1020 W VENICE BLVD 90291
Certificate Information: 1020 W VENICE BLVD 90291
- Application / Permit
- 15010-10000-03210
- Plan Check / Job No.
- B15LA12680
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- NEW RESTAURANT TWO STORY RESTAURANT WITH OUTDOOR DINING.
- Permit Issued
- Issued on 3/21/2017
- Issuing Office
- Metro
- Current Status
- Issued on 3/21/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/9/2015 | APPLICANT |
| Disabled Access Plans Picked Up | 9/14/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2015 | MOHAMMAD FIROUZBAKHT |
| Corrections Issued | 10/20/2015 | MOHAMMAD FIROUZBAKHT |
| Quality Review Completed | 10/26/2015 | KESETE HAREGOT |
| Building Plans Picked Up | 10/29/2015 | APPLICANT |
| Green Plans Picked Up | 10/29/2015 | APPLICANT |
| Plan Check Approved | 12/22/2016 | MOHAMMAD FIROUZBAKHT |
| Issued | 3/21/2017 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 2/12/2016 | RICHARD DOCKUS |
| DAS Clearance | Cleared | 2/16/2016 | WAI LAU |
| Food Service Establishment | Cleared | 2/16/2016 | AMPHORN WONG |
| Permit | Cleared | 2/26/2016 | ARNULFO NUNO |
| Hydrant and Access approval | Cleared | 3/15/2016 | ROBERT DUFF |
| Miscellaneous | Cleared | 4/5/2016 | ERIC CLAROS |
| Miscellaneous | Cleared | 4/5/2016 | ERIC CLAROS |
| ZA Case | Cleared | 4/5/2016 | ERIC CLAROS |
| "Q" conditions | Cleared | 6/23/2016 | MOHAMMAD FIROUZBAKHT |
| Coastal Zone | Cleared | 6/23/2016 | MOHAMMAD FIROUZBAKHT |
| Specific Plan | Cleared | 6/23/2016 | MOHAMMAD FIROUZBAKHT |
| ZA Case | Cleared | 6/23/2016 | MOHAMMAD FIROUZBAKHT |
| ZI | Cleared | 6/23/2016 | MOHAMMAD FIROUZBAKHT |
| Supp. Use District POD/CDO/TDO | Cleared | 7/5/2016 | MOHAMMAD FIROUZBAKHT |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2016 | BRIAN KELLY |
| Sewer availability | Cleared | 7/21/2016 | BRIAN KELLY |
| Driveway location | Cleared | 8/15/2016 | PEDRO AYALA |
| Specific Plan | Cleared | 8/15/2016 | PEDRO AYALA |
| Highway dedication | Cleared | 8/26/2016 | LUZ RABELO |
| Specific Plan | Cleared | 9/1/2016 | PEDRO AYALA |
| Low Impact Development | Cleared | 12/1/2016 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 12/5/2016 | RAVIL MANAPOV |
| Food establishment approval | Cleared | 12/22/2016 | LACDHS APPROVED |
Contact Information
| Architect | Coscia, Anthony Walter; Lic. No.: C23407 | 747 INDIANA AVENUE COSCIA ARCHITECTURE + DESIGN VENICE, CA 90291 |
| Contractor | L J Construction; Lic. No.: 799342-B | 15902A HALLIBURTON ROAD # 182 HACIENDA HEIGHTS, CA 91745 |
| Engineer | Pallmann, Robert; Lic. No.: C72746 | 12777 WEST JEFFERSON BLVD SUITE 200 LOS ANGELES, CA 90066 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2017 | Approved | JASON BORUTA |
| Pre-Inspection | 3/1/2018 | Approved | JASON BORUTA |
| Deputy Reinf. Concrete | 4/16/2018 | Approved | JASON BORUTA |
| Excavation/Setback/Form/Re-Bar | 4/18/2018 | Not Ready for Inspection | JASON BORUTA |
| Masonry Wall/Backfill | 4/27/2018 | Not Ready for Inspection | JASON BORUTA |
| Masonry Wall/Backfill | 4/30/2018 | Not Ready for Inspection | JASON BORUTA |
| Pre-Inspection | 6/5/2018 | Approved | JASON BORUTA |
| Pre-Inspection | 7/23/2018 | Not Ready for Inspection | JASON BORUTA |
| Pre-Inspection | 8/13/2018 | Not Ready for Inspection | JASON BORUTA |
| Pre-Inspection | 8/15/2018 | Not Ready for Inspection | JASON BORUTA |
| Pre-Inspection | 8/22/2018 | No Access for Inspection | JASON BORUTA |
| Pre-Inspection | 9/7/2018 | Not Ready for Inspection | JASON BORUTA |
| Special/Order Compliance | 9/7/2018 | Partial Inspection | TONY HARTONO |
| Pre-Inspection | 11/26/2018 | Not Ready for Inspection | JASON BORUTA |
| Special/Order Compliance | 2/7/2019 | Not Ready for Inspection | JASON BORUTA |
| Pre-Inspection | 3/21/2019 | Corrections Issued | JASON BORUTA |
| Pre-Inspection | 5/14/2019 | Not Ready for Inspection | JASON BORUTA |
| Special/Order Compliance | 3/17/2020 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 4/30/2020 | Approved | JEFF BYTHEWAY |
