2016 ALLEN MANALANSAN
Applicant returned to address corrections 10/5/2016 ALLEN MANALANSAN
Applicant returned to address corrections 10/26/2016 ALLEN MANALANSAN
Applicant returned to address corrections 11/1/2016 ALLEN MANALANSAN
Applicant returned to address corrections 11/22/2016 ALLEN MANALANSAN
Plan Check Approved 7/18/2018 ALLEN MANALANSAN
Issued 7/18/2018 LADBS
TCO Issued (Expire Date: 10-21-2020) 4/24/2020 RICKEY JACKSON
TCO Issued (Expire Date: 04-18-2021) 10/20/2020 JEFFREY DURAN
CofO in Progress 2/19/2021 JEFFREY DURAN
Permit Finaled 2/25/2021 RICKEY JACKSON
CofO Issued 2/25/2021 RICKEY JACKSON
Permit Finaled 2/25/2021 RICKEY JACKSON

Permit Application Clearance Information

Address approval Cleared 11/24/2015 LEE GUILBEAUX
Highway dedication Cleared 11/24/2015 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/6/2016 LEE GUILBEAUX
Permit Cleared 1/6/2016 LEE GUILBEAUX
Fire Marshall Fire Life Safety Cleared 6/7/2016 MENOA AGHAJANI
Hydrant and Access approval Cleared 6/7/2016 MENOA AGHAJANI
Disturb/Remove Protected Trees Cleared 8/8/2016 ADRIAN SANCHEZ
Low Impact Development Cleared 1/31/2017 MARTIN FRAGOSO
Stormwater Pollution Mitigatn Cleared 1/31/2017 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/14/2017 LEE GUILBEAUX
Address approval Cleared 4/4/2018 LEE GUILBEAUX
Building over 3-story or 36-ft Cleared 4/10/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/10/2018 CALOSHA APPROVED
Sewer availability Cleared 4/11/2018 LEE GUILBEAUX
DAS Clearance Cleared 5/8/2018 RICARDO TRES
Green Code Cleared 5/23/2018 MARCUS LEVIAS
Driveway location Cleared 6/1/2018 ALBERT ISAGULIAN
Internal circulation Cleared 6/1/2018 ALBERT ISAGULIAN
Specific Plan Cleared 6/1/2018 ALBERT ISAGULIAN
Transportation Demand Ord. Cleared 6/1/2018 ALBERT ISAGULIAN
Work Adjacent to Public Way Cleared 7/12/2018 BOK GOH
Comm Cor/Mini-Mall Cleared 7/13/2018 FIPE LEILUA
Comm Cor/Mini-Mall Cleared 7/13/2018 FIPE LEILUA
Comm Cor/Mini-Mall Cleared 7/13/2018 FIPE LEILUA
Frnt yard landscape/Water mgmt Cleared 7/13/2018 FIPE LEILUA
Prkng lot landscape/Water mgmt Cleared 7/13/2018 FIPE LEILUA
Site Plan review Cleared 7/13/2018 FIPE LEILUA
Specific Plan Cleared 7/13/2018 FIPE LEILUA
Specific Plan Cleared 7/13/2018 FIPE LEILUA
ZA Case Cleared 7/13/2018 FIPE LEILUA
ZA Case Cleared 7/13/2018 FIPE LEILUA

Contact Information

Architect Hernandez, Darcia Kay; Lic. No.: C30188 24092 JUANENO DRIVE      MISSION VIEJO, CA 92691
Contractor Millie And Severson General Contractors; Lic. No.: 99031-A P O BOX 3601      LOS ALAMITOS, CA 90720
Engineer Abratique, Efren Reyes; Lic. No.: C45425 466 WREN DR      LOS ANGELES, CA 90065
Engineer Cochran, Michael Lee; Lic. No.: S3663 16169 SUNSET BLVD 306      PACIFIC PALISADES, CA 90272
Engineer Donlon, Kevin Hamilton; Lic. No.: C79983 11507 MOORPARK ST 104      STUDIO CITY, CA 91602
Engineer Sivathasan, Kathiravetpilla; Lic. No.: GE2708 831 LA DOCENA LANE      CORONA, CA 92879
Landscape Architect Dean, James W; Lic. No.: LA1146 996 LAWRENCE DRIVE UNIT 205      NEWBURY PARK, CA 91320

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/23/2018 Not Ready for Inspection JEFFREY DURAN
Pre-Inspection 7/23/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 7/30/2018 Partial Inspection CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 8/17/2018 Partial Inspection JEFFREY DURAN
Footing/Foundation/Slab 8/17/2018 Partial Inspection JEFFREY DURAN
Pre-Inspection 8/17/2018 Approved JEFFREY DURAN
Pre-Inspection 8/20/2018 Approved JEFFREY DURAN
Deputy Reinf. Concrete 8/29/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 8/29/2018 OK to Expire Permit JEFFREY DURAN
Footing/Foundation/Slab 8/29/2018 Partial Approval JEFFREY DURAN
Reinforced Concrete Frame 8/29/2018 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/5/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/6/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/6/2018 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 9/6/2018 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 9/6/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/7/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/13/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/13/2018 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 9/13/2018 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 9/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/17/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/18/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 9/18/2018 Partial Approval JEFFREY DURAN
Wood Frame 9/18/2018 Not Ready for Inspection JEFFREY DURAN
Deputy EIFS 10/11/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/11/2018 Conditional Approval JEFFREY DURAN
Green Building Rough 10/11/2018 Not Ready for Inspection JEFFREY DURAN
Pre-Inspection 10/11/2018 Conditional Approval JEFFREY DURAN
Structural Steel Frame 10/11/2018 Partial Inspection JEFFREY DURAN
Verify Sprinkler Sign Off 10/11/2018 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 10/19/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/23/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/24/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/25/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/30/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 10/31/2018 Approved JEFFREY DURAN
Deputy Steel/Welding 11/2/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 11/14/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 11/15/2018 Conditional Approval JEFFREY DURAN
