1000 W TEMPLE ST 90012

Certificate Information: 1000 W TEMPLE ST 90012

Application / Permit
15010-10000-02603
Plan Check / Job No.
B15LA10007
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW SEVEN STORY MIXED USE BUILDING WITH TWO LEVELS OF SUBTERANEAN GARAGE.
Permit Issued
Issued on 6/27/2018
Issuing Office
West Los Angeles
Current Status
Issued on 6/27/2018
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/27/2015 APPLICANT
Assigned to Plan Check Engineer 8/13/2015 KAMRAN GHOTBI RAVANDI
Disabled Access Plans Picked Up 8/13/2015 APPLICANT
Corrections Issued 9/8/2015 KAMRAN GHOTBI RAVANDI
Quality Review Completed 9/8/2015 ARA SARGSYAN
Green Plans Picked Up 11/12/2015 APPLICANT
Applicant returned to address corrections 2/5/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/9/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/18/2016 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 6/20/2017 KAMRAN GHOTBI RAVANDI
Plan Check Approved 6/27/2018 KAMRAN GHOTBI RAVANDI
Issued 6/27/2018 LADBS
Building Plans Picked Up 9/29/2022 APPLICANT
TCO Issued (Expire Date: 05-09-2023) 11/10/2022 ERNESTO CORRAL
TCO Issued (Expire Date: 11-28-2023) 6/1/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 06-01-2024) 12/4/2023 ERNESTO CORRAL
TCO Issued (Expire Date: 12-03-2024) 6/6/2024 ADAM BURGESS
TCO Issued (Expire Date: 05-18-2025) 11/19/2024 ERNESTO CORRAL
TCO Issued (Expire Date: 11-18-2025) 5/22/2025 ADAM BURGESS
TCO Issued (Expire Date: 05-11-2026) 11/12/2025 ERNESTO CORRAL
TCO Issued (Expire Date: 06-16-2026) 12/18/2025 RAFAEL ESPINOZA

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 3/29/2018 BRIAN CARR
Miscellaneous Cleared 3/29/2018 BRIAN CARR
Prkng lot landscape/Water mgmt Cleared 3/29/2018 BRIAN CARR
Site Plan review Cleared 3/29/2018 BRIAN CARR
ZA Case Cleared 3/29/2018 BRIAN CARR
ZA Case Cleared 3/29/2018 BRIAN CARR
ZA Case Cleared 3/29/2018 BRIAN CARR
ZA Case Cleared 3/29/2018 BRIAN CARR
ZI Cleared 3/29/2018 BRIAN CARR
Address approval Cleared 4/11/2018 CARLA VALLADARES
Hydrant and Access approval Cleared 4/20/2018 JOHN DALLAS
Eng Process Fee Ord 176,300 Cleared 4/24/2018 KAREN LE
Work Adjacent to Public Way Cleared 4/25/2018 TERRY PHAN
HPOZ Cleared 5/4/2018 LAMBERT GIESSINGER
Sewer availability Cleared 5/8/2018 JAMES KHO
DAS Clearance Cleared 5/17/2018 SHINE LIN
Highway dedication Cleared 5/24/2018 ADRIAN SANCHEZ
Driveway location Cleared 5/29/2018 MOHAMMAD HASAN
Green Code Cleared 5/29/2018 RUSSELL KELLY
Internal circulation Cleared 5/29/2018 MOHAMMAD HASAN
Miscellaneous Cleared 5/29/2018 MOHAMMAD HASAN
Specific Plan Cleared 5/29/2018 MOHAMMAD HASAN
Construction near power lines Cleared 6/1/2018 OSCAR CASTRO
Fire Marshall Fire Life Safety Cleared 6/5/2018 DOMINIQUE MEDINA
Building over 3-story or 36-ft Cleared 6/7/2018 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 6/7/2018 CALOSHA APPROVED
Miscellaneous Cleared 6/7/2018 BRIAN CARR
Opn space landscape/Water mgmt Cleared 6/7/2018 BRIAN CARR
Specific Plan Cleared 6/7/2018 BRIAN CARR
Low Impact Development Cleared 6/25/2018 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 6/26/2018 ZEMAMU GEBREWOLD
Permit Cleared 6/27/2018 ZEMAMU GEBREWOLD

Contact Information

Architect Oakes, Leland E Jr; Lic. No.: C11614 545 CYPRESS AVENUE      HERMOSA BEACH, CA 90254
Contractor Owner-Builder       ,
Engineer Blunda, Abraham Matthew; Lic. No.: C61051 2200 WEST ORANGEWOOD AVE STE 150      ORANGE, CA 92868
Engineer Knur, Reinard Thomas; Lic. No.: GE2755 1435 MONCADO DR      GLENDALE, CA 91207
Geologist Knur, Reinard Thomas; Lic. No.: EG1547 1435 MONCADO DRIVE      GLENDALE, CA 91207

Inspector Information

NICK DANERI, (213) 202-5615 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/5/2018 Partial Inspection LESLIE TRUJILLO
Piling/Pier/Caisson 5/14/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 5/15/2019 Partial Approval JAMES POWERS
METHANE-Barrier 5/15/2019 Not Ready for Inspection JAMES POWERS
METHANE-Subgrade 5/15/2019 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 7/11/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Barrier 7/11/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Subgrade 7/11/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 7/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 7/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 7/17/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/17/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/17/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 7/17/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Subgrade 7/17/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 7/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/18/2019 Conditional Approval LESLIE TRUJILLO
Excavation/Setback/Form/Re-Bar 7/18/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 7/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/19/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 7/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/22/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 7/22/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 7/22/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Subgrade 7/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 7/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 7/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 7/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/1/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/1/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/1/2019 Partial Approval LESLIE TRUJILLO
METHANE-Subgrade 8/1/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/9/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/9/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/9/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Subgrade 8/9/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/15/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/15/2019 Partial Inspection LESLIE TRUJILLO
METHANE-Subgrade 8/15/2019 Approved LESLIE TRUJILLO
Deputy Methane Barrier 8/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/20/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/20/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/20/2019 Partial Inspection LESLIE TRUJILLO
Deputy Methane Barrier 8/21/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 8/21/2019 Conditional Approval LESLIE TRUJILLO
Masonry Wall/Backfill 8/21/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 8/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/23/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/23/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/23/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 8/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 8/27/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 8/27/2019 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 8/28/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 8/29/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 8/29/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 8/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/4/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/4/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 9/4/2019 Partial Inspection LESLIE TRUJILLO
Deputy Reinf. Concrete 9/5/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 9/6/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/13/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/13/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 9/13/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/16/2019 Conditional Approval LESLIE TRUJILLO
Green Building Rough 9/16/2019 Conditional Approval LESLIE TRUJILLO
METHANE-Rough 9/16/2019 Partial Approval LESLIE TRUJILLO
Reinforced Concrete Frame 9/16/2019 Partial Approval LESLIE TRUJILLO
Verify Sprinkler Sign Off 9/16/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/17/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/17/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/17/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/18/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/18/2019 Not Ready for Inspection LESLIE TRUJILLO
METHANE-Barrier 9/18/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/19/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 9/19/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/24/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 9/24/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/25/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/25/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 9/25/2019 Partial Inspection LESLIE TRUJILLO
Deputy Methane Barrier 9/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 9/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/27/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 9/27/2019 Not Ready for Inspection LESLIE TRUJILLO
METHANE-Barrier 9/27/2019 Partial Inspection LESLIE TRUJILLO
Deputy Methane Barrier 9/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 9/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 9/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 9/30/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 9/30/2019 Not Ready for Inspection LESLIE TRUJILLO
Deputy Methane Barrier 10/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/1/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 10/2/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/2/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/2/2019 Partial Approval LESLIE TRUJILLO
Masonry Wall/Backfill 10/2/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 10/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/3/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/3/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/3/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 10/3/2019 Conditional Approval LESLIE TRUJILLO
Masonry Wall/Backfill 10/3/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/9/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/10/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/10/2019 Partial Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/10/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 10/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/11/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 10/15/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/15/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 10/15/2019 Partial Inspection ERNESTO CORRAL
Deputy Methane Barrier 10/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/16/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 10/16/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 10/16/2019 Partial Inspection ERNESTO CORRAL
Deputy Methane Barrier 10/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 10/17/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 10/17/2019 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 10/17/2019 Partial Inspection ERNESTO CORRAL
METHANE-Barrier 10/17/2019 Partial Inspection ERNESTO CORRAL
Deputy Methane Barrier 10/18/2019 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 10/18/2019 Approved JEFF BYTHEWAY
Deputy Shotcrete 10/18/2019 Approved JEFF BYTHEWAY
Deputy Methane Barrier 10/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/21/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/21/2019 Partial Approval LESLIE TRUJILLO
Green Building Rough 10/21/2019 Conditional Approval LESLIE TRUJILLO
Interior/Exterior Lathing 10/21/2019 Approved BRUCE CAMPBELL
METHANE-Rough 10/21/2019 Conditional Approval LESLIE TRUJILLO
