1624 N MICHELTORENA ST 90026

Certificate Information: 1624 N MICHELTORENA ST 90026

Application / Permit
15010-10000-02868
Plan Check / Job No.
B15LA11267
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 3-STORY SFD WITH ATTACHED GARAGE LEVEL. SMALL LOT SUBDIVISION PURSUANT TO TENTATIVE PARCEL MAP AA 2014-4159-PMLA-SL. A CERTIFICATE OF OCCUPANCY (TEMPORARY OR FINAL) SHALL NOT BE ISSUED UNTIL AFTER THE FINAL MAP HAS BEEN RECORDED. (PARCEL A)
Permit Issued
Issued on 1/16/2018
Issuing Office
Metro
Current Status
CofO Issued on 2/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2015 APPLICANT
Disabled Access Plans Picked Up 9/9/2015 APPLICANT
Assigned to Plan Check Engineer 9/17/2015 LAWRENCE QUIRANTE
Green Plans Picked Up 9/18/2015 APPLICANT
Corrections Issued 9/29/2015 LAWRENCE QUIRANTE
Quality Review Completed 10/9/2015 BILL STUTSMAN
Building Plans Picked Up 10/27/2015 APPLICANT
Applicant returned to address corrections 3/8/2016 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/25/2016 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/8/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/15/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 3/16/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/27/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 5/23/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 6/5/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 6/22/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 6/28/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 7/11/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 8/30/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/8/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/12/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/14/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/19/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/26/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/28/2017 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/4/2017 LAWRENCE QUIRANTE
Plan Check Approved 10/16/2017 LAWRENCE QUIRANTE
Issued 1/16/2018 LADBS
CofO in Progress 2/17/2022 SCOTT FINNILA
Permit Finaled 2/17/2022 DEROLD HAUFF
CofO Issued 2/17/2022 DEROLD HAUFF
Permit Finaled 2/17/2022 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 2/26/2016 MICHAEL SCADUTO
Address approval Cleared 9/1/2016 RAVIL MANAPOV
DAS Clearance Cleared 9/12/2016 SHINE LIN
Hydrant and Access approval Cleared 9/12/2016 JOHN CONNEALLY
Highway dedication Cleared 12/19/2016 SEVAK ISAKHAYAN
Work Adjacent to Public Way Cleared 2/7/2017 DAVID PEREZ
Miscellaneous Cleared 2/9/2017 BRIAN CARR
Tract Map conditions Cleared 2/16/2017 GRACIELA ACOSTA
Building over 3-story or 36-ft Cleared 2/22/2017 CALOSHA APPROVED
Grading Pre-Inspection Cleared 2/22/2017 ROBERT HUGHES
Eng Process Fee Ord 176,300 Cleared 3/2/2017 ADRIAN SANCHEZ
Sewer availability Cleared 3/2/2017 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 3/13/2017 DAISY BENICIA
Miscellaneous Cleared 7/20/2017 MARITZA PRZEKOP
Green Code Cleared 10/3/2017 JOHN KLARIN
Roof/Waste drainage to street Cleared 10/5/2017 ZEMAMU GEBREWOLD
Miscellaneous Cleared 10/12/2017 ZEMAMU GEBREWOLD
Permit Cleared 10/12/2017 ZEMAMU GEBREWOLD

