Pre-Inspection
|
4/4/2019
|
Approved
|
THOMAS FINNILA
|
|
Pre-Inspection
|
10/21/2019
|
Approved
|
THOMAS FINNILA
|
|
PLUMBING-Rough
|
10/31/2019
|
Corrections Issued
|
JOHN HAYES
|
|
PLUMBING-Rough
|
11/1/2019
|
Corrections Issued
|
RAYMOND KEHOE
|
|
Underground Mechanical
|
11/5/2019
|
Partial Approval
|
RAYMOND KEHOE
|
|
Footing/Foundation/Slab
|
12/5/2019
|
Partial Approval
|
JEFFREY PARD
|
|
Protected Tree Letter
|
12/5/2019
|
Not Ready for Inspection
|
JEFFREY PARD
|
|
Excavation/Setback/Form/Re-Bar
|
1/22/2020
|
Partial Approval
|
RAYMOND KEHOE
|
|
Excavation/Setback/Form/Re-Bar
|
2/13/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Sewer
|
3/31/2020
|
Corrections Issued
|
RAYMOND KEHOE
|
|
ELECTRICAL-Rough
|
4/22/2020
|
Partial Inspection
|
WILLIAM KUEHN
|
|
Masonry Wall/Backfill
|
4/22/2020
|
Partial Inspection
|
WILLIAM KUEHN
|
|
PLUMBING-Rough
|
4/22/2020
|
Partial Inspection
|
WILLIAM KUEHN
|
|
Excavation/Setback/Form/Re-Bar
|
4/24/2020
|
Not Ready for Inspection
|
MARK JOHNSON
|
|
Footing/Foundation/Slab
|
4/24/2020
|
Partial Approval
|
MARK JOHNSON
|
|
Protected Tree Letter
|
4/24/2020
|
Not Ready for Inspection
|
MARK JOHNSON
|
|
Footing/Foundation/Slab
|
4/29/2020
|
Corrections Issued
|
MISAEL ESPARZA
|
|
Footing/Foundation/Slab
|
4/30/2020
|
Partial Approval
|
MISAEL ESPARZA
|
|
Protected Tree Letter
|
4/30/2020
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Excavation/Setback/Form/Re-Bar
|
5/6/2020
|
Partial Approval
|
RAYMOND KEHOE
|
|
Reinforced Concrete Frame
|
5/14/2020
|
Corrections Issued
|
CHARLES POWELL
|
|
Piling/Pier/Caisson
|
5/18/2020
|
Approved
|
CHARLES POWELL
|
|
Special/Order Compliance
|
5/18/2020
|
Approved
|
CHARLES POWELL
|
|
Deputy Reinf. Concrete
|
5/21/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
6/4/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
6/12/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
6/29/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Masonry Wall/Backfill
|
7/8/2020
|
Approved
|
CHARLES POWELL
|
|
Deputy Reinf. Concrete
|
7/10/2020
|
Corrections Issued
|
CHARLES POWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/17/2020
|
Corrections Issued
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
7/22/2020
|
Corrections Issued
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
7/28/2020
|
Corrections Issued
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
8/10/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
8/13/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Footing/Foundation/Slab
|
8/13/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Protected Tree Letter
|
8/13/2020
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
8/17/2020
|
Corrections Issued
|
CHARLES POWELL
|
|
ELECTRICAL-Rough
|
8/19/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
8/19/2020
|
Partial Approval
|
CHARLES POWELL
|
|
PLUMBING-Rough
|
8/19/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Deputy Reinf. Concrete
|
8/24/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Reinforced Concrete Frame
|
9/8/2020
|
Approved
|
CHARLES POWELL
|
|
Sewer
|
9/10/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
12/9/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Footing/Foundation/Slab
|
12/9/2020
|
Partial Approval
|
CHARLES POWELL
|
|
Protected Tree Letter
|
12/9/2020
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
BUILDING-Rough-Frame
|
12/30/2020
|
Corrections Issued
|
CHARLES POWELL
|
|
Green Building Rough
|
12/30/2020
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Verify Sprinkler Sign Off
|
12/30/2020
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Excavation/Setback/Form/Re-Bar
|
1/12/2021
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/14/2021
|
Approved
|
CHARLES POWELL
|
|
BUILDING-Rough-Frame
|
1/28/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/28/2021
|
Approved
|
CHARLES POWELL
|
|
Verify Sprinkler Sign Off
|
1/28/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
ELECTRICAL-Rough
|
3/16/2021
|
Partial Approval
|
CHARLES POWELL
|
|
HVAC-Rough
|
3/16/2021
|
Partial Approval
|
CHARLES POWELL
|
|
PLUMBING-Rough
|
3/17/2021
|
Corrections Issued
|
CHARLES POWELL
|
|
ELECTRICAL-Rough
|
3/31/2021
|
Partial Approval
|
CHARLES POWELL
|
|
PLUMBING-Rough
|
3/31/2021
|
Corrections Issued
|
CHARLES POWELL
|
|
ELECTRICAL-Rough
|
4/8/2021
|
Corrections Issued
|
CHARLES POWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/12/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Green Building Rough
|
4/12/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Verify Sprinkler Sign Off
|
4/12/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Shower Pan
|
4/29/2021
|
Approved
|
CHARLES POWELL
|
|
BUILDING-Rough-Frame
|
5/10/2021
|
No Access for Inspection
|
CHARLES POWELL
|
|
Green Building Rough
|
5/10/2021
|