Reinforced Concrete Frame 10/21/2019 Partial Inspection LESLIE TRUJILLO
Verify Sprinkler Sign Off 10/21/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/22/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/23/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 10/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/25/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/28/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/28/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/28/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/29/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 10/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 10/30/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 10/30/2019 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 10/31/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 10/31/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 10/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/1/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/4/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/4/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 11/4/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/5/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/6/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/6/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 11/6/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/7/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 11/7/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 11/7/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/8/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/13/2019 Partial Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 11/13/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/14/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/14/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 11/14/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 11/14/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/15/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/18/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 11/18/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 11/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/20/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 11/20/2019 No Access for Inspection LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 11/21/2019 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 11/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 11/22/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 11/25/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/25/2019 Conditional Approval DANIEL COLLINS
Deputy Shotcrete 11/25/2019 Conditional Approval DANIEL COLLINS
Deputy Methane Barrier 11/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/26/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 11/26/2019 Conditional Approval ERNESTO CORRAL
Floor/Roof Diaphrgm/Shear Wall 11/26/2019 Partial Approval DANIEL COLLINS
Deputy Methane Barrier 11/27/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 11/27/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 11/27/2019 Conditional Approval ERNESTO CORRAL
Deputy Methane Barrier 12/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Shotcrete 12/2/2019 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 12/6/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/9/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/10/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/11/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/12/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/12/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/12/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 12/12/2019 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/13/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/16/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/17/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 12/18/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 12/19/2019 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 12/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/20/2019 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/23/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/23/2019 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 12/23/2019 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 12/23/2019 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/24/2019 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 12/24/2019 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/26/2019 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/27/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 12/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/30/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 12/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 12/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 12/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 12/31/2019 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 1/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/2/2020 Partial Approval LESLIE TRUJILLO
Deputy Shotcrete 1/2/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/2/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 1/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/6/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/6/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/8/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/8/2020 Partial Approval LESLIE TRUJILLO
Deputy Methane Barrier 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/9/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/9/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 1/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 1/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 1/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/13/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/13/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 1/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 1/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 1/15/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/15/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/15/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/15/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/17/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/17/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/17/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/17/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 1/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/22/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/22/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/22/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 1/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/24/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/24/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/27/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 1/27/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 1/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/28/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/28/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/29/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/29/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/30/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/30/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 1/31/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 1/31/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/4/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/4/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/5/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/5/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/7/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/7/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/10/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/10/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 2/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 2/11/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/11/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/11/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/11/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 2/12/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/12/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/12/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 2/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/13/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Order to Comply Issued LESLIE TRUJILLO
Footing/Foundation/Slab 2/13/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 2/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 2/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/14/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 2/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/18/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/19/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/21/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 2/21/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 2/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/24/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 2/24/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 2/25/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 2/25/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 2/25/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 2/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/26/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 2/26/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/26/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 2/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/27/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 2/27/2020 Partial Approval JAMES POWERS
METHANE-Barrier 2/27/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/27/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/28/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 2/28/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/2/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/3/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 3/3/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/4/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/4/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/4/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 3/4/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 3/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/5/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 3/5/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/6/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 3/6/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/9/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/9/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 3/9/2020 Conditional Approval LESLIE TRUJILLO