Special/Order Compliance 11/15/2018 Corrections Issued JEFFREY DURAN
Deputy Steel/Welding 11/20/2018 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 11/21/2018 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 11/26/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 11/26/2018 Corrections Issued JEFFREY DURAN
Footing/Foundation/Slab 11/26/2018 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 11/26/2018 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 11/27/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/28/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 11/29/2018 Approved JEFFREY DURAN
Deputy Steel/Welding 11/29/2018 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 11/29/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/4/2018 Conditional Approval JEFFREY DURAN
Special/Order Compliance 12/4/2018 Corrections Issued JEFFREY DURAN
Deputy Steel/Welding 12/6/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 12/12/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/13/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/13/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/14/2018 Approved JEFFREY DURAN
Pre-Inspection 12/14/2018 Partial Inspection JEFFREY DURAN
Deputy Steel/Welding 12/18/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/26/2018 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 12/26/2018 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 12/26/2018 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 12/27/2018 Approved JEFFREY DURAN
Deputy Steel/Welding 12/27/2018 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/3/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/9/2019 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/9/2019 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 1/9/2019 Conditional Approval JEFFREY DURAN
Special/Order Compliance 1/22/2019 Partial Inspection JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/28/2019 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 1/28/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/29/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 1/29/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 1/30/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/30/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 2/12/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 2/12/2019 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 2/12/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 2/19/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/20/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/25/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 2/26/2019 Conditional Approval JEFFREY DURAN
Green Building Rough 2/26/2019 Not Ready for Inspection JEFFREY DURAN
Reinforced Concrete Frame 2/26/2019 Partial Approval JEFFREY DURAN
Structural Steel Frame 2/26/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 2/26/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Steel/Welding 2/28/2019 Conditional Approval JAMES STEPHENS
Masonry Wall/Backfill 3/4/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 3/5/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 3/6/2019 Conditional Approval JEFFREY DURAN
Reinforced Concrete Frame 3/8/2019 Conditional Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/11/2019 Not Ready for Inspection JOHN KITCKO
Deputy Steel/Welding 3/13/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 3/14/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 3/15/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 3/18/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 3/20/2019 Approved JEFFREY DURAN
Deputy Steel/Welding 3/27/2019 Conditional Approval JAMES STEPHENS
Deputy Steel/Welding 3/28/2019 Conditional Approval JAMES STEPHENS
Excavation/Setback/Form/Re-Bar 3/29/2019 Partial Approval ROBERT COLE
Footing/Foundation/Slab 3/29/2019 Conditional Approval ROBERT COLE
Excavation/Setback/Form/Re-Bar 4/4/2019 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 4/4/2019 Partial Approval JEFFREY DURAN
Deputy Steel/Welding 4/8/2019 Conditional Approval JAMES STEPHENS
Deputy Drilled-In Anchors 4/9/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/9/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 4/10/2019 Approved JEFFREY DURAN
Deputy Steel/Welding 4/10/2019 Approved JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/10/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 4/11/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/11/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/16/2019 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 4/18/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/19/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/19/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 4/22/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/22/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/22/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 4/23/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 4/23/2019 Approved JEFFREY DURAN
Deputy Shotcrete 4/23/2019 Approved JEFFREY DURAN
Deputy Steel/Welding 4/23/2019 Approved JEFFREY DURAN
Deputy Drilled-In Anchors 4/24/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/24/2019 Approved JEFFREY DURAN
Deputy Shotcrete 4/24/2019 Approved JEFFREY DURAN
