8732 W ST IVES DR 90069
Certificate Information: 8732 W ST IVES DR 90069
- Application / Permit
- 15010-10000-03086
- Plan Check / Job No.
- B15LA12236
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story SFD w/ basement & attached 4-car garage with carlift & retaining wall below w/ shoring; Overall dimensions 66'1" x 64'0"
- Permit Issued
- Issued on 2/19/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2015 | KRIKOR MANOUKIAN |
| Corrections Issued | 9/30/2015 | KRIKOR MANOUKIAN |
| Quality Review Completed | 10/2/2015 | GARO TELMI |
| Building Plans Picked Up | 10/5/2015 | APPLICANT |
| Green Plans Picked Up | 10/5/2015 | APPLICANT |
| Plan Check Approved | 2/19/2016 | KRIKOR MANOUKIAN |
| Issued | 2/19/2016 | LADBS |
| Intent to Revoke-Status Void | 6/13/2019 | CATHERINE NUEZCA GABA |
| Re-Activate Permit | 8/15/2019 | CATHERINE NUEZCA GABA |
| Intent to Revoke-Status Void | 4/8/2020 | VICTOR CUEVAS |
| Re-Activate Permit | 10/16/2020 | VICTOR CUEVAS |
| CofO in Progress | 11/19/2024 | RAUL BARAJAS |
| Permit Finaled | 11/20/2024 | RUBEN SALAS |
| CofO Issued | 11/20/2024 | RUBEN SALAS |
| Permit Finaled | 11/20/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/16/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 11/16/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 11/16/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 11/16/2015 | ARMENIA HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2015 | ARMENIA HERNANDEZ |
| BHO/Hillside ordinance | Cleared | 11/18/2015 | ARMENIA HERNANDEZ |
| Hydrant and Access approval | Cleared | 11/19/2015 | ROBERT DUFF |
| Permit | Cleared | 11/23/2015 | ARMENIA HERNANDEZ |
| Green Code | Cleared | 12/14/2015 | RUSSELL KELLY |
| Miscellaneous | Cleared | 1/19/2016 | ARMENIA HERNANDEZ |
| Sewer availability | Cleared | 1/20/2016 | JAMES KHO |
| Low Impact Development | Cleared | 2/4/2016 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/4/2016 | JAMES KHO |
| Work Adjacent to Public Way | Cleared | 2/4/2016 | WARREN LIU |
| Building over 3-story or 36-ft | Cleared | 2/11/2016 | CALOSHA APPROVED |
| CMU Activity Summary | Cleared | 2/11/2016 | KRIKOR MANOUKIAN |
| Excavation more than 5-ft deep | Cleared | 2/11/2016 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/11/2016 | KRIKOR MANOUKIAN |
| Grading Pre-Inspection | Cleared | 2/11/2016 | KRIKOR MANOUKIAN |
| Miscellaneous | Cleared | 2/19/2016 | KRIKOR MANOUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Babayan, Raffi Samuel; Lic. No.: C72168 | 1140 N COLUMBUS AVE 112 GLENDALE, CA 91202 |
| Engineer | De, Leon Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Resnick, Bruce Daniel; Lic. No.: S3293 | 1927 PONTIUS AVE LOS ANGELES, CA 90025 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 9/8/2016 | Approved | JOEL WILLIAMS |
| Deputy Grading | 9/9/2016 | Approved | DANNY TOLENTINO |
| Deputy Grading | 9/14/2016 | Approved | DANNY TOLENTINO |
| Deputy Grading | 9/15/2016 | Conditional Approval | DANNY TOLENTINO |
| Piling/Pier/Caisson | 9/15/2016 | Partial Inspection | DANNY TOLENTINO |
| Deputy Grading | 9/16/2016 | Approved | JOEL WILLIAMS |
| Footing/Foundation/Slab | 9/16/2016 | Partial Approval | JOEL WILLIAMS |
| Piling/Pier/Caisson | 9/26/2016 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 10/3/2016 | No Access for Inspection | BRAD BESCOS |
| Footing/Foundation/Slab | 10/4/2016 | Corrections Issued | BRAD BESCOS |
| Piling/Pier/Caisson | 10/5/2016 | Partial Approval | JOEL WILLIAMS |
| Deputy Reinf. Concrete | 10/12/2016 | Approved | BRAD BESCOS |
| Footing/Foundation/Slab | 10/12/2016 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 10/13/2016 | No Access for Inspection | BRAD BESCOS |
| Piling/Pier/Caisson | 10/20/2016 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 10/21/2016 | No Access for Inspection | BRAD BESCOS |
| Piling/Pier/Caisson | 10/31/2016 | Partial Approval | BRAD BESCOS |
| Footing/Foundation/Slab | 11/8/2016 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 11/22/2016 | Approved | BRAD BESCOS |
| Deputy Steel/Welding | 12/1/2016 | Approved | BRAD BESCOS |