Deputy Methane Barrier 3/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/10/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/11/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/11/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/11/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/12/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/12/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/12/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/17/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/17/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/17/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/19/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/19/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/19/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/24/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/25/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/25/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/25/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/26/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/26/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/26/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 3/27/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 3/27/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 3/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 3/31/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 3/31/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 3/31/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/1/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/1/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/1/2020 Conditional Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/2/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/2/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/2/2020 Partial Approval LESLIE TRUJILLO
Deputy Pre-Stress Concrete 4/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/3/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/6/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/7/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/8/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/13/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/13/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 4/13/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/14/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/15/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/15/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/15/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/16/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/17/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/17/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/20/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/21/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/22/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/22/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/22/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/22/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/23/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/23/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/23/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 4/23/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/24/2020 Conditional Approval RONALD PACHECO
Deputy Reinf. Masonry 4/24/2020 Conditional Approval RONALD PACHECO
Deputy Shotcrete 4/24/2020 Conditional Approval RONALD PACHECO
Deputy Reinf. Masonry 4/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/27/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/28/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/28/2020 Conditional Approval LESLIE TRUJILLO
Footing/Foundation/Slab 4/28/2020 Partial Approval LESLIE TRUJILLO
METHANE-Barrier 4/28/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/29/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/29/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/29/2020 Conditional Approval LESLIE TRUJILLO
Floor/Roof Diaphrgm/Shear Wall 4/29/2020 Partial Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 4/30/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 4/30/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 4/30/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Masonry 5/1/2020 Conditional Approval LESLIE TRUJILLO
Deputy Shotcrete 5/1/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/4/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/5/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/5/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/5/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 5/5/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/6/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/6/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/6/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/7/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/7/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/8/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/8/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/11/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/11/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/11/2020 Partial Approval JAMES POWERS
METHANE-Barrier 5/11/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/12/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/12/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/12/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/13/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/13/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/14/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/14/2020 Partial Approval JAMES POWERS
METHANE-Barrier 5/14/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/14/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/15/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/15/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/18/2020 Conditional Approval LESLIE TRUJILLO
Deputy Reinf. Concrete 5/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/18/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/19/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/19/2020 Partial Approval JAMES POWERS
METHANE-Barrier 5/19/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 5/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/21/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/22/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/22/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/22/2020 Partial Approval JAMES POWERS
METHANE-Barrier 5/22/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/26/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/26/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/27/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/27/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/27/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/28/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/28/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/29/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 5/29/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/1/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Concrete 6/1/2020 Conditional Approval ERNESTO CORRAL
Deputy Reinf. Masonry 6/1/2020 Conditional Approval ERNESTO CORRAL
Deputy Pre-Stress Concrete 6/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/2/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/2/2020 Partial Approval JAMES POWERS
METHANE-Barrier 6/2/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/3/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/3/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/4/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 6/4/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/4/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/5/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/8/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/9/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/9/2020 Partial Approval JAMES POWERS
METHANE-Barrier 6/9/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 6/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/10/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/10/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/11/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/11/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 6/11/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 6/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/12/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/12/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/15/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 6/15/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/16/2020 Partial Approval JAMES POWERS
METHANE-Barrier 6/16/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/16/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/17/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 6/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/18/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/19/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/19/2020 Partial Approval JAMES POWERS
METHANE-Barrier 6/19/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/22/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/22/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/23/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/23/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/24/2020 Corrections Issued NICK DANERI
Deputy Reinf. Concrete 6/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/24/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 6/24/2020 Partial Approval JAMES POWERS
METHANE-Barrier 6/24/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 6/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/25/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/25/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/26/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 6/26/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 6/26/2020 Conditional Approval NICK DANERI
Deputy Pre-Stress Concrete 6/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/29/2020 Partial Approval JAMES POWERS
METHANE-Barrier 6/29/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 6/29/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/30/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 6/30/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/30/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 7/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/1/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/1/2020 Partial Approval JAMES POWERS
METHANE-Barrier 7/1/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 7/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/2/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 7/2/2020 Partial Approval JAMES POWERS
Green Building Rough 7/2/2020 Not Ready for Inspection JAMES POWERS
METHANE-Rough 7/2/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/2/2020 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 7/2/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 7/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/6/2020 Partial Approval JAMES POWERS
METHANE-Barrier 7/6/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/6/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/7/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/8/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/8/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/8/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/9/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/10/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/10/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/13/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/13/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/13/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/14/2020 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 7/15/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/15/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/15/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 7/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/16/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 7/16/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/16/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/17/2020 Partial Approval JAMES POWERS
