4121 W SANTA MONICA BLVD 90029
Certificate Information: 4121 W SANTA MONICA BLVD 90029
- Application / Permit
- 15010-10000-03531
- Plan Check / Job No.
- B15LA13861
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- A new two-story commercial building with one level basement (one story core and shell only retail use, one story parking garage and one level of basement parking garage)
- Permit Issued
- Issued on 10/18/2016
- Issuing Office
- Metro
- Current Status
- CofO Corrected on 3/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
Submitted | 10/5/2015 | APPLICANT |
Assigned to Plan Check Engineer | 10/22/2015 | SAI KHUM |
Green Plans Picked Up | 10/23/2015 | APPLICANT |
Disabled Access Plans Picked Up | 10/26/2015 | APPLICANT |
Corrections Issued | 11/2/2015 | SAI KHUM |
Quality Review Completed | 11/17/2015 | JOHN VASQUEZ |
Building Plans Picked Up | 11/18/2015 | APPLICANT |
Applicant returned to address corrections | 12/7/2015 | SAI KHUM |
Applicant returned to address corrections | 12/17/2015 | SAI KHUM |
Applicant returned to address corrections | 12/18/2015 | SAI KHUM |
Applicant returned to address corrections | 1/4/2016 | SAI KHUM |
Applicant returned to address corrections | 1/14/2016 | SAI KHUM |
Applicant returned to address corrections | 2/3/2016 | SAI KHUM |
Applicant returned to address corrections | 2/11/2016 | SAI KHUM |
Applicant returned to address corrections | 2/26/2016 | SAI KHUM |
Applicant returned to address corrections | 3/24/2016 | SAI KHUM |
Applicant returned to address corrections | 4/7/2016 | SAI KHUM |
Applicant returned to address corrections | 4/8/2016 | SAI KHUM |
Plan Check Approved | 10/18/2016 | SAI KWAN KHUM |
Issued | 10/18/2016 | LADBS |
CofO in Progress | 3/4/2020 | DANIEL MC AULIFFE |
CofO Issued-Status Void | 3/4/2020 | TERRY HERR |
Permit Finaled-Status Void | 3/4/2020 | TERRY HERR |
Re-Activate Permit | 3/10/2020 | DAVID TSAU |
CofO Corrected | 3/10/2020 | TERRY HERR |
Permit Finaled | 3/10/2020 | TERRY HERR |
Permit Application Clearance Information
Address approval | Cleared | 12/1/2015 | VALENTINO PUEBLOS |
Eng Process Fee Ord 176,300 | Cleared | 12/1/2015 | VALENTINO PUEBLOS |
Sewer availability | Cleared | 12/1/2015 | VALENTINO PUEBLOS |
ZA Case | Cleared | 12/1/2015 | ULISES GONZALEZ |
ZI | Cleared | 12/1/2015 | ULISES GONZALEZ |
"D" conditions | Cleared | 12/3/2015 | ERIC CLAROS |
Encroachment in public way | Cleared | 12/3/2015 | KARAN PATEL |
Permit | Cleared | 12/3/2015 | KARAN PATEL |
Driveway location | Cleared | 12/18/2015 | TAIMOUR TANAVOLI |
Highway dedication | Cleared | 12/18/2015 | RAVIL MANAPOV |
Internal circulation | Cleared | 12/18/2015 | TAIMOUR TANAVOLI |
DAS Clearance | Cleared | 2/25/2016 | EDDIE GARIN |
Green Code | Cleared | 3/1/2016 | ALDO UBAU |
GPI Written Notices | Cleared | 3/2/2016 | SAI KWAN KHUM |
Grading Pre-Inspection | Cleared | 3/2/2016 | SAI KWAN KHUM |
Comm Cor/Mini-Mall | Cleared | 3/10/2016 | DANIEL SKOLNICK |
Low Impact Development | Cleared | 3/22/2016 | VIJAY DESAI |
Miscellaneous | Cleared | 3/22/2016 | NATALIE MOORE |
Roof/Waste drainage to street | Cleared | 3/22/2016 | ADRIAN SANCHEZ |
Stormwater Pollution Mitigatn | Cleared | 3/22/2016 | VIJAY DESAI |
Hydrant and Access approval | Cleared | 3/25/2016 | JOHN CONNEALLY |