Deputy Drilled-In Anchors 4/25/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/25/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/25/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 4/26/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/26/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 4/26/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/26/2019 Conditional Approval JEFFREY DURAN
Excavation/Setback/Form/Re-Bar 4/26/2019 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 4/26/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/29/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 4/30/2019 Approved JEFFREY DURAN
Deputy Steel/Welding 4/30/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 5/1/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/2/2019 Approved JEFFREY DURAN
Deputy Shotcrete 5/2/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 5/3/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 5/3/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/9/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/10/2019 Conditional Approval JEFFREY DURAN
Deputy Grading 5/14/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/14/2019 Conditional Approval JEFFREY DURAN
Green Building Rough 5/14/2019 Corrections Issued JEFFREY DURAN
Deputy Grading 5/15/2019 Conditional Approval JEFFREY DURAN
Deputy Grading 5/16/2019 Conditional Approval JEFFREY DURAN
Deputy Grading 5/17/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/22/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 5/29/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/4/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 6/5/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 6/5/2019 Partial Approval JEFFREY DURAN
Insulation 6/5/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 6/5/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/6/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/7/2019 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 6/10/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/10/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/11/2019 Approved JEFFREY DURAN
Deputy Shotcrete 6/11/2019 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 6/12/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 6/12/2019 Approved JEFFREY DURAN
Deputy Shotcrete 6/12/2019 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 6/12/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 6/13/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 6/13/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 6/14/2019 Approved JEFFREY DURAN
Deputy Shotcrete 6/14/2019 Approved JEFFREY DURAN
Deputy Drilled-In Anchors 6/17/2019 Conditional Approval ROBERT COLE
Deputy Reinf. Concrete 6/17/2019 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 6/18/2019 Conditional Approval ANDREW DORSO
Deputy Drilled-In Anchors 6/21/2019 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 6/21/2019 Conditional Approval ROBERT COLE
Pre-Inspection 6/21/2019 Partial Inspection ROBERT COLE
Deputy Drilled-In Anchors 6/24/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 6/24/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 6/25/2019 Approved JEFFREY DURAN
Pre-Inspection 6/25/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/1/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 7/2/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/2/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 7/2/2019 Partial Approval JEFFREY DURAN
Insulation 7/2/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 7/5/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/5/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 7/8/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/8/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/9/2019 Approved JEFFREY DURAN
Insulation 7/9/2019 Partial Approval JEFFREY DURAN
Special/Order Compliance 7/9/2019 Corrections Issued JEFFREY DURAN
Deputy Shotcrete 7/10/2019 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 7/11/2019 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 7/11/2019 Conditional Approval JAMES STEPHENS
Deputy Reinf. Concrete 7/12/2019 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 7/12/2019 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/15/2019 Approved JEFFREY DURAN
Insulation 7/15/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/16/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/17/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/18/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/18/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 7/18/2019 Partial Approval JEFFREY DURAN
Insulation 7/18/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/19/2019 Conditional Approval ROBERT COLE
Deputy Shotcrete 7/19/2019 Conditional Approval ROBERT COLE
Insulation 7/19/2019 Not Ready for Inspection ROBERT COLE
Deputy Reinf. Masonry 7/22/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/22/2019 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 7/23/2019 Conditional Approval ROBERT COLE
Deputy Reinf. Masonry 7/23/2019 Conditional Approval ROBERT COLE
Deputy Shotcrete 7/23/2019 Conditional Approval ROBERT COLE
Deputy Pre-Stress Concrete 7/24/2019 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/24/2019 Conditional Approval JAMES STEPHENS
Deputy Shotcrete 7/24/2019 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 7/25/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/25/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 7/26/2019 Approved JEFFREY DURAN