Deputy Steel/Welding 7/17/2020 Partial Approval JAMES POWERS
METHANE-Barrier 7/17/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 7/17/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/20/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/21/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/21/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/22/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/23/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 7/23/2020 Partial Approval JAMES POWERS
Wood Frame 7/23/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/24/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/27/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/27/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/28/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 7/28/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 7/28/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 7/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/29/2020 Partial Approval JAMES POWERS
Drywall Nailing 7/29/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/29/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/30/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 7/30/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 7/30/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/30/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 7/31/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 7/31/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/31/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/3/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/3/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/3/2020 Order to Comply Issued JAMES POWERS
Deputy Reinf. Concrete 8/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/4/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/4/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/4/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 8/4/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 8/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/5/2020 Partial Approval JAMES POWERS
Masonry Wall/Backfill 8/5/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/5/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/6/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/6/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/7/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/7/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/10/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/10/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/12/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/12/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/12/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/13/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/13/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/13/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/14/2020 Order to Comply Issued JAMES POWERS
Deputy Reinf. Concrete 8/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/14/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/14/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/14/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/14/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/14/2020 Partial Approval JAMES POWERS
METHANE-Barrier 8/14/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/14/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/17/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/17/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 8/17/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/17/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/18/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/18/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/18/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/19/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/19/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 8/19/2020 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/20/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/20/2020 Partial Approval JAMES POWERS
METHANE-Barrier 8/20/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/20/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/21/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/21/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/22/2020 Partial Inspection ERNESTO CORRAL
Deputy Reinf. Concrete 8/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/24/2020 Partial Approval JAMES POWERS
Drywall Nailing 8/24/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/24/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/25/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/25/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/25/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/26/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/26/2020 Partial Approval JAMES POWERS
METHANE-Barrier 8/26/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/26/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/27/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 8/27/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/28/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 8/31/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 8/31/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 8/31/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/1/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/1/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 9/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 9/2/2020 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Masonry 9/2/2020 Conditional Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 9/2/2020 Partial Inspection RAFAEL ESPINOZA
Piling/Pier/Caisson 9/2/2020 Partial Inspection RAFAEL ESPINOZA
Deputy Pre-Stress Concrete 9/3/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 9/3/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 9/3/2020 Conditional Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 9/3/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 9/3/2020 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 9/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/4/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/4/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/8/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/8/2020 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 9/8/2020 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 9/8/2020 Partial Approval EDWIN GREGORYONA
METHANE-Barrier 9/8/2020 Partial Inspection EDWIN GREGORYONA
Deputy Pre-Stress Concrete 9/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/9/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/10/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/10/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/11/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/14/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/14/2020 Partial Approval JAMES POWERS
Insulation 9/14/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/15/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 9/15/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/16/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/16/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/16/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/16/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/17/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 9/17/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/17/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/17/2020 Partial Approval JAMES POWERS
METHANE-Barrier 9/17/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/17/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/18/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/18/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 9/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/21/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/21/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 9/21/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 9/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/22/2020 Partial Approval JAMES POWERS
Insulation 9/22/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/22/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/22/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/23/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/23/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/23/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/23/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/24/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/24/2020 Partial Approval JAMES POWERS
METHANE-Barrier 9/24/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/25/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/25/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/25/2020 Corrections Issued JAMES POWERS
Deputy Pre-Stress Concrete 9/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/28/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/29/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 9/29/2020 Partial Approval JAMES POWERS
Drywall Nailing 9/29/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 9/30/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/30/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 9/30/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 9/30/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/1/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/1/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/1/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 10/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/2/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/2/2020 Partial Approval JAMES POWERS
Insulation 10/2/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/5/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 10/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/6/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/6/2020 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 10/6/2020 Not Ready for Inspection JAMES POWERS
Insulation 10/6/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/6/2020 Partial Approval JAMES POWERS
METHANE-Barrier 10/6/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 10/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/7/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/7/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/7/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/8/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 10/8/2020 Conditional Approval NICK DANERI
Reinforced Concrete Frame 10/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/9/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/9/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/9/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/13/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/13/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/13/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Not Ready for Inspection JAMES POWERS
