9262 W NIGHTINGALE DR 90069

Certificate Information: 9262 W NIGHTINGALE DR 90069

Application / Permit
15010-10000-03203
Plan Check / Job No.
B15LA12642
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) SFD 2 STORY WITH BASEMENT AND ATTACHED GARAGE
Permit Issued
Issued on 6/17/2016
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2015 APPLICANT
Green Plans Picked Up 9/24/2015 APPLICANT
Assigned to Plan Check Engineer 10/1/2015 CORA JOHNSON
Corrections Issued 10/4/2015 CORA JOHNSON
Quality Review Completed 10/9/2015 BILL STUTSMAN
Building Plans Picked Up 10/9/2015 APPLICANT
Plan Check Approved 4/28/2016 CORA JOHNSON
Issued 6/17/2016 LADBS
CofO in Progress 7/16/2021 BRAD BESCOS
Permit Finaled 7/20/2021 DEROLD HAUFF
CofO Issued 7/20/2021 DEROLD HAUFF
Permit Finaled 7/20/2021 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 9/15/2015 CORA JOHNSON
Grading Pre-Inspection Cleared 9/15/2015 CORA JOHNSON
Address approval Cleared 10/14/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 10/14/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 10/14/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 10/14/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 10/14/2015 ARMENIA HERNANDEZ
BHO/Hillside ordinance Cleared 10/14/2015 ARMENIA HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/14/2015 ARMENIA HERNANDEZ
Distance to fire station Cleared 10/20/2015 ROBERT DUFF
Excavation more than 5-ft deep Cleared 11/21/2015 CALOSHA APPROVED
Sewer availability Cleared 1/20/2016 ADRIAN HERNANDEZ
Low Impact Development Cleared 3/18/2016 MICHAEL SCADUTO
Roof/Waste drainage to street Cleared 3/22/2016 JOHN LIN
Green Code Cleared 4/1/2016 JOHN KLARIN

Contact Information

Contractor Tyler Development Corporation; Lic. No.: 451882-B 1932 COTNER AVE      LOS ANGELES, CA 90025

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 9/13/2016 Approved JOEL WILLIAMS
Deputy Grading 9/15/2016 Conditional Approval DANNY TOLENTINO
Deputy Grading 9/16/2016 No Access for Inspection JOEL WILLIAMS
Deputy Grading 9/19/2016 Approved JOEL WILLIAMS
Deputy Grading 9/23/2016 Conditional Approval DANNY TOLENTINO
Deputy Grading 10/4/2016 Conditional Approval DANNY TOLENTINO
Deputy Grading 10/14/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 10/17/2016 Approved BRAD BESCOS
Deputy Grading 10/25/2016 Approved BRAD BESCOS
Deputy Grading 10/26/2016 No Access for Inspection JOEL WILLIAMS
Deputy Grading 10/28/2016 Approved BRAD BESCOS
Deputy Grading 11/7/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/8/2016 Approved BRAD BESCOS
Deputy Grading 11/9/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/10/2016 No Access for Inspection JOEL WILLIAMS
Deputy Grading 11/15/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/16/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/17/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/18/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/21/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/22/2016 Approved BRAD BESCOS
Deputy Grading 11/23/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/28/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/29/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 11/30/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 12/1/2016 Approved BRAD BESCOS
Footing/Foundation/Slab 12/1/2016 Partial Approval BRAD BESCOS
Piling/Pier/Caisson 12/1/2016 Partial Approval BRAD BESCOS
Deputy Grading 12/2/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 12/5/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 12/8/2016 Approved BRAD BESCOS
Deputy Grading 12/9/2016 Approved JOEL WILLIAMS
Deputy Grading 12/12/2016 No Access for Inspection BRAD BESCOS
Deputy Grading 12/13/2016 No Access for Inspection JOEL WILLIAMS
