3800 N HOLLYLINE AVE 91423

Certificate Information: 3800 N HOLLYLINE AVE 91423

Application / Permit
15010-10000-03131
Plan Check / Job No.
B15LA12308
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 4-CAR GARAGE AND 1 UNCOVERED PARKING ON SITE PER DIR-2015-1638-DRB-SPP-MSP SEE COMMENTS.
Permit Issued
Issued on 3/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 10/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2015 APPLICANT
Assigned to Plan Check Engineer 9/17/2015 EMMANUEL MARTINEZ
Corrections Issued 9/22/2015 RICARDO SUPAN
Quality Review Completed 9/25/2015 LAWRENCE QUIRANTE
Building Plans Picked Up 9/25/2015 APPLICANT
Green Plans Picked Up 10/14/2015 APPLICANT
Applicant returned to address corrections 11/19/2015 RICARDO SUPAN
Applicant returned to address corrections 6/20/2016 RICARDO SUPAN
Applicant returned to address corrections 8/22/2016 RICARDO SUPAN
Applicant returned to address corrections 8/31/2016 RICARDO SUPAN
Plan Check Approved 10/7/2016 RICARDO SUPAN
Issued 3/20/2019 LADBS
CofO in Progress 4/26/2024 MISAEL ESPARZA
No Progress 4/26/2024 MISAEL ESPARZA
CofO in Progress 4/26/2024 MISAEL ESPARZA
CofO in Progress 4/26/2024 MISAEL ESPARZA
CofO in Progress 4/30/2024 MISAEL ESPARZA
CofO Issued 10/23/2024 DANIEL ORRANTE
Permit Finaled 10/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/21/2015 KIRK LINKLATER
Address approval Cleared 10/7/2015 ADRIAN HERNANDEZ
BHO/Hillside ordinance Cleared 10/7/2015 ADRIAN HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/7/2015 ADRIAN HERNANDEZ
BHO/Hillside ordinance Cleared 10/13/2015 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 10/13/2015 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 10/13/2015 RICHARD SOUTHERLAND
BHO/Hillside ordinance Cleared 10/13/2015 RICHARD SOUTHERLAND
Permit Cleared 10/13/2015 RICHARD SOUTHERLAND
Sewer availability Cleared 10/13/2015 RICHARD SOUTHERLAND
Hydrant and Access approval Cleared 10/16/2015 JOHN DALLAS
Stormwater Pollution Mitigatn Cleared 10/28/2015 MARTIN FRAGOSO
Excavation more than 5-ft deep Cleared 8/31/2016 CALOSHA APPROVED
GPI Written Notices Cleared 8/31/2016 RICARDO SUPAN
Disturb/Remove Protected Trees Cleared 9/1/2016 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 8/21/2018 ADRIAN SANCHEZ
Miscellaneous Cleared 12/19/2018 EDBER MACEDO
Specific Plan Cleared 12/19/2018 EDBER MACEDO
Green Code Cleared 2/26/2019 JOHN KLARIN
Low Impact Development Cleared 2/26/2019 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Owner-Builder       ,
Engineer Chiu, Ivan Wai-Kuen; Lic. No.: L6762 2160 PARNELL WY      ALTADENA, CA 91001
Engineer Krief, Dan Dov; Lic. No.: C76041 1450 S BEVERLY DR 305      LOS ANGELES, CA 90035
Engineer Park, Juntae; Lic. No.: C65104 1444 HI POINT ST      LOS ANGELES, CA 90035