Insulation 10/13/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 10/13/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/13/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/14/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/14/2020 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Partial Approval JAMES POWERS
Insulation 10/14/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/14/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/15/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/15/2020 Partial Approval JAMES POWERS
Insulation 10/15/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/15/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/16/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/16/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/16/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/16/2020 Partial Inspection JAMES POWERS
Insulation 10/16/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/16/2020 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 10/16/2020 Approved JAMES POWERS
Deputy Pre-Stress Concrete 10/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/19/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/19/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/19/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/19/2020 Not Ready for Inspection JAMES POWERS
Insulation 10/19/2020 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 10/19/2020 Partial Approval JAMES POWERS
METHANE-Barrier 10/19/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 10/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/20/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/20/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/21/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/21/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/21/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/22/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/22/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 10/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/23/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/23/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/26/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Partial Approval JAMES POWERS
Insulation 10/26/2020 Partial Approval JAMES POWERS
METHANE-Barrier 10/26/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 10/26/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/27/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/27/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 10/27/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/28/2020 Partial Approval JAMES POWERS
Deputy Wood Construction 10/28/2020 Partial Approval JAMES POWERS
Drywall Nailing 10/28/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/28/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/28/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/29/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/29/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/29/2020 Partial Approval JAMES POWERS
Insulation 10/29/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 10/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 10/30/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 10/30/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/30/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/2/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/2/2020 Partial Approval JAMES POWERS
Insulation 11/2/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/4/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/4/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/4/2020 Partial Approval JAMES POWERS
Insulation 11/4/2020 Partial Approval JAMES POWERS
METHANE-Barrier 11/4/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/4/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/5/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/5/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 11/5/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/5/2020 Partial Approval JAMES POWERS
Insulation 11/5/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 11/5/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/6/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/6/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 11/6/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/6/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/9/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/10/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/10/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/12/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/12/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/12/2020 Conditional Approval NICK DANERI
Drywall Nailing 11/12/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/12/2020 Partial Approval NICK DANERI
Insulation 11/12/2020 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 11/13/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/13/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/13/2020 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 11/16/2020 Conditional Approval NICK DANERI
Deputy Pre-Stress Concrete 11/16/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/16/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/16/2020 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Not Ready for Inspection NICK DANERI
Deputy Drilled-In Anchors 11/17/2020 Conditional Approval NICK DANERI
Deputy Pre-Stress Concrete 11/17/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/17/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/17/2020 Conditional Approval NICK DANERI
Drywall Nailing 11/17/2020 Partial Approval NICK DANERI
Excavation/Setback/Form/Re-Bar 11/17/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval NICK DANERI
Insulation 11/17/2020 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 11/18/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/18/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/18/2020 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Partial Approval NICK DANERI
Insulation 11/18/2020 Partial Approval NICK DANERI
Interior/Exterior Lathing 11/18/2020 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 11/19/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/19/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/19/2020 Conditional Approval NICK DANERI
Deputy Shotcrete 11/19/2020 Conditional Approval NICK DANERI
Drywall Nailing 11/19/2020 Partial Inspection NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Partial Approval NICK DANERI
Insulation 11/19/2020 Partial Approval NICK DANERI
Deputy Drilled-In Anchors 11/20/2020 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 11/20/2020 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 11/20/2020 Conditional Approval NICK DANERI
Drywall Nailing 11/20/2020 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/20/2020 Partial Approval NICK DANERI
Insulation 11/20/2020 Partial Approval NICK DANERI
Deputy Reinf. Concrete 11/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/23/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/23/2020 Partial Approval JAMES POWERS
METHANE-Barrier 11/23/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/24/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/24/2020 Partial Approval JAMES POWERS
Piling/Pier/Caisson 11/24/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/25/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 11/25/2020 Order to Comply Issued JAMES POWERS
Deputy Reinf. Masonry 11/25/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/25/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 11/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 11/30/2020 Partial Approval JAMES POWERS
Drywall Nailing 11/30/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/30/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 11/30/2020 Partial Approval JAMES POWERS
METHANE-Barrier 11/30/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/1/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/1/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/2/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/2/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/3/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/3/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Not Ready for Inspection JAMES POWERS
Insulation 12/3/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/4/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/4/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 12/7/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/7/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/7/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/8/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/8/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/8/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/8/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/9/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/9/2020 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 12/9/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/10/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/10/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/10/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 12/10/2020 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 12/10/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/11/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/11/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/14/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/14/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/14/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Partial Approval JAMES POWERS
Insulation 12/14/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/14/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/15/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/15/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/15/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/15/2020 Partial Approval JAMES POWERS
METHANE-Barrier 12/15/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/15/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/16/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/16/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/16/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/16/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/16/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/17/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/17/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/17/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/17/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/18/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/18/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/18/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/21/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/21/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/21/2020 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/21/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/22/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/22/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/22/2020 Partial Approval JAMES POWERS
Insulation 12/22/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/22/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/23/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/23/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/23/2020 Partial Approval JAMES POWERS
Drywall Nailing 12/23/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/24/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/24/2020 Partial Approval JAMES POWERS