Deputy Grading 12/14/2016 No Access for Inspection JOEL WILLIAMS
Deputy Grading 1/17/2017 Approved JOEL WILLIAMS
Footing/Foundation/Slab 1/17/2017 Partial Approval JOEL WILLIAMS
Underground Mechanical 1/26/2017 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 2/23/2017 Partial Approval JOEL WILLIAMS
Footing/Foundation/Slab 3/2/2017 Partial Approval JOEL WILLIAMS
Footing/Foundation/Slab 3/10/2017 Partial Approval JOEL WILLIAMS
Footing/Foundation/Slab 3/29/2017 Conditional Approval BRAD BESCOS
Footing/Foundation/Slab 4/28/2017 Not Ready for Inspection JOEL WILLIAMS
Footing/Foundation/Slab 5/2/2017 Partial Approval JOEL WILLIAMS
Footing/Foundation/Slab 5/18/2017 Partial Approval BRAD BESCOS
PLUMBING-Rough 6/2/2017 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 6/14/2017 Partial Approval JOEL WILLIAMS
Footing/Foundation/Slab 7/12/2017 Partial Approval JOEL WILLIAMS
PLUMBING-Rough 7/17/2017 Partial Approval JOEL WILLIAMS
PLUMBING-Rough 7/21/2017 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 8/2/2017 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 8/29/2017 Partial Approval BRAD BESCOS
Footing/Foundation/Slab 9/19/2017 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 10/4/2017 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 11/3/2017 Corrections Issued DANIEL GONZALEZ
Piling/Pier/Caisson 11/3/2017 Corrections Issued DANIEL GONZALEZ
BUILDING-Rough-Frame 11/7/2017 Not Ready for Inspection DANIEL GONZALEZ
Green Building Rough 11/7/2017 Not Ready for Inspection DANIEL GONZALEZ
Reinforced Concrete Frame 11/7/2017 Partial Approval DANIEL GONZALEZ
Verify Sprinkler Sign Off 11/7/2017 Not Ready for Inspection DANIEL GONZALEZ
Deputy Reinf. Concrete 11/8/2017 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 11/16/2017 Not Ready for Inspection DANNY TOLENTINO
Piling/Pier/Caisson 11/16/2017 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 11/29/2017 Conditional Approval DANIEL GONZALEZ
Footing/Foundation/Slab 12/4/2017 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 12/20/2017 Not Ready for Inspection DANIEL GONZALEZ
PLUMBING-Rough 12/20/2017 Not Ready for Inspection DANIEL GONZALEZ
PLUMBING-Rough 12/21/2017 Partial Inspection DANIEL GONZALEZ
Reinforced Masonry Frame 12/21/2017 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 1/12/2018 Approved DANIEL GONZALEZ
Footing/Foundation/Slab 1/12/2018 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 1/22/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 1/26/2018 Approved DANIEL GONZALEZ
Footing/Foundation/Slab 2/1/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 2/6/2018 Partial Approval DANIEL GONZALEZ
HVAC-Rough 2/12/2018 Corrections Issued DANIEL GONZALEZ
HVAC-Rough 2/15/2018 Partial Inspection ROBERT MINASSIANS
Special/Order Compliance 2/15/2018 Partial Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 2/22/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 2/23/2018 No Access for Inspection DANIEL GONZALEZ
Deputy Reinf. Concrete 3/21/2018 No Access for Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 3/23/2018 Partial Approval DANIEL GONZALEZ
Piling/Pier/Caisson 3/23/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 3/27/2018 Partial Approval DANIEL GONZALEZ
Deck 3/28/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 3/28/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 3/30/2018 Approved DANIEL GONZALEZ
Footing/Foundation/Slab 4/4/2018 Conditional Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 4/6/2018 No Access for Inspection DANIEL GONZALEZ
PLUMBING-Rough 4/11/2018 No Access for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 4/12/2018 Not Ready for Inspection DANIEL GONZALEZ
PLUMBING-Rough 4/12/2018 Partial Approval DANIEL GONZALEZ