Deputy Shotcrete 7/26/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 7/29/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/31/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 7/31/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/1/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/1/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/2/2019 Approved JEFFREY DURAN
Deputy Shotcrete 8/2/2019 Approved JEFFREY DURAN
Drywall Nailing 8/2/2019 Partial Approval JEFFREY DURAN
Green Building Rough 8/2/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Reinf. Concrete 8/5/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/5/2019 Conditional Approval JEFFREY DURAN
Insulation 8/6/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/7/2019 Approved JEFFREY DURAN
Deputy Reinf. Masonry 8/8/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/9/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Masonry 8/9/2019 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 8/13/2019 Approved JEFFREY DURAN
Deputy Shotcrete 8/13/2019 Approved JEFFREY DURAN
Deputy Reinf. Concrete 8/14/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/14/2019 Conditional Approval JEFFREY DURAN
Deputy Shotcrete 8/15/2019 Conditional Approval JAMES STEPHENS
Deputy Reinf. Masonry 8/16/2019 Approved MILLARD ARDOIN
Deputy Shotcrete 8/16/2019 Approved MILLARD ARDOIN
Wall Anchors 8/16/2019 Partial Approval MILLARD ARDOIN
Deputy Reinf. Masonry 8/19/2019 Approved JEFFREY DURAN
Deputy Shotcrete 8/19/2019 Approved JEFFREY DURAN
Deputy Shotcrete 8/20/2019 Approved JEFFREY DURAN
Deputy Shotcrete 8/26/2019 Approved JEFFREY DURAN
Special/Order Compliance 9/3/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 9/9/2019 Not Ready for Inspection MILLARD ARDOIN
Green Building Rough 9/9/2019 Not Ready for Inspection MILLARD ARDOIN
Deputy Reinf. Concrete 9/17/2019 Conditional Approval JEFFREY DURAN
Drywall Nailing 9/18/2019 Partial Approval JEFFREY DURAN
Green Building Rough 9/18/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 9/18/2019 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 9/24/2019 Partial Approval JEFFREY DURAN
Deputy Reinf. Concrete 9/26/2019 Conditional Approval JEFFREY DURAN
Pre-Inspection 11/4/2019 Partial Inspection JEFFREY DURAN
Special/Order Compliance 11/4/2019 Not Ready for Inspection JEFFREY DURAN
T-Bar Ceiling 11/13/2019 Partial Inspection JEFFREY DURAN
Special/Order Compliance 11/21/2019 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 11/22/2019 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 11/25/2019 Partial Inspection DANIEL VARNUM
Special/Order Compliance 11/25/2019 Partial Inspection DANIEL VARNUM
T-Bar Ceiling 11/26/2019 Partial Approval MILLARD ARDOIN
Special/Order Compliance 12/2/2019 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 12/3/2019 Conditional Approval JEFFREY DURAN
T-Bar Ceiling 12/3/2019 Conditional Approval JEFFREY DURAN
T-Bar Ceiling 12/4/2019 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 12/9/2019 Partial Approval JEFFREY DURAN
T-Bar Ceiling 12/9/2019 Approved JEFFREY DURAN
Masonry Wall/Backfill 12/10/2019 Partial Inspection JEFFREY DURAN
Green Building Rough 12/11/2019 Partial Approval JEFFREY DURAN
Reinforced Masonry Frame 12/11/2019 Partial Approval JEFFREY DURAN
Verify Sprinkler Sign Off 12/11/2019 Not Ready for Inspection JEFFREY DURAN
Drywall Nailing 12/23/2019 Partial Approval JEFFREY DURAN
Green Building Rough 12/23/2019 Not Ready for Inspection JEFFREY DURAN
Deputy Shotcrete 12/24/2019 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 1/3/2020 Partial Approval JEFFREY DURAN
Pre-Inspection 1/10/2020 Partial Inspection JEFFREY DURAN
Deputy Steel/Welding 1/14/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/15/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/16/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/17/2020 Conditional Approval JEFFREY DURAN
Deputy Pre-Stress Concrete 1/22/2020 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 1/23/2020 Conditional Approval JAMES STEPHENS
Footing/Foundation/Slab 1/27/2020 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 1/30/2020 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 2/10/2020 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 2/10/2020 Not Ready for Inspection JEFFREY FULTON
Deputy Reinf. Masonry 2/27/2020 Conditional Approval JEFFREY DURAN
Special/Order Compliance 3/17/2020 Partial Inspection JEFFREY DURAN
Drywall Nailing 3/24/2020 Approved JEFFREY DURAN
Final 3/24/2020 Not Ready for Inspection JEFFREY DURAN
Footing/Foundation/Slab 3/24/2020 Approved JEFFREY DURAN
Green Building Final 3/24/2020 Approved JEFFREY DURAN
Green Building Rough 3/24/2020 Approved JEFFREY DURAN
Reinforced Masonry Frame 3/24/2020 Approved JEFFREY DURAN
SGSOV-Seismic Gas S/O Valve 3/24/2020 SGSOV Approved JEFFREY DURAN
Smoke Detectors 3/24/2020 Approved JEFFREY DURAN
Structural Steel Frame 3/24/2020 Approved JEFFREY DURAN
Verify Sprinkler Sign Off 3/24/2020 Approved JEFFREY DURAN
Final 3/27/2020 Not Ready for Inspection JEFFREY DURAN
Final 4/2/2020 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 4/2/2020 Partial Approval JEFFREY DURAN
Final 4/13/2020 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 4/13/2020 Partial Approval ROBERT DAVIS
Final 4/15/2020 Not Ready for Inspection JEFFREY DURAN
Special/Order Compliance 4/16/2020 Conditional Approval JEFFREY DURAN
Final 4/20/2020 Not Ready for Inspection HAMID PISHEHVAR
Final 4/24/2020 OK for TCO JEFFREY DURAN
Special/Order Compliance 9/25/2020 Approved HAMID PISHEHVAR