Deputy Shotcrete 12/24/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/28/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/28/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/28/2020 Not Ready for Inspection JAMES POWERS
Insulation 12/28/2020 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 12/28/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/29/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/29/2020 Partial Approval JAMES POWERS
Reinforced Concrete Frame 12/29/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/30/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/30/2020 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 12/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 12/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 12/31/2020 Partial Approval JAMES POWERS
Footing/Foundation/Slab 12/31/2020 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/4/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/4/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/4/2021 Partial Approval JAMES POWERS
Insulation 1/4/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/5/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/5/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/6/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/6/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/6/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/6/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/7/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/7/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/8/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/8/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/8/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Partial Approval JAMES POWERS
METHANE-Barrier 1/8/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/8/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/11/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/11/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/11/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/12/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/12/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 1/12/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval JAMES POWERS
Insulation 1/12/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/13/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/13/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 1/13/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/13/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 1/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/14/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 1/14/2021 Partial Approval JAMES POWERS
Green Building Rough 1/14/2021 Not Ready for Inspection JAMES POWERS
Insulation 1/14/2021 Partial Approval JAMES POWERS
METHANE-Barrier 1/14/2021 Not Ready for Inspection JAMES POWERS
Pre-Inspection 1/14/2021 Approved JAMES POWERS
Reinforced Concrete Frame 1/14/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/15/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 1/15/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/15/2021 Partial Approval JAMES POWERS
Wood Frame 1/15/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/19/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/19/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/19/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/19/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/20/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/20/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/20/2021 Partial Approval JAMES POWERS
METHANE-Barrier 1/20/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/20/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/21/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/21/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/21/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/22/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/22/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/22/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/25/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/25/2021 Partial Approval JAMES POWERS
METHANE-Barrier 1/25/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 1/25/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/26/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/26/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/27/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Masonry 1/27/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/27/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 1/27/2021 Partial Approval JAMES POWERS
Drywall Nailing 1/27/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 1/27/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/28/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/28/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/28/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 1/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 1/29/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/29/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 1/29/2021 Partial Approval JAMES POWERS
Green Building Rough 1/29/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 1/29/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 1/29/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 2/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/1/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/2/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/2/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/2/2021 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 2/2/2021 Partial Approval JAMES POWERS
METHANE-Barrier 2/2/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 2/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/3/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/3/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/3/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Partial Approval JAMES POWERS
Green Building Rough 2/3/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 2/3/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/3/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/3/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 2/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/4/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/4/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/4/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/5/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/5/2021 Partial Approval JAMES POWERS
Insulation 2/5/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/8/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 2/8/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/8/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 2/8/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 2/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/9/2021 Partial Approval JAMES POWERS
METHANE-Barrier 2/9/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/9/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/10/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/10/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/11/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/12/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 2/12/2021 Partial Approval JAMES POWERS
METHANE-Barrier 2/12/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/12/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/16/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/17/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/17/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Partial Approval JAMES POWERS
Green Building Rough 2/17/2021 Approved JAMES POWERS
Insulation 2/17/2021 Partial Approval JAMES POWERS
METHANE-Rough 2/17/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/17/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/17/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 2/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/18/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/19/2021 Partial Approval JAMES POWERS
Insulation 2/19/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 2/19/2021 Partial Approval JAMES POWERS
METHANE-Barrier 2/19/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 2/19/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/22/2021 Partial Approval JAMES POWERS
Drywall Nailing 2/22/2021 Partial Approval JAMES POWERS
METHANE-Rough 2/22/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/22/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/22/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 2/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/23/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/24/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/24/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 2/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/25/2021 Partial Approval JAMES POWERS
Pre-Inspection 2/25/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 2/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 2/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/26/2021 Partial Approval JAMES POWERS
Insulation 2/26/2021 Partial Approval JAMES POWERS
METHANE-Rough 2/26/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 2/26/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 2/26/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 3/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/1/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/1/2021 Partial Approval JAMES POWERS
METHANE-Barrier 3/1/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/1/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/2/2021 Partial Approval JAMES POWERS
Insulation 3/2/2021 Partial Approval JAMES POWERS
METHANE-Rough 3/2/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/2/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 3/2/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 3/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/3/2021 Partial Approval JAMES POWERS
Pre-Inspection 3/3/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/3/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/4/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/4/2021 Partial Approval JAMES POWERS
Pre-Inspection 3/4/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/5/2021 Partial Approval JAMES POWERS
METHANE-Barrier 3/5/2021 Not Ready for Inspection JAMES POWERS
Pre-Inspection 3/5/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/5/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/8/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/8/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/9/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Partial Approval JAMES POWERS
Insulation 3/9/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/9/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/10/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/10/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/10/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/11/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/11/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/11/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/12/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/12/2021 Partial Approval JAMES POWERS