Flood clearance | Cleared | 4/7/2016 | ROMANO GALASSI |
Comm Cor/Mini-Mall | Cleared | 5/24/2016 | DAVID WEINTRAUB |
Contact Information
Architect | Shubin, Russell James; Lic. No.: C19250 | 3834 WILLAT AVENUE CULVER CITY, CA 90232 |
Contractor | Owner-Builder | , |
Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
Engineer | Knur, Reinard Thomas; Lic. No.: GE2755 | 1435 MONCADO DR GLENDALE, CA 91207 |
Inspector Information
DAVID BURKHEAD, (213) 482-7294 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
No Data Available. |
Inspection Request History
Pre-Inspection | 11/1/2016 | Approved | BARRY SILLS |
Deputy Steel/Welding | 11/30/2016 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Concrete | 4/26/2017 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Concrete | 5/9/2017 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Concrete | 5/10/2017 | Conditional Approval | BARRY SILLS |
Footing/Foundation/Slab | 5/10/2017 | Partial Approval | BARRY SILLS |
Deputy Reinf. Concrete | 5/11/2017 | Conditional Approval | ERNESTO CORRAL |
Reinforced Concrete Frame | 5/11/2017 | Partial Approval | ERNESTO CORRAL |
Verify Sprinkler Sign Off | 5/11/2017 | Not Ready for Inspection | ERNESTO CORRAL |
Deputy Reinf. Concrete | 5/12/2017 | Conditional Approval | BARRY SILLS |
Deputy Shotcrete | 5/18/2017 | Approved | SAKO AGHAZARIAN |
Deputy Shotcrete | 5/19/2017 | Approved | SAKO AGHAZARIAN |
Deputy Shotcrete | 5/22/2017 | Approved | SAKO AGHAZARIAN |
Deputy Shotcrete | 5/23/2017 | Approved | SAKO AGHAZARIAN |
Deputy Shotcrete | 5/24/2017 | Conditional Approval | ERNESTO CORRAL |
Green Building Rough | 5/24/2017 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Reinforced Concrete Frame | 5/24/2017 | Partial Inspection | ERNESTO CORRAL |
Verify Sprinkler Sign Off | 5/24/2017 | Not Ready for Inspection | ERNESTO CORRAL |
Deputy Reinf. Concrete | 5/25/2017 | Approved | SAKO AGHAZARIAN |
Deputy Shotcrete | 5/25/2017 | Approved | SAKO AGHAZARIAN |
Deputy Reinf. Concrete | 5/26/2017 | Conditional Approval | TED RIES |
Deputy Shotcrete | 5/26/2017 | Conditional Approval | TED RIES |
Deputy Shotcrete | 5/30/2017 | Conditional Approval | BARRY SILLS |
Deputy Shotcrete | 5/31/2017 | Conditional Approval | BARRY SILLS |
Deputy Shotcrete | 6/1/2017 | Conditional Approval | BARRY SILLS |
Deputy Shotcrete | 6/2/2017 | Conditional Approval | BARRY SILLS |
Reinforced Concrete Frame | 6/2/2017 | Partial Approval | BARRY SILLS |
Verify Sprinkler Sign Off | 6/2/2017 | Approved | BARRY SILLS |
Deputy Shotcrete | 6/5/2017 | Approved | SAKO AGHAZARIAN |
Deputy Shotcrete | 6/5/2017 | Conditional Approval | BARRY SILLS |
Reinforced Masonry Frame | 6/5/2017 | Partial Approval | BARRY SILLS |
Deputy Shotcrete | 6/6/2017 | Conditional Approval | BARRY SILLS |
Deputy Shotcrete | 6/7/2017 | Conditional Approval | BARRY SILLS |
Reinforced Concrete Frame | 6/7/2017 | Partial Approval | BARRY SILLS |
Deputy Shotcrete | 6/8/2017 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Masonry | 6/12/2017 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Masonry | 6/13/2017 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Masonry | 6/14/2017 | Conditional Approval | BARRY SILLS |
