214 S BRISTOL AVE 90049

Certificate Information: 214 S BRISTOL AVE 90049

Application / Permit
15010-10000-03251
Plan Check / Job No.
B15LA12843
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
New 2- story irregular shape 29'-0" x 51'-0" accessory living quarters. The proposed structure shall be fully sprinklered per NFPA-13D requirements.
Permit Issued
Issued on 9/22/2016
Issuing Office
Metro
Current Status
Issued on 9/22/2016
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2015 APPLICANT
Green Plans Picked Up 9/28/2015 APPLICANT
Assigned to Plan Check Engineer 10/1/2015 ARMEN SARKISIAN
Corrections Issued 10/6/2015 ARMEN SARKISIAN
Quality Review Completed 10/7/2015 STEVEN KIM
Building Plans Picked Up 10/7/2015 APPLICANT
Applicant returned to address corrections 12/9/2015 ARMEN SARKISIAN
Applicant returned to address corrections 1/4/2016 ARMEN SARKISIAN
Applicant returned to address corrections 1/22/2016 ARMEN SARKISIAN
Applicant returned to address corrections 2/10/2016 ARMEN SARKISIAN
Applicant returned to address corrections 3/15/2016 ARMEN SARKISIAN
Applicant returned to address corrections 3/31/2016 ARMEN SARKISIAN
Plan Check Approved 5/18/2016 ARMEN SARKISIAN
Issued 9/22/2016 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/22/2015 SHANNON CAMPBELL
Sewer availability Cleared 12/22/2015 SHANNON CAMPBELL
Low Impact Development Cleared 3/11/2016 MICHAEL SCADUTO
Hydrant and Access approval Cleared 3/21/2016 ROBERT DUFF
Roof/Waste drainage to street Cleared 3/31/2016 RICHARD SOUTHERLAND
Green Code Cleared 5/16/2016 MARCUS LEVIAS

Contact Information

Contractor Dbca Inc; Lic. No.: 915336-B 14605 N 73RD STREET      SCOTTSDALE, AZ 85260
Engineer Shah, Kamal Rajendra; Lic. No.: C46200 28039 SMYTH DR STE 200      VALENCIA, CA 91355

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/13/2016 Partial Approval DAVID KOSKI
Underground Mechanical 12/20/2016 Partial Approval DAVID KOSKI
Underground Mechanical 12/21/2016 Partial Approval DAVID KOSKI
Footing/Foundation/Slab 12/27/2016 Approved DAVID KOSKI
Floor/Roof Diaphrgm/Shear Wall 3/17/2017 Partial Inspection DAVID KOSKI
Green Building Rough 3/17/2017 Partial Inspection DAVID KOSKI
Verify Sprinkler Sign Off 3/17/2017 Partial Inspection DAVID KOSKI
Footing/Foundation/Slab 8/10/2017 Partial Approval KENNETH NAGLE
Reinforced Concrete Frame 8/28/2017 Partial Approval JOHN LUMB
Gas Test 8/31/2017 Approved DANIEL ORRANTE
Underground Mechanical 8/31/2017 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 11/3/2017 Partial Approval JOHN LUMB
BUILDING-Rough-Frame 11/15/2017 Corrections Issued RICHARD STEINBACH
Deputy Wood Construction 11/15/2017 Approved RICHARD STEINBACH
ELECTRICAL-Rough 11/15/2017 Corrections Issued RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 11/15/2017 Partial Approval RICHARD STEINBACH
Green Building Rough 11/15/2017 Approved RICHARD STEINBACH
HVAC-Rough 11/15/2017 Corrections Issued RICHARD STEINBACH
PLUMBING-Rough 11/15/2017 Corrections Issued RICHARD STEINBACH
Verify Sprinkler Sign Off 11/15/2017 Not Ready for Inspection RICHARD STEINBACH
Underground Mechanical 7/3/2018 Partial Approval VINCENT SCIPIONI
BUILDING-Rough-Frame 7/26/2018 Not Ready for Inspection VINCENT SCIPIONI
ELECTRICAL-Rough 7/26/2018 Partial Approval VINCENT SCIPIONI
HVAC-Rough 7/26/2018 Not Ready for Inspection VINCENT SCIPIONI
PLUMBING-Rough 7/26/2018 Partial Approval VINCENT SCIPIONI
Verify Sprinkler Sign Off 7/26/2018 Corrections Issued VINCENT SCIPIONI
BUILDING-Rough-Frame 8/9/2018 Partial Approval VINCENT SCIPIONI
Insulation 8/9/2018 Approved VINCENT SCIPIONI
Drywall Nailing 9/7/2018 Approved VINCENT SCIPIONI
Shower Pan 11/7/2018 Approved MICHAEL PELHAM
Interior/Exterior Lathing 5/31/2019 Not Ready for Inspection TIM CHRISTENSEN
Interior/Exterior Lathing 6/11/2019 Partial Approval RICHARD STEINBACH
Interior/Exterior Lathing 6/14/2019 Approved MICHAEL TEMPLE
Gas Test 1/29/2020 Approved MICHAEL TEMPLE
PLUMBING-Final 10/26/2020 Not Ready for Inspection ANDREW NAVE
Special/Order Compliance 3/7/2025 Corrections Issued KENNETH NAGLE
ELECTRICAL-Final 8/8/2025 Approved HERBERT GIRON
HVAC-Final 8/8/2025 Approved HERBERT GIRON
PLUMBING-Final 8/8/2025 Approved HERBERT GIRON