METHANE-Barrier 3/12/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/15/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/15/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/16/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/16/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/17/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/17/2021 Partial Approval JAMES POWERS
METHANE-Rough 3/17/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 3/17/2021 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 3/17/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 3/18/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 3/18/2021 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 3/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/19/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 3/19/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/19/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/22/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/22/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval JAMES POWERS
Piling/Pier/Caisson 3/22/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 3/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/23/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/23/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 3/23/2021 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 3/23/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 3/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/24/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/24/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/24/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/25/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/25/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/25/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 3/25/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/26/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 3/26/2021 Partial Approval JAMES POWERS
Drywall Nailing 3/26/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/30/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/30/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 3/31/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 3/31/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 4/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/1/2021 Partial Approval JAMES POWERS
METHANE-Barrier 4/1/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/1/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/5/2021 Order to Comply Issued JAMES POWERS
Drywall Nailing 4/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/5/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/6/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/7/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/7/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Partial Approval JAMES POWERS
METHANE-Rough 4/7/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/7/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/7/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 4/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/8/2021 Partial Approval JAMES POWERS
Deputy Seismic Resistance 4/8/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/8/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 4/8/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/9/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/9/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 4/9/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/12/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval JAMES POWERS
METHANE-Barrier 4/12/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 4/12/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/12/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/12/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 4/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/13/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/14/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/14/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Partial Approval JAMES POWERS
Insulation 4/14/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 4/14/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/15/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 4/15/2021 Partial Approval JAMES POWERS
METHANE-Barrier 4/15/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/15/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/16/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/19/2021 Partial Approval JAMES POWERS
METHANE-Rough 4/19/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/19/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 4/19/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 4/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 4/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/20/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 4/21/2021 Partial Approval JAMES POWERS
Drywall Nailing 4/21/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 4/22/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/22/2021 Conditional Approval NICK DANERI
Deputy Pre-Stress Concrete 4/23/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 4/23/2021 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/23/2021 Partial Approval NICK DANERI
Insulation 4/23/2021 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 4/26/2021 Conditional Approval NICK DANERI
Piling/Pier/Caisson 4/26/2021 Conditional Approval NICK DANERI
Deputy Pre-Stress Concrete 4/27/2021 Conditional Approval NICK DANERI
Drywall Nailing 4/27/2021 Partial Approval NICK DANERI
Insulation 4/27/2021 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 4/28/2021 Conditional Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/28/2021 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 4/29/2021 Conditional Approval NICK DANERI
Drywall Nailing 4/29/2021 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 4/30/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 4/30/2021 Conditional Approval NICK DANERI
Drywall Nailing 4/30/2021 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 4/30/2021 Partial Approval NICK DANERI
Deputy Reinf. Masonry 5/3/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/3/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Partial Approval JAMES POWERS
Insulation 5/3/2021 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 5/3/2021 Partial Approval JAMES POWERS
METHANE-Rough 5/3/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/3/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/3/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/4/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Partial Approval JAMES POWERS
Insulation 5/4/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/5/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/6/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 5/6/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/7/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/7/2021 Not Ready for Inspection JAMES POWERS
Insulation 5/7/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 5/7/2021 No Access for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/10/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/10/2021 Partial Approval JAMES POWERS
Insulation 5/10/2021 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/10/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 5/10/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/10/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/10/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/11/2021 Conditional Approval NICK DANERI
Deputy Reinf. Concrete 5/11/2021 Conditional Approval NICK DANERI
Deputy Reinf. Masonry 5/11/2021 Conditional Approval NICK DANERI
Drywall Nailing 5/11/2021 Partial Approval NICK DANERI
Deputy Pre-Stress Concrete 5/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/12/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/12/2021 Partial Approval JAMES POWERS
METHANE-Barrier 5/12/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/12/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/13/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/14/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/14/2021 Partial Approval EDWIN GREGORYONA
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Partial Approval EDWIN GREGORYONA
Insulation 5/14/2021 Partial Approval EDWIN GREGORYONA
Deputy Pre-Stress Concrete 5/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/17/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/17/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/17/2021 Not Ready for Inspection JAMES POWERS
Insulation 5/17/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 5/17/2021 Not Ready for Inspection JAMES POWERS
METHANE-Barrier 5/17/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/18/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/18/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval JAMES POWERS
Insulation 5/18/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/19/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/19/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/19/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/19/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/19/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/20/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 5/21/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/21/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Partial Approval JAMES POWERS
Insulation 5/21/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/24/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/24/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 5/24/2021 Partial Approval JAMES POWERS
METHANE-Barrier 5/24/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 5/25/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 5/25/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/25/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/26/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/27/2021 Partial Approval JAMES POWERS
Drywall Nailing 5/27/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 5/28/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/1/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/1/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/2/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/2/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/3/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/3/2021 Partial Approval JAMES POWERS
Insulation 6/3/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 6/4/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/7/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/7/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/7/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/7/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/8/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/9/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/9/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/10/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/11/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/11/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Partial Approval JAMES POWERS
Insulation 6/11/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/14/2021 Partial Approval TIMOTHY BUXTON
Deputy Pre-Stress Concrete 6/15/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/15/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/15/2021 Partial Approval JAMES POWERS