Green Building Rough | 6/14/2017 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Reinforced Masonry Frame | 6/14/2017 | Partial Approval | BARRY SILLS |
Deputy Reinf. Masonry | 6/15/2017 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Concrete | 6/16/2017 | Conditional Approval | BARRY SILLS |
Green Building Rough | 6/16/2017 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Reinforced Masonry Frame | 6/16/2017 | Partial Approval | BARRY SILLS |
Deputy Reinf. Masonry | 6/19/2017 | Conditional Approval | TED RIES |
Deputy Reinf. Concrete | 7/10/2017 | Conditional Approval | BARRY SILLS |
Deputy Reinf. Concrete | 7/17/2017 | Conditional Approval | TED RIES |
Footing/Foundation/Slab | 7/17/2017 | Partial Inspection | TED RIES |
Reinforced Concrete Frame | 7/17/2017 | Partial Inspection | TED RIES |
Deputy Reinf. Concrete | 7/18/2017 | Conditional Approval | TED RIES |
Footing/Foundation/Slab | 7/18/2017 | Partial Approval | TED RIES |
Reinforced Concrete Frame | 8/1/2017 | Not Ready for Inspection | TED RIES |
Deputy Reinf. Concrete | 8/3/2017 | Conditional Approval | TED RIES |
Deputy Shotcrete | 8/3/2017 | Conditional Approval | TED RIES |
Deputy Shotcrete | 8/4/2017 | Conditional Approval | TED RIES |
Deputy Reinf. Masonry | 8/9/2017 | Conditional Approval | TED RIES |
Green Building Rough | 8/9/2017 | Not Ready for Inspection | DONALD CRICHLOW |
Reinforced Masonry Frame | 8/9/2017 | Partial Approval | TED RIES |
Deputy Reinf. Masonry | 8/10/2017 | Conditional Approval | TED RIES |
Deputy Reinf. Masonry | 8/11/2017 | Conditional Approval | TED RIES |
Deputy Reinf. Masonry | 8/15/2017 | Conditional Approval | TED RIES |
Green Building Rough | 8/15/2017 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Reinforced Masonry Frame | 8/15/2017 | Partial Approval | TED RIES |
Deputy Reinf. Concrete | 9/13/2017 | Conditional Approval | TED RIES |
Deputy Reinf. Concrete | 9/15/2017 | Conditional Approval | TED RIES |
Deputy Reinf. Concrete | 9/19/2017 | Conditional Approval | TED RIES |
Deputy Reinf. Concrete | 9/25/2017 | Approved | SAKO AGHAZARIAN |
Green Building Rough | 9/25/2017 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
Reinforced Concrete Frame | 9/25/2017 | Partial Approval | SAKO AGHAZARIAN |
Deputy Reinf. Concrete | 9/26/2017 | Conditional Approval | TED RIES |
Special/Order Compliance | 4/18/2019 | Approved | TED RIES |
Insulation | 5/15/2019 | Partial Approval | TED RIES |
Insulation | 6/3/2019 | Partial Approval | TED RIES |
Interior/Exterior Lathing | 10/18/2019 | Partial Approval | DANIEL MC AULIFFE |
Drywall Nailing | 3/4/2020 | Approved | DANIEL MC AULIFFE |
Final | 3/4/2020 | Conditional Approval | DANIEL MC AULIFFE |
Footing/Foundation/Slab | 3/4/2020 | Approved | DANIEL MC AULIFFE |
Green Building Final | 3/4/2020 | Approved | DANIEL MC AULIFFE |
Green Building Rough | 3/4/2020 | Approved | DANIEL MC AULIFFE |
Reinforced Concrete Frame | 3/4/2020 | Approved | DANIEL MC AULIFFE |
Reinforced Masonry Frame | 3/4/2020 | Approved | DANIEL MC AULIFFE |
SGSOV-Seismic Gas S/O Valve | 3/4/2020 | SGSOV Approved | DANIEL MC AULIFFE |
SUSMP-Std. Urban Storm Water | 3/4/2020 | Approved | DANIEL MC AULIFFE |
Smoke Detectors | 3/4/2020 | Approved | DANIEL MC AULIFFE |
Structural Steel Frame | 3/4/2020 | Approved | DANIEL MC AULIFFE |