Deputy Steel/Welding 4/23/2018 No Access for Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 4/23/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 4/24/2018 No Access for Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 5/2/2018 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 5/4/2018 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 5/4/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 5/7/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 5/9/2018 Partial Approval DANIEL GONZALEZ
Deputy Shotcrete 5/10/2018 No Access for Inspection DANIEL GONZALEZ
Deputy Reinf. Concrete 5/15/2018 No Access for Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 5/16/2018 Partial Approval ROBERT MINASSIANS
Deputy Reinf. Concrete 5/21/2018 No Access for Inspection DANIEL GONZALEZ
Deputy Steel/Welding 5/21/2018 No Access for Inspection DANIEL GONZALEZ
Deputy Steel/Welding 5/22/2018 Partial Approval DANIEL GONZALEZ
Pool Piping 5/22/2018 Partial Inspection DANIEL GONZALEZ
Deputy Steel/Welding 5/23/2018 Partial Approval DANIEL GONZALEZ
PLUMBING-Rough 5/30/2018 Partial Approval DANIEL GONZALEZ
Deputy Steel/Welding 6/12/2018 Partial Approval DANIEL GONZALEZ
HVAC-Rough 6/18/2018 Partial Inspection DANIEL GONZALEZ
Footing/Foundation/Slab 6/29/2018 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 7/3/2018 Not Ready for Inspection DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 7/18/2018 Corrections Issued DANIEL GONZALEZ
Footing/Foundation/Slab 7/18/2018 Corrections Issued DANIEL GONZALEZ
PLUMBING-Rough 7/23/2018 Not Ready for Inspection DANIEL GONZALEZ
Piling/Pier/Caisson 7/23/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 8/1/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 8/13/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 8/24/2018 Partial Approval DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 9/7/2018 Partial Approval DANIEL GONZALEZ
Footing/Foundation/Slab 9/7/2018 Partial Approval DANIEL GONZALEZ
Excavation/Setback/Form/Re-Bar 9/18/2018 Not Ready for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 9/18/2018 Partial Approval DANNY TOLENTINO
Deputy Reinf. Concrete 9/20/2018 No Access for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 10/22/2018 Partial Approval DANIEL GONZALEZ
Deputy Reinf. Concrete 10/26/2018 Partial Approval DANIEL GONZALEZ
ELECTRICAL-Rough 10/29/2018 Not Ready for Inspection DANIEL GONZALEZ
Pool Piping 11/8/2018 Partial Inspection DANIEL GONZALEZ
Gas Test 12/18/2018 Partial Approval RONALD COWAN
Deputy Drilled-In Anchors 1/23/2019 No Access for Inspection DANNY TOLENTINO
Footing/Foundation/Slab 1/25/2019 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 2/21/2019 Partial Approval DANNY TOLENTINO
Deputy Drilled-In Anchors 3/8/2019 Conditional Approval DANNY TOLENTINO
Footing/Foundation/Slab 3/20/2019 Partial Approval RONALD COWAN
Deputy Shotcrete 4/10/2019 No Access for Inspection DANNY TOLENTINO
Deputy Wood Construction 4/10/2019 No Access for Inspection DANNY TOLENTINO
Deputy Steel/Welding 4/11/2019 Conditional Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 4/11/2019 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/23/2019 Partial Approval DANNY TOLENTINO
Insulation 5/9/2019 Partial Approval DANNY TOLENTINO
ELECTRICAL-Rough 6/12/2019 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 6/12/2019 Not Ready for Inspection DANNY TOLENTINO
HVAC-Rough 6/12/2019 Partial Approval DANNY TOLENTINO
PLUMBING-Rough 6/24/2019 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 8/9/2019 Partial Approval RICHARD STEINBACH
Gas Test 8/13/2019 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 8/13/2019 Partial Approval RICHARD STEINBACH
HVAC-Rough 8/20/2019 Partial Approval RICHARD STEINBACH
