5323 E ABBOTT PL 90042
Certificate Information: 5323 E ABBOTT PL 90042
- Application / Permit
- 15010-10000-03286
- Plan Check / Job No.
- B15LA12919
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY S.F.D. WITH ATTACHED GARAGE
- Permit Issued
- Issued on 9/1/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2015 | HANS SANTIAGO |
| Green Plans Picked Up | 10/23/2015 | APPLICANT |
| Corrections Issued | 11/4/2015 | EMMANUEL MARTINEZ |
| Quality Review Completed | 11/18/2015 | KESETE HAREGOT |
| Building Plans Picked Up | 11/19/2015 | APPLICANT |
| Applicant returned to address corrections | 7/27/2016 | EMMANUEL MARTINEZ |
| Applicant returned to address corrections | 8/24/2016 | HANS SANTIAGO |
| Applicant returned to address corrections | 1/24/2017 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/27/2017 | HANS SANTIAGO |
| Plan Check Approved | 8/8/2017 | Andrew Santiago |
| Issued | 9/1/2017 | LADBS |
| CofO in Progress | 7/26/2019 | HAMIK HARTOUNIAN |
| No Progress | 8/2/2019 | HAMIK HARTOUNIAN |
| CofO in Progress | 8/5/2019 | HAMIK HARTOUNIAN |
| CofO Issued-Status Void | 8/13/2019 | DEROLD HAUFF |
| Permit Finaled-Status Void | 8/13/2019 | DEROLD HAUFF |
| Re-Activate Permit | 8/11/2021 | RONALD MYRICK |
| No Progress | 8/12/2021 | RONALD MYRICK |
| CofO Revoked | 8/12/2021 | RONALD MYRICK |
| Permit Revoked | 8/12/2021 | RONALD MYRICK |
| CofO in Progress | 5/20/2026 | LILIANA PORTILLO |
| CofO Issued | 5/21/2026 | DEROLD HAUFF |
| Permit Finaled | 5/21/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 7/27/2016 | EMMANUEL MARTINEZ |
| Grading Pre-Inspection | Cleared | 7/27/2016 | EMMANUEL MARTINEZ |
| Address approval | Cleared | 8/1/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 8/1/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 8/1/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 8/1/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 8/1/2016 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2016 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 8/1/2016 | ROBERT DUFF |
| Permit | Cleared | 8/1/2016 | RAVIL MANAPOV |
| Sewer availability | Cleared | 8/1/2016 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 2/15/2017 | SEVAK ISAKHAYAN |
| Low Impact Development | Cleared | 3/1/2017 | SAM NAVID |
| HPOZ | Cleared | 3/6/2017 | ARIANE BRISKI |
| Green Code | Cleared | 4/21/2017 | WILLIAM ROSE |
| Disturb/Remove Protected Trees | Cleared | 7/26/2017 | LUIS TORRES |
| Roof/Waste drainage to street | Cleared | 8/1/2017 | KENNETH PHAM |
Contact Information
| Architect | Linn, Daniel Samuel; Lic. No.: C14843 | 5732 BELLEVUE AVE LA JOLLA, CA 92037 |
| Contractor | Zorzoli Construction Inc; Lic. No.: 965210-B | 19903 EAST RAMBLING ROAD COVINA, CA 91724 |
| Engineer | Horowitz, Richard William; Lic. No.: C38249 | 12485 ROUGHMONT PLACE SAN DIEGO, CA 92131 |
| Engineer | Jeremy, Stone; Lic. No.: C85850 | 300 EAST BELLEVUE DRIVE 212 PASADENA, CA 91101 |
| Geologist | Christopher, Allen; Lic. No.: EG2648 | 135 E LAUREL AVE. SIERRA MADRE, CA 91024 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/19/2017 | Partial Approval | LUIS ALVAREZ |
| Footing/Foundation/Slab | 1/4/2018 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 2/22/2018 | Conditional Approval | LUIS ALVAREZ |
| Deputy Drilled-In Anchors | 4/10/2018 | Conditional Approval | LUIS ALVAREZ |
| Footing/Foundation/Slab | 4/13/2018 | Approved | DOMINIC DANERI |
| Excavation/Setback/Form/Re-Bar | 4/26/2018 | Partial Approval | LUIS ALVAREZ |
| Underground Mechanical | 5/11/2018 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2018 | Not Ready for Inspection | DOMINIC DANERI |
| Insulation | 6/15/2018 | Partial Approval | LUIS ALVAREZ |
| PLUMBING-Rough | 6/15/2018 | Partial Approval | LUIS ALVAREZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2018 | Partial Approval | FRANCISCO MORADO |
| HVAC-Rough | 9/21/2018 | Approved | FRANCISCO MORADO |
| ELECTRICAL-Rough | 10/1/2018 | Not Ready for Inspection | FRANCISCO MORADO |
| PLUMBING-Rough | 10/1/2018 | Approved | FRANCISCO MORADO |
| ELECTRICAL-Rough | 10/9/2018 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/15/2018 | Not Ready for Inspection | FRANCISCO MORADO |
| BUILDING-Rough-Frame | 10/16/2018 | Corrections Issued | RUBEN SALAS |
| Insulation | 10/16/2018 | Partial Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 10/17/2018 | Partial Approval | FRANCISCO MORADO |
| Wood Frame | 10/31/2018 | Corrections Issued | FRANCISCO MORADO |
| Wood Frame | 11/16/2018 | Not Ready for Inspection | RUBEN SALAS |
| Wood Frame | 11/20/2018 | Approved | ENRIQUE MIRELES |
| Insulation | 12/17/2018 | Partial Approval | FRANCISCO MORADO |
| Drywall Nailing | 1/10/2019 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 1/10/2019 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 1/10/2019 | Partial Approval | RAUL BARAJAS |
| Wood Frame | 1/10/2019 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 1/25/2019 | Approved | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 4/11/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| Reinforced Masonry Frame | 4/30/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 5/1/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 5/10/2019 | Partial Approval | HAMIK HARTOUNIAN |
| Masonry Wall/Backfill | 5/15/2019 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 6/20/2019 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 6/20/2019 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Final | 6/20/2019 | Approved | HAMIK HARTOUNIAN |
| HVAC-Final | 7/3/2019 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 7/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Final | 7/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2019 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 7/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 7/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 7/16/2019 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/22/2019 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/22/2019 | Approved | ENRIQUE MIRELES |
| Final | 7/22/2019 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 7/22/2019 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/22/2019 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 7/22/2019 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 7/22/2019 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/22/2019 | Approved | ENRIQUE MIRELES |
| Final | 7/25/2019 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Service/Power Release | 7/25/2019 | Approved | HAMIK HARTOUNIAN |
| Final | 5/19/2026 | OK to Issue CofO | LILIANA PORTILLO |