16613 S FIGUEROA ST 90248
Certificate Information: 16613 S FIGUEROA ST 90248
- Application / Permit
- 15010-10000-02645
- Plan Check / Job No.
- B15LA10267
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- A NEW ON GRADE 3 STORY COMMERCIAL/RESIDENTIAL MIXED USE BUILDING
- Permit Issued
- Issued on 4/16/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/24/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/24/2015 | APPLICANT |
| Disabled Access Plans Picked Up | 8/21/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2015 | LARRY LEE |
| Green Plans Picked Up | 8/28/2015 | APPLICANT |
| Corrections Issued | 9/9/2015 | LARRY LEE |
| Quality Review Completed | 9/14/2015 | BILL STUTSMAN |
| Building Plans Picked Up | 9/18/2015 | APPLICANT |
| Applicant returned to address corrections | 6/13/2017 | LARRY LEE |
| Applicant returned to address corrections | 7/7/2017 | LARRY LEE |
| Applicant returned to address corrections | 8/23/2017 | LARRY LEE |
| Applicant returned to address corrections | 8/29/2017 | LARRY LEE |
| Applicant returned to address corrections | 1/22/2018 | LARRY LEE |
| Plan Check Approved | 4/11/2018 | LARRY LEE |
| Issued | 4/16/2018 | LADBS |
| CofO in Progress | 11/24/2021 | JOEY BUCHANAN |
| Permit Finaled | 11/24/2021 | NICK LAROCCA |
| CofO Issued | 11/24/2021 | NICK LAROCCA |
| Permit Finaled | 11/24/2021 | NICK LAROCCA |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 9/18/2015 | ROBERT DUFF |
| Green Code | Cleared | 1/6/2017 | MICKEY YAMASHITA |
| Address approval | Cleared | 6/2/2017 | ROCHELLE DUNGCA |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2017 | ROCHELLE DUNGCA |
| Opn space landscape/Water mgmt | Cleared | 6/9/2017 | EDBER MACEDO |
| Prkng lot landscape/Water mgmt | Cleared | 6/9/2017 | EDBER MACEDO |
| Low Impact Development | Cleared | 6/15/2017 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 6/15/2017 | RAVIL MANAPOV |
| Stormwater Pollution Mitigatn | Cleared | 6/15/2017 | AMMAR ELTAWIL |
| DAS Clearance | Cleared | 7/12/2017 | SHINE LIN |
| Sewer availability | Cleared | 7/14/2017 | JAMES MORALEZ |
| Fire Marshall Fire Life Safety | Cleared | 7/19/2017 | DAVE MYERS |
| Food Service Establishment | Cleared | 8/4/2017 | PAWAN VERMA |
| Driveway location | Cleared | 9/21/2017 | CLIVE GRAWE |
| Highway dedication | Cleared | 9/28/2017 | WESLEY LUONG |
| Permit | Cleared | 9/28/2017 | WESLEY LUONG |
| Food establishment approval | Cleared | 1/22/2018 | LACDHS APPROVED |
Contact Information
| Architect | Saroian, Varoozh; Lic. No.: C13791 | 128 S KENWOOD STREET GLENDALE, CA 91205 |
| Engineer | Kamkar, Albert; Lic. No.: C38311 | 12340 SANTA MONICA BLVD 236 SANTA MONICA, CA 90025 |
| Engineer | Minas, Caro Jolfaie; Lic. No.: GE601 | 4742 SAN FERNANDO RD GLENDALE, CA 91204 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/24/2018 | Approved | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 6/13/2018 | Partial Approval | NICK LAROCCA |
| Footing/Foundation/Slab | 6/13/2018 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 6/15/2018 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 6/15/2018 | Partial Inspection | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 6/22/2018 | Partial Approval | NICK LAROCCA |
| Footing/Foundation/Slab | 6/22/2018 | Partial Approval | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 6/25/2018 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 6/28/2018 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 6/28/2018 | Partial Approval | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 6/29/2018 | Partial Inspection | NICK LAROCCA |
| Masonry Wall/Backfill | 7/10/2018 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Masonry | 7/11/2018 | Approved | NICK LAROCCA |
| Masonry Wall/Backfill | 7/11/2018 | Partial Approval | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 7/19/2018 | Partial Inspection | NICK LAROCCA |
| Green Building Rough | 7/19/2018 | Approved | NICK LAROCCA |
| Reinforced Masonry Frame | 7/19/2018 | Partial Approval | NICK LAROCCA |
| Verify Sprinkler Sign Off | 7/19/2018 | Not Ready for Inspection | NICK LAROCCA |
| Deputy Reinf. Masonry | 7/20/2018 | Approved | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 7/31/2018 | Approved | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 8/1/2018 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Masonry | 8/10/2018 | Approved | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 8/10/2018 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 8/13/2018 | Conditional Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 8/17/2018 | Approved | RAFAEL ESPINOZA |
| Masonry Wall/Backfill | 8/17/2018 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Reinf. Masonry | 8/20/2018 | Conditional Approval | RAFAEL ESPINOZA |
| Excavation/Setback/Form/Re-Bar | 8/27/2018 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Masonry | 8/28/2018 | Conditional Approval | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 10/12/2018 | Partial Inspection | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 1/14/2019 | Partial Inspection | NICK LAROCCA |
| Footing/Foundation/Slab | 4/15/2019 | Partial Inspection | NICK LAROCCA |
| Excavation/Setback/Form/Re-Bar | 5/15/2019 | Partial Approval | NICK LAROCCA |
| Footing/Foundation/Slab | 5/15/2019 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 7/8/2019 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 8/20/2019 | Partial Approval | NICK LAROCCA |
| Deputy Reinf. Concrete | 8/30/2019 | Approved | NICK LAROCCA |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2019 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2019 | Corrections Issued | NICK LAROCCA |
| Wood Frame | 11/22/2019 | Partial Approval | RAFAEL ESPINOZA |
| Deputy Wood Construction | 12/3/2019 | Approved | NICK LAROCCA |
| Wood Frame | 12/5/2019 | Partial Approval | NICK LAROCCA |
| Drywall Nailing | 12/12/2019 | Partial Approval | NICK LAROCCA |
| Drywall Nailing | 12/18/2019 | Partial Approval | NICK LAROCCA |
| Deputy Wood Construction | 1/2/2020 | Approved | NICK LAROCCA |
| Wood Frame | 1/6/2020 | Partial Approval | NICK LAROCCA |
| Interior/Exterior Lathing | 2/20/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 3/9/2020 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 3/18/2020 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 4/8/2020 | Partial Approval | JOEY BUCHANAN |
| Special/Order Compliance | 4/22/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 4/28/2020 | Partial Approval | JOEY BUCHANAN |
| Special/Order Compliance | 5/15/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 7/28/2020 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 7/29/2020 | Corrections Issued | JOEY BUCHANAN |
| Wood Frame | 8/7/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 9/3/2020 | Approved | JOEY BUCHANAN |
| Masonry Wall/Backfill | 9/4/2020 | Approved | NICK LAROCCA |
| Footing/Foundation/Slab | 9/9/2020 | Not Ready for Inspection | NICK LAROCCA |
| Deputy Drilled-In Anchors | 9/10/2020 | Conditional Approval | NICK LAROCCA |
| Deputy Steel/Welding | 9/24/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 10/9/2020 | Partial Approval | JOEY BUCHANAN |
| Insulation | 10/21/2020 | Partial Approval | JOEY BUCHANAN |
| Drywall Nailing | 10/28/2020 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Masonry | 11/18/2020 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 12/17/2020 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 1/11/2021 | Partial Approval | NICK LAROCCA |
| Wood Frame | 2/4/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Special/Order Compliance | 2/5/2021 | Approved | LEOPOLDO MENDOZA |
| Insulation | 2/11/2021 | Partial Approval | JOEY BUCHANAN |
| Special/Order Compliance | 2/17/2021 | Approved | JOEY BUCHANAN |
| Drywall Nailing | 2/23/2021 | Partial Inspection | JOEY BUCHANAN |
| Special/Order Compliance | 3/18/2021 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 3/24/2021 | Approved | JOEY BUCHANAN |
| T-Bar Ceiling | 4/20/2021 | Not Ready for Inspection | NICK LAROCCA |
| Special/Order Compliance | 4/22/2021 | Partial Approval | NICK LAROCCA |
| Special/Order Compliance | 4/29/2021 | Corrections Issued | JOEY BUCHANAN |
| Special/Order Compliance | 6/18/2021 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 7/21/2021 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 7/28/2021 | Approved | JOEY BUCHANAN |
| Final | 8/10/2021 | Corrections Issued | JOEY BUCHANAN |
| Footing/Foundation/Slab | 8/10/2021 | Approved | JOEY BUCHANAN |
| Green Building Final | 8/10/2021 | Approved | JOEY BUCHANAN |
| Reinforced Masonry Frame | 8/10/2021 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 8/10/2021 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 8/10/2021 | Approved | JOEY BUCHANAN |
| Final | 8/18/2021 | Corrections Issued | JOEY BUCHANAN |
| Pre-Inspection | 8/19/2021 | Corrections Issued | JOEY BUCHANAN |
| Final | 8/24/2021 | Not Ready for Inspection | JOEY BUCHANAN |
| Final | 11/19/2021 | Conditional Approval | JOEY BUCHANAN |