| Deputy Reinf. Concrete | 12/5/2016 | Approved | BRAD BESCOS |
| Piling/Pier/Caisson | 12/5/2016 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 12/9/2016 | Approved | BRAD BESCOS |
| Piling/Pier/Caisson | 12/9/2016 | Partial Approval | BRAD BESCOS |
| Piling/Pier/Caisson | 12/15/2016 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 12/21/2016 | No Access for Inspection | BRAD BESCOS |
| Piling/Pier/Caisson | 12/21/2016 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 12/28/2016 | No Access for Inspection | BRAD BESCOS |
| Footing/Foundation/Slab | 2/2/2017 | Partial Approval | JOEL WILLIAMS |
| Deputy Reinf. Concrete | 2/8/2017 | No Access for Inspection | BRAD BESCOS |
| Deputy Reinf. Concrete | 5/17/2017 | No Access for Inspection | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 5/26/2017 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 7/25/2017 | Approved | BRAD BESCOS |
| Piling/Pier/Caisson | 7/25/2017 | Partial Approval | BRAD BESCOS |
| Deputy Reinf. Concrete | 8/2/2017 | No Access for Inspection | BRAD BESCOS |
| Piling/Pier/Caisson | 8/2/2017 | Partial Approval | BRAD BESCOS |
| Deputy Grading | 8/30/2017 | Approved | BRAD BESCOS |
| Deputy Grading | 9/7/2017 | No Access for Inspection | BRAD BESCOS |
| Deputy Grading | 9/11/2017 | Approved | BRAD BESCOS |
| Piling/Pier/Caisson | 9/26/2017 | Partial Approval | JOEL WILLIAMS |
| Footing/Foundation/Slab | 12/28/2017 | Partial Approval | JOEL WILLIAMS |
| Footing/Foundation/Slab | 2/5/2018 | Partial Approval | DANNY TOLENTINO |
| Special/Order Compliance | 2/14/2018 | Corrections Issued | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 2/22/2018 | Partial Inspection | DANIEL GONZALEZ |
| Deputy Reinf. Concrete | 3/16/2018 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 3/16/2018 | Not Ready for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 3/23/2018 | Partial Approval | DANIEL GONZALEZ |
| Special/Order Compliance | 3/29/2018 | Corrections Issued | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 4/20/2018 | Partial Approval | DANIEL GONZALEZ |
| Deputy Reinf. Concrete | 4/23/2018 | Partial Approval | DANIEL GONZALEZ |
| Grounding or Bonding | 4/30/2018 | Not Ready for Inspection | DANNY TOLENTINO |
| PLUMBING-Rough | 4/30/2018 | Partial Approval | DANNY TOLENTINO |
| ELECTRICAL-Rough | 5/15/2018 | Partial Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 5/15/2018 | Partial Inspection | DANIEL GONZALEZ |
| PLUMBING-Rough | 5/15/2018 | Partial Inspection | DANIEL GONZALEZ |
| Piling/Pier/Caisson | 5/16/2018 | Conditional Approval | ROBERT MINASSIANS |
| Deputy Reinf. Concrete | 5/31/2018 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 5/31/2018 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 6/14/2018 | Partial Inspection | DANIEL GONZALEZ |
| Deputy Reinf. Concrete | 6/26/2018 | No Access for Inspection | DANNY TOLENTINO |
| Footing/Foundation/Slab | 7/2/2018 | Partial Approval | DANNY TOLENTINO |
| Deputy Reinf. Concrete | 7/6/2018 | No Access for Inspection | DANNY TOLENTINO |
| ELECTRICAL-Rough | 8/1/2018 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 8/1/2018 | Partial Approval | DANIEL GONZALEZ |
| PLUMBING-Rough | 8/1/2018 | Partial Approval | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 9/10/2018 | Partial Approval | DANIEL GONZALEZ |
| Deputy Reinf. Concrete | 9/11/2018 | Conditional Approval | ROBERT MINASSIANS |
| Deputy Reinf. Concrete | 9/12/2018 | No Access for Inspection | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 4/11/2019 | Corrections Issued | DANNY TOLENTINO |
| Deputy Reinf. Concrete | 4/26/2019 | Conditional Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/29/2019 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 5/8/2019 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/3/2019 | Partial Approval | DANNY TOLENTINO |
| Special/Order Compliance | 9/5/2019 | Partial Inspection | RICHARD STEINBACH |
| Special/Order Compliance | 9/6/2019 | Partial Inspection | RICHARD STEINBACH |