| Special/Order Compliance | 7/31/2020 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 10/23/2020 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 11/16/2020 | Partial Approval | JEFF BYTHEWAY |
| Deputy Reinf. Concrete | 2/10/2021 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 4/26/2021 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 4/28/2021 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 4/29/2021 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 4/30/2021 | Conditional Approval | SORIN CIRSTOIU |
| Structural Steel Frame | 4/30/2021 | Corrections Issued | SORIN CIRSTOIU |
| Deputy Steel/Welding | 5/3/2021 | Conditional Approval | SORIN CIRSTOIU |
| Masonry Wall/Backfill | 6/10/2021 | Partial Approval | SORIN CIRSTOIU |
| Deputy Reinf. Masonry | 7/30/2021 | Conditional Approval | JOHN DODGE |
| Masonry Wall/Backfill | 8/4/2021 | Partial Approval | SORIN CIRSTOIU |
| Deputy Reinf. Masonry | 8/12/2021 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 8/17/2021 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 8/18/2021 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 8/19/2021 | Approved | SORIN CIRSTOIU |
| Deputy Steel/Welding | 8/20/2021 | Conditional Approval | SORIN CIRSTOIU |
| Masonry Wall/Backfill | 9/22/2021 | Partial Inspection | SORIN CIRSTOIU |
| Masonry Wall/Backfill | 9/23/2021 | Partial Inspection | SORIN CIRSTOIU |
| Masonry Wall/Backfill | 9/28/2021 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Masonry | 10/1/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 11/10/2021 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 11/12/2021 | Corrections Issued | NICK LAROCCA |
| Deputy Steel/Welding | 11/16/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 11/17/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 11/18/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 11/19/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 11/22/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 12/1/2021 | Partial Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 12/2/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 12/3/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 12/29/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 12/30/2021 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 1/6/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 1/7/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 1/11/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 1/12/2022 | Partial Approval | JOEY BUCHANAN |
| Deputy Steel/Welding | 1/13/2022 | Approved | DERRICK SPENCER |
| Deputy Steel/Welding | 1/14/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 1/19/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 1/20/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 1/21/2022 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 2/18/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 2/24/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 2/25/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/10/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/11/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/12/2022 | Approved | JEFF BYTHEWAY |
| Deputy Steel/Welding | 5/13/2022 | Approved | NICK LAROCCA |
| Deputy Steel/Welding | 5/31/2022 | Conditional Approval | DAVID TSAU |
| Footing/Foundation/Slab | 7/7/2022 | Partial Approval | DERRICK SPENCER |
| Special/Order Compliance | 2/7/2023 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 3/6/2023 | Partial Approval | DERRICK SPENCER |
| Pre-Inspection | 6/2/2023 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2023 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 6/7/2023 | Partial Approval | DERRICK SPENCER |
| Special/Order Compliance | 8/10/2023 | Partial Inspection | SORIN CIRSTOIU |
| Smoke Detectors | 11/20/2023 | No Access for Inspection | DERRICK SPENCER |
| Special/Order Compliance | 4/2/2024 | Partial Inspection | PAUL DAVIDSON |
| Special/Order Compliance | 10/21/2024 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 1/30/2026 | Not Ready for Inspection | PAUL DAVIDSON |