Insulation 6/15/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/16/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/16/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/16/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/17/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/17/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/18/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/18/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/21/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 6/21/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/22/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/22/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/22/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/23/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/23/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/23/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/24/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/25/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 6/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/25/2021 Not Ready for Inspection RAFAEL ESPINOZA
Deputy Pre-Stress Concrete 6/28/2021 Partial Approval JAMES POWERS
Drywall Nailing 6/28/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/28/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/29/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 6/30/2021 Partial Approval JAMES POWERS
METHANE-Barrier 6/30/2021 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 6/30/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/1/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/2/2021 Partial Approval JAMES POWERS
Drywall Nailing 7/2/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 7/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/6/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 7/7/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Partial Approval JAMES POWERS
Insulation 7/7/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/9/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/9/2021 Partial Approval JAMES POWERS
Drywall Nailing 7/12/2021 Partial Approval DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 7/13/2021 Partial Approval JAMES POWERS
Insulation 7/13/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 7/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/15/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Not Ready for Inspection JAMES POWERS
Insulation 7/15/2021 Partial Approval JAMES POWERS
Drywall Nailing 7/19/2021 Partial Approval JAMES POWERS
Insulation 7/19/2021 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/20/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/22/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/26/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Partial Approval JAMES POWERS
Insulation 7/27/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 7/29/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/29/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/2/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/2/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/2/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 8/2/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/3/2021 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 8/3/2021 Conditional Approval DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 Partial Approval DAVID TSAU
Deputy Pre-Stress Concrete 8/4/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/4/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/5/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/5/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/5/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/5/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/6/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/6/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/9/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2021 Partial Approval JAMES POWERS
Insulation 8/10/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/11/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/11/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/12/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/12/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/12/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/12/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 8/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/13/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/13/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/16/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/16/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/16/2021 Not Ready for Inspection JAMES POWERS
Insulation 8/16/2021 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 8/16/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 8/17/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/17/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/17/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/18/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/19/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/20/2021 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 8/23/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/23/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/23/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Partial Approval JAMES POWERS
Insulation 8/23/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/24/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/25/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/25/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/26/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/27/2021 Partial Approval JAMES POWERS
Drywall Nailing 8/27/2021 Partial Approval JAMES POWERS
Insulation 8/27/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/30/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 8/31/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/31/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/1/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/1/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/1/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/1/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/1/2021 Partial Approval JAMES POWERS
METHANE-Barrier 9/1/2021 Not Ready for Inspection JAMES POWERS
Deputy Pre-Stress Concrete 9/2/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/2/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/2/2021 Partial Approval JAMES POWERS
Deputy Pre-Stress Concrete 9/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/3/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/3/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/7/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/9/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/9/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/10/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/10/2021 Partial Approval JAMES POWERS
Drywall Nailing 9/10/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/10/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/13/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/13/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/13/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/13/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/14/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/14/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/14/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/14/2021 Partial Approval JAMES POWERS
Drywall Nailing 9/14/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/15/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 9/15/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/15/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/17/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/17/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Partial Approval JAMES POWERS
Drywall Nailing 9/24/2021 Partial Approval JAMES POWERS
Insulation 9/24/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/27/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 9/27/2021 Partial Approval JAMES POWERS
Final 9/27/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/27/2021 Partial Approval JAMES POWERS
Green Building Final 9/27/2021 Partial Approval JAMES POWERS
METHANE-Barrier 9/27/2021 Partial Approval JAMES POWERS
METHANE-Final 9/27/2021 Not Ready for Inspection JAMES POWERS
METHANE-Rough 9/27/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/27/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/27/2021 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Not Ready JAMES POWERS
Smoke Detectors 9/27/2021 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 9/27/2021 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 9/28/2021 Partial Approval JAMES POWERS
Final 9/29/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/29/2021 Partial Approval JAMES POWERS
Footing/Foundation/Slab 9/29/2021 Approved JAMES POWERS
Green Building Final 9/29/2021 Approved JAMES POWERS
Insulation 9/29/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 9/29/2021 Partial Approval JAMES POWERS
METHANE-Barrier 9/29/2021 Approved JAMES POWERS
METHANE-Final 9/29/2021 Approved JAMES POWERS
METHANE-Rough 9/29/2021 Approved JAMES POWERS
Reinforced Concrete Frame 9/29/2021 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/29/2021 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/29/2021 SGSOV Not Ready JAMES POWERS
Smoke Detectors 9/29/2021 Approved JAMES POWERS
Verify Sprinkler Sign Off 9/29/2021 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/1/2021 Not Ready for Inspection JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 10/1/2021 Not Ready for Inspection JONATHAN QUACH
Drywall Nailing 10/5/2021 Partial Approval TIMOTHY BUXTON
Floor/Roof Diaphrgm/Shear Wall 10/5/2021 Partial Approval TIMOTHY BUXTON
Insulation 10/5/2021 Partial Approval TIMOTHY BUXTON
Deputy Wood Construction 10/6/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Partial Approval JAMES POWERS
Insulation 10/8/2021 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 10/12/2021 Partial Approval JAMES POWERS
Drywall Nailing 10/12/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/12/2021 Partial Approval JAMES POWERS
Insulation 10/12/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval JAMES POWERS
Drywall Nailing 10/15/2021 Partial Approval JAMES POWERS
Insulation 10/15/2021 Partial Approval JAMES POWERS
Drywall Nailing 10/20/2021 Partial Approval RAFAEL ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 10/20/2021 Partial Approval RAFAEL ESPINOZA
Insulation 10/20/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 10/25/2021 Partial Approval JAMES POWERS
Final 10/25/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/25/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/25/2021 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 10/25/2021 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Not Ready JAMES POWERS
Verify Sprinkler Sign Off 10/25/2021 Not Ready for Inspection JAMES POWERS
Drywall Nailing 10/28/2021 Not Ready for Inspection JAMES POWERS
Final 10/28/2021 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval JAMES POWERS
Insulation 10/28/2021 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/28/2021 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 10/28/2021 SGSOV Not Ready JAMES POWERS
Verify Sprinkler Sign Off 10/28/2021 Partial Approval JAMES POWERS
Deputy Shotcrete 10/29/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 10/29/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/1/2021 Partial Approval RAFAEL ESPINOZA
Insulation 11/1/2021 Partial Approval RAFAEL ESPINOZA