PLUMBING-Rough 8/20/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 9/13/2019 Partial Approval RICHARD STEINBACH
Gas Test 9/13/2019 Partial Approval RICHARD STEINBACH
Sewer 9/13/2019 Approved RICHARD STEINBACH
Deputy Reinf. Concrete 9/17/2019 Conditional Approval RICHARD STEINBACH
Shower Pan 9/27/2019 Partial Approval RICHARD STEINBACH
Interior/Exterior Lathing 10/8/2019 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 10/23/2019 Partial Approval ROBERT CORNELL
Excavation/Setback/Form/Re-Bar 10/30/2019 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 12/12/2019 Partial Approval RICHARD STEINBACH
Gas Test 12/19/2019 Partial Approval RICHARD STEINBACH
ELECTRICAL-Rough 1/14/2020 Partial Approval BRIAN SULLIVAN
HVAC-Rough 1/15/2020 Partial Approval RICHARD STEINBACH
BUILDING-Rough-Frame 1/22/2020 Partial Approval RICHARD STEINBACH
Green Building Rough 1/22/2020 Approved RICHARD STEINBACH
HVAC-Rough 1/22/2020 Approved RICHARD STEINBACH
Special/Order Compliance 1/22/2020 Approved MATTHEW NUCKOLLS
Verify Sprinkler Sign Off 1/22/2020 Partial Approval RICHARD STEINBACH
Insulation 2/5/2020 Partial Approval ROBERT CORNELL
Interior/Exterior Lathing 2/7/2020 Partial Approval RICHARD STEINBACH
Drywall Nailing 2/12/2020 Partial Approval RICHARD STEINBACH
ELECTRICAL-Rough 3/4/2020 Partial Approval RICHARD STEINBACH
Footing/Foundation/Slab 3/26/2020 Partial Approval ROBERT CORNELL
ELECTRICAL-Rough 4/7/2020 Conditional Approval RAUL BARAJAS
Interior/Exterior Lathing 4/7/2020 Partial Approval RAUL BARAJAS
Wood Frame 4/7/2020 Partial Approval RAUL BARAJAS
Insulation 4/17/2020 Partial Approval RAUL BARAJAS
Drywall Nailing 4/24/2020 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 4/24/2020 Partial Approval RAUL BARAJAS
Insulation 5/5/2020 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 5/12/2020 Partial Approval RAUL BARAJAS
Drywall Nailing 5/14/2020 Partial Approval RAUL BARAJAS
Interior/Exterior Lathing 5/14/2020 Approved RAUL BARAJAS
Footing/Foundation/Slab 5/22/2020 Approved RAUL BARAJAS
Interior/Exterior Lathing 5/22/2020 Approved RAUL BARAJAS
Sewer 6/3/2020 Conditional Approval RAUL BARAJAS
Shower Pan 7/29/2020 Approved RAUL BARAJAS
Insulation 8/6/2020 Approved RAUL BARAJAS
Special/Order Compliance 9/18/2020 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 12/7/2020 Partial Approval JOSEPH MCGARRY
Service/Power Release 12/11/2020 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 1/28/2021 Approved RAUL BARAJAS
Drywall Nailing 3/22/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 4/14/2021 Partial Inspection RAUL BARAJAS
HVAC-Final 4/14/2021 Partial Approval RAUL BARAJAS
PLUMBING-Final 4/14/2021 Partial Inspection RAUL BARAJAS
HVAC-Final 4/23/2021 Approved RAUL BARAJAS
Service/Power Release 4/23/2021 Approved RAUL BARAJAS
BUILDING-Rough-Frame 4/27/2021 Approved RAUL BARAJAS
ELECTRICAL-Final 4/27/2021 Approved RAUL BARAJAS
Final 4/27/2021 Corrections Issued RAUL BARAJAS
Green Building Final 4/27/2021 Approved RAUL BARAJAS
PLUMBING-Final 4/27/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 4/27/2021 SGSOV Not Ready RAUL BARAJAS
Smoke Detectors 4/27/2021 Approved RAUL BARAJAS
Verify Sprinkler Sign Off 4/27/2021 Approved RAUL BARAJAS
Final 5/10/2021 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/10/2021 SGSOV Not Ready RAUL BARAJAS
Final 5/13/2021 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/13/2021 SGSOV Not Ready RAUL BARAJAS
Final 5/19/2021 Not Ready for Inspection RAUL BARAJAS
Final 5/27/2021 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Not Ready RAUL BARAJAS
Final 6/17/2021 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Approved RAUL BARAJAS
Final 7/12/2021 Partial Approval BRAD BESCOS
Final 7/14/2021 OK to Issue CofO BRAD BESCOS