No Access for Inspection
|
CHARLES POWELL
|
|
Verify Sprinkler Sign Off
|
5/10/2021
|
No Access for Inspection
|
CHARLES POWELL
|
|
Wood Frame
|
5/17/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/15/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Interior/Exterior Lathing
|
6/15/2021
|
Partial Approval
|
CHARLES POWELL
|
|
PLUMBING-Rough
|
7/6/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Interior/Exterior Lathing
|
7/12/2021
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
BUILDING-Rough-Frame
|
7/13/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Green Building Rough
|
7/13/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Interior/Exterior Lathing
|
7/13/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Verify Sprinkler Sign Off
|
7/13/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
BUILDING-Rough-Frame
|
7/20/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Green Building Rough
|
7/20/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Verify Sprinkler Sign Off
|
7/20/2021
|
Corrections Issued
|
CHARLES POWELL
|
|
Insulation
|
7/27/2021
|
Partial Approval
|
JAVIER RAMOS JR
|
|
BUILDING-Rough-Frame
|
8/3/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Green Building Rough
|
8/3/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
Insulation
|
8/3/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Interior/Exterior Lathing
|
8/12/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Drywall Nailing
|
8/13/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Insulation
|
8/13/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Special/Order Compliance
|
8/13/2021
|
Corrections Issued
|
MICHAEL PELHAM
|
|
Drywall Nailing
|
9/3/2021
|
Partial Approval
|
CHARLES POWELL
|
|
Green Building Rough
|
9/3/2021
|
Not Ready for Inspection
|
CHARLES POWELL
|
|
BUILDING-Rough-Frame
|
9/17/2021
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Grading Pre-Inspection
|
9/17/2021
|
Partial Inspection
|
MISAEL ESPARZA
|
|
Green Building Rough
|
9/17/2021
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Interior/Exterior Lathing
|
9/17/2021
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Verify Sprinkler Sign Off
|
9/17/2021
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
BUILDING-Rough-Frame
|
10/14/2021
|
Partial Approval
|
MISAEL ESPARZA
|
|
Green Building Rough
|
10/14/2021
|
Approved
|
MISAEL ESPARZA
|
|
Verify Sprinkler Sign Off
|
10/14/2021
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Insulation
|
10/19/2021
|
Approved
|
ASHLEY THOMPSON
|
|
Drywall Nailing
|
10/28/2021
|
Partial Approval
|
MARK JOHNSON
|
|
Pre-Inspection
|
4/25/2022
|
Approved
|
MISAEL ESPARZA
|
|
Excavation/Setback/Form/Re-Bar
|
7/13/2022
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Service/Power Release
|
7/20/2022
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Excavation/Setback/Form/Re-Bar
|
1/27/2023
|
Partial Inspection
|
MISAEL ESPARZA
|
|
PLUMBING-Final
|
4/4/2023
|
Corrections Issued
|
MISAEL ESPARZA
|
|
PLUMBING-Final
|
4/26/2023
|
Not Ready for Inspection
|
THOMAS FINNILA
|
|
PLUMBING-Final
|
5/30/2023
|
Partial Inspection
|
JOHN COLEMAN
|
|
ELECTRICAL-Final
|
6/5/2023
|
Not Ready for Inspection
|
JACK KARGODORIAN
|
|
ELECTRICAL-Final
|
6/6/2023
|
Corrections Issued
|
JUAN VALENZUELA
|
|
ELECTRICAL-Final
|
6/12/2023
|
Corrections Issued
|
JOHN COLEMAN
|
|
ELECTRICAL-Final
|
7/21/2023
|
Partial Inspection
|
MISAEL ESPARZA
|
|
PLUMBING-Final
|
10/30/2023
|
Corrections Issued
|
MISAEL ESPARZA
|
|
Gas Test
|
11/15/2023
|
Approved
|
MISAEL ESPARZA
|
|
PLUMBING-Final
|
11/15/2023
|
Approved
|
MISAEL ESPARZA
|
|
Grounding or Bonding
|
11/20/2023
|
Partial Inspection
|
MISAEL ESPARZA
|
|
BUILDING-Rough-Frame
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Drywall Nailing
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Footing/Foundation/Slab
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Green Building Final
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Protected Tree Letter
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Reinforced Masonry Frame
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
SGSOV-Seismic Gas S/O Valve
|
4/17/2024
|
SGSOV Approved
|
MISAEL ESPARZA
|
|
Service/Power Release
|
4/17/2024
|
Not Ready for Inspection
|
MISAEL ESPARZA
|
|
Smoke Detectors
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Structural Steel Frame
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Verify Sprinkler Sign Off
|
4/17/2024
|
Approved
|
MISAEL ESPARZA
|
|
Final
|
4/18/2024
|
Corrections Issued
|
MISAEL ESPARZA
|
|
HVAC-Final
|
4/18/2024
|
Corrections Issued
|
MISAEL ESPARZA
|
|
Final
|
4/25/2024
|
OK to Issue CofO
|
MISAEL ESPARZA
|
|
Service/Power Release
|
4/25/2024
|
Approved
|
MISAEL ESPARZA
|
|
Pre-Inspection
|
4/29/2024
|
Approved
|
MISAEL ESPARZA
|