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2019 Approved THOMAS FINNILA
Pre-Inspection 10/21/2019 Approved THOMAS FINNILA
PLUMBING-Rough 10/31/2019 Corrections Issued JOHN HAYES
PLUMBING-Rough 11/1/2019 Corrections Issued RAYMOND KEHOE
Underground Mechanical 11/5/2019 Partial Approval RAYMOND KEHOE
Footing/Foundation/Slab 12/5/2019 Partial Approval JEFFREY PARD
Protected Tree Letter 12/5/2019 Not Ready for Inspection JEFFREY PARD
Excavation/Setback/Form/Re-Bar 1/22/2020 Partial Approval RAYMOND KEHOE
Excavation/Setback/Form/Re-Bar 2/13/2020 Partial Approval CHARLES POWELL
Sewer 3/31/2020 Corrections Issued RAYMOND KEHOE
ELECTRICAL-Rough 4/22/2020 Partial Inspection WILLIAM KUEHN
Masonry Wall/Backfill 4/22/2020 Partial Inspection WILLIAM KUEHN
PLUMBING-Rough 4/22/2020 Partial Inspection WILLIAM KUEHN
Excavation/Setback/Form/Re-Bar 4/24/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 4/24/2020 Partial Approval MARK JOHNSON
Protected Tree Letter 4/24/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 4/29/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/30/2020 Partial Approval MISAEL ESPARZA
Protected Tree Letter 4/30/2020 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 5/6/2020 Partial Approval RAYMOND KEHOE
Reinforced Concrete Frame 5/14/2020 Corrections Issued CHARLES POWELL
Piling/Pier/Caisson 5/18/2020 Approved CHARLES POWELL
Special/Order Compliance 5/18/2020 Approved CHARLES POWELL
Deputy Reinf. Concrete 5/21/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 6/4/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 6/12/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 6/29/2020 Partial Approval CHARLES POWELL
Masonry Wall/Backfill 7/8/2020 Approved CHARLES POWELL
Deputy Reinf. Concrete 7/10/2020 Corrections Issued CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Corrections Issued CHARLES POWELL
Excavation/Setback/Form/Re-Bar 7/22/2020 Corrections Issued CHARLES POWELL
Excavation/Setback/Form/Re-Bar 7/28/2020 Corrections Issued CHARLES POWELL
Excavation/Setback/Form/Re-Bar 8/10/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 8/13/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 8/13/2020 Partial Approval CHARLES POWELL
Protected Tree Letter 8/13/2020 Not Ready for Inspection CHARLES POWELL
Excavation/Setback/Form/Re-Bar 8/17/2020 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 8/19/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 8/19/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 8/19/2020 Partial Approval CHARLES POWELL
Deputy Reinf. Concrete 8/24/2020 Partial Approval CHARLES POWELL
Reinforced Concrete Frame 9/8/2020 Approved CHARLES POWELL
Sewer 9/10/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Partial Approval CHARLES POWELL
Excavation/Setback/Form/Re-Bar 12/9/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 12/9/2020 Partial Approval CHARLES POWELL
Protected Tree Letter 12/9/2020 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 12/30/2020 Corrections Issued CHARLES POWELL
Green Building Rough 12/30/2020 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 12/30/2020 Not Ready for Inspection CHARLES POWELL
Excavation/Setback/Form/Re-Bar 1/12/2021 Not Ready for Inspection ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 1/14/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 1/28/2021 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Approved CHARLES POWELL
Verify Sprinkler Sign Off 1/28/2021 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 3/16/2021 Partial Approval CHARLES POWELL
HVAC-Rough 3/16/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 3/17/2021 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 3/31/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 3/31/2021 Corrections Issued CHARLES POWELL
ELECTRICAL-Rough 4/8/2021 Corrections Issued CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval CHARLES POWELL
Green Building Rough 4/12/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 4/12/2021 Not Ready for Inspection CHARLES POWELL
Shower Pan 4/29/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 5/10/2021 No Access for Inspection CHARLES POWELL
Green Building Rough 5/10/2021 No Access for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 5/10/2021 No Access for Inspection CHARLES POWELL
Wood Frame 5/17/2021 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval CHARLES POWELL
Interior/Exterior Lathing 6/15/2021 Partial Approval CHARLES POWELL
PLUMBING-Rough 7/6/2021 Not Ready for Inspection CHARLES POWELL
Interior/Exterior Lathing 7/12/2021 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 7/13/2021 Partial Approval CHARLES POWELL
Green Building Rough 7/13/2021 Not Ready for Inspection CHARLES POWELL
Interior/Exterior Lathing 7/13/2021 Partial Approval CHARLES POWELL
Verify Sprinkler Sign Off 7/13/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 7/20/2021 Partial Approval CHARLES POWELL
Green Building Rough 7/20/2021 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 7/20/2021 Corrections Issued CHARLES POWELL
Insulation 7/27/2021 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/3/2021 Partial Approval CHARLES POWELL
Green Building Rough 8/3/2021 Not Ready for Inspection CHARLES POWELL
Insulation 8/3/2021 Partial Approval CHARLES POWELL
Interior/Exterior Lathing 8/12/2021 Partial Approval CHARLES POWELL
Drywall Nailing 8/13/2021 Partial Approval CHARLES POWELL
Insulation 8/13/2021 Partial Approval CHARLES POWELL
Special/Order Compliance 8/13/2021 Corrections Issued MICHAEL PELHAM
Drywall Nailing 9/3/2021 Partial Approval CHARLES POWELL
Green Building Rough 9/3/2021 Not Ready for Inspection CHARLES POWELL
BUILDING-Rough-Frame 9/17/2021 Not Ready for Inspection MISAEL ESPARZA
Grading Pre-Inspection 9/17/2021 Partial Inspection MISAEL ESPARZA
Green Building Rough 9/17/2021 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 9/17/2021 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 9/17/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 10/14/2021 Partial Approval MISAEL ESPARZA
Green Building Rough 10/14/2021 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 10/14/2021 Not Ready for Inspection MISAEL ESPARZA
Insulation 10/19/2021 Approved ASHLEY THOMPSON
Drywall Nailing 10/28/2021 Partial Approval MARK JOHNSON
Pre-Inspection 4/25/2022 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 7/13/2022 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 7/20/2022 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 1/27/2023 Partial Inspection MISAEL ESPARZA
PLUMBING-Final 4/4/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 4/26/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 5/30/2023 Partial Inspection JOHN COLEMAN
ELECTRICAL-Final 6/5/2023 Not Ready for Inspection JACK KARGODORIAN
ELECTRICAL-Final 6/6/2023 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Final 6/12/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Final 7/21/2023 Partial Inspection MISAEL ESPARZA
PLUMBING-Final 10/30/2023 Corrections Issued MISAEL ESPARZA
Gas Test 11/15/2023 Approved MISAEL ESPARZA
PLUMBING-Final 11/15/2023 Approved MISAEL ESPARZA
Grounding or Bonding 11/20/2023 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 4/17/2024 Approved MISAEL ESPARZA
Drywall Nailing 4/17/2024 Approved MISAEL ESPARZA
Footing/Foundation/Slab 4/17/2024 Approved MISAEL ESPARZA
Green Building Final 4/17/2024 Approved MISAEL ESPARZA
Protected Tree Letter 4/17/2024 Approved MISAEL ESPARZA
Reinforced Masonry Frame 4/17/2024 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 4/17/2024 SGSOV Approved MISAEL ESPARZA
Service/Power Release 4/17/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 4/17/2024 Approved MISAEL ESPARZA
Structural Steel Frame 4/17/2024 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 4/17/2024 Approved MISAEL ESPARZA
Final 4/18/2024 Corrections Issued MISAEL ESPARZA
HVAC-Final 4/18/2024 Corrections Issued MISAEL ESPARZA
Final 4/25/2024 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 4/25/2024 Approved MISAEL ESPARZA
Pre-Inspection 4/29/2024 Approved MISAEL ESPARZA