| Footing/Foundation/Slab | 9/20/2019 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 10/3/2019 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 10/22/2019 | Partial Approval | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 10/22/2019 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 12/17/2019 | Conditional Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 12/19/2019 | Partial Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 2/12/2020 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 2/13/2020 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 3/6/2020 | Conditional Approval | RICHARD STEINBACH |
| Special/Order Compliance | 4/8/2020 | Order to Comply Issued | RUBEN SALAS |
| Special/Order Compliance | 10/20/2020 | No Access for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 12/16/2020 | Partial Inspection | RAUL BARAJAS |
| Special/Order Compliance | 1/15/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/19/2021 | Partial Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 1/19/2021 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 1/19/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 3/4/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 3/4/2021 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/4/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 3/25/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 3/25/2021 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/25/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 4/27/2021 | No Access for Inspection | RAUL BARAJAS |
| Green Building Rough | 4/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 4/27/2021 | Partial Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 4/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Rough | 5/25/2021 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 5/25/2021 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 5/25/2021 | Partial Approval | RAUL BARAJAS |
| Reinforced Concrete Frame | 5/25/2021 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 5/25/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 10/21/2021 | Order to Comply Issued | BRAD BESCOS |
| PLUMBING-Rough | 6/10/2022 | Approved | RAUL BARAJAS |
| Shower Pan | 9/2/2022 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/31/2023 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Final | 10/31/2023 | Corrections Issued | RAUL BARAJAS |
| Service/Power Release | 10/31/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 12/8/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 12/8/2023 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 12/18/2023 | Partial Inspection | STUART CHAPMAN |
| Service/Power Release | 12/18/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 12/26/2023 | Corrections Issued | RAUL BARAJAS |
| Service/Power Release | 1/22/2024 | Partial Inspection | RAUL BARAJAS |
| Service/Power Release | 1/31/2024 | Approved | RAUL BARAJAS |
| Pre-Inspection | 3/18/2024 | Partial Inspection | RAUL BARAJAS |
| Gas Test | 4/23/2024 | Approved | ROY SPAULDING |
| PLUMBING-Final | 4/23/2024 | Approved | ROY SPAULDING |
| HVAC-Final | 4/29/2024 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/29/2024 | SGSOV Approved | RAUL BARAJAS |
| HVAC-Final | 7/15/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 7/22/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 7/31/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/6/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Drywall Nailing | 8/6/2024 | Approved | RAUL BARAJAS |
| Final | 8/6/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 8/6/2024 | Approved | RAUL BARAJAS |
| Green Building Final | 8/6/2024 | Approved | RAUL BARAJAS |
| Green Building Rough | 8/6/2024 | Approved | RAUL BARAJAS |
| Reinforced Concrete Frame | 8/6/2024 | Approved | RAUL BARAJAS |
| Smoke Detectors | 8/6/2024 | No Access for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 8/6/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/9/2024 | Approved | RAUL BARAJAS |
| Final | 8/9/2024 | Partial Inspection | RAUL BARAJAS |
| Smoke Detectors | 8/9/2024 | Approved | RAUL BARAJAS |
| Final | 11/19/2024 | OK to Issue CofO | RAUL BARAJAS |