Contact Information

Architect Thibodeau, Robert E; Lic. No.: C25585 529 CALIFORNIA AVENUE      VENICE, CA 90291
Contractor Ridge Inc; Lic. No.: 934983-B 4541 FORMAN AVE      TOLUCA LAKE, CA 91602
Engineer Karakanov, Valeri Kirilov; Lic. No.: C70785 423 EAST PROVIDENCIA AVE 103      BURBANK, CA 91501
Engineer Mahn, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/3/2018 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 4/6/2018 Partial Approval SCOTT FINNILA
Deputy Reinf. Concrete 4/9/2018 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 4/19/2018 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/3/2018 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/9/2018 No Access for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 5/10/2018 Not Ready for Inspection SCOTT FINNILA
Final 5/10/2018 Not Ready for Inspection SCOTT FINNILA
Footing/Foundation/Slab 5/10/2018 Partial Approval SCOTT FINNILA
Green Building Final 5/10/2018 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 5/10/2018 Not Ready for Inspection SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 5/10/2018 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 5/10/2018 Not Ready for Inspection SCOTT FINNILA
Smoke Detectors 5/10/2018 Not Ready for Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 5/10/2018 Not Ready for Inspection SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 5/22/2018 Partial Approval DOMINIC DANERI
Deputy Reinf. Concrete 5/25/2018 Partial Approval SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/25/2018 Corrections Issued SCOTT FINNILA
Excavation/Setback/Form/Re-Bar 6/26/2018 Partial Approval SCOTT FINNILA
Deputy Wood Construction 7/31/2018 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/2/2018 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 9/27/2018 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/27/2018 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 12/14/2018 Partial Approval SCOTT FINNILA
Green Building Rough 12/14/2018 Not Ready for Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 12/14/2018 Not Ready for Inspection SCOTT FINNILA
Drywall Nailing 1/24/2019 Not Ready for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/24/2019 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 2/12/2019 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 5/10/2019 Corrections Issued SCOTT FINNILA
HVAC-Rough 5/10/2019 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 5/10/2019 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 5/22/2019 Partial Inspection SCOTT FINNILA
HVAC-Rough 5/22/2019 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 5/22/2019 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/31/2019 No Access for Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/5/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 8/16/2019 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 9/23/2019 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/28/2019 Corrections Issued SCOTT FINNILA
Gas Test 10/28/2019 Not Ready for Inspection SCOTT FINNILA
Green Building Rough 10/28/2019 Corrections Issued SCOTT FINNILA
HVAC-Rough 10/28/2019 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 10/28/2019 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 11/15/2019 Corrections Issued SCOTT FINNILA
Rough-Elec/Plmb/HVAC 11/19/2019 Not Ready for Inspection SCOTT FINNILA
BUILDING-Rough-Frame 1/14/2020 Corrections Issued BRAD BESCOS
ELECTRICAL-Rough 1/17/2020 Partial Approval SCOTT FINNILA
HVAC-Rough 1/17/2020 Approved SCOTT FINNILA
PLUMBING-Rough 1/17/2020 Partial Approval SCOTT FINNILA
Insulation 1/27/2020 Approved SCOTT FINNILA
Drywall Nailing 3/2/2020 Conditional Approval SCOTT FINNILA
Interior/Exterior Lathing 3/2/2020 Partial Approval SCOTT FINNILA
Shower Pan 3/2/2020 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 4/15/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 5/18/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 5/18/2020 Not Ready for Inspection ENRIQUE MIRELES
Underground Mechanical 5/26/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/8/2020 Partial Approval SCOTT FINNILA
Sewer 10/22/2020 Corrections Issued SCOTT FINNILA
Underground Mechanical 10/22/2020 Corrections Issued SCOTT FINNILA
Sewer 10/30/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 10/30/2020 Partial Approval SCOTT FINNILA
Sewer 11/30/2020 Partial Approval ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 12/14/2020 No Access for Inspection SCOTT FINNILA
Underground Mechanical 12/14/2020 No Access for Inspection SCOTT FINNILA
Rough-Elec/Plmb/HVAC 12/16/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 12/22/2020 Partial Approval SCOTT FINNILA
Rough-Elec/Plmb/HVAC 12/22/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 12/28/2020 Approved SCOTT FINNILA
Final 2/5/2021 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 2/5/2021 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 4/14/2021 Approved SCOTT FINNILA
Final 4/14/2021 Partial Inspection SCOTT FINNILA
Footing/Foundation/Slab 4/14/2021 Approved SCOTT FINNILA
Green Building Final 4/14/2021 Partial Inspection SCOTT FINNILA
Green Building Rough 4/14/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 4/14/2021 SGSOV Not Ready SCOTT FINNILA
Service/Power Release 4/14/2021 Partial Inspection SCOTT FINNILA
Sewer 4/14/2021 Partial Inspection SCOTT FINNILA
Smoke Detectors 4/14/2021 Partial Inspection SCOTT FINNILA
Verify Sprinkler Sign Off 4/14/2021 Approved SCOTT FINNILA
Gas Test 5/11/2021 Approved SCOTT FINNILA
PLUMBING-Final 6/22/2021 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 10/12/2021 SGSOV Not Ready SCOTT FINNILA
Final 12/17/2021 Corrections Issued SCOTT FINNILA
Green Building Final 12/17/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/17/2021 SGSOV Approved SCOTT FINNILA
Service/Power Release 12/17/2021 Corrections Issued SCOTT FINNILA
Smoke Detectors 12/17/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 1/14/2022 No Access for Inspection SCOTT FINNILA
Service/Power Release 1/18/2022 Approved SCOTT FINNILA
HVAC-Final 1/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/20/2022 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 2/4/2022 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 2/4/2022 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 2/16/2022 Approved SCOTT FINNILA
Final 2/17/2022 OK to Issue CofO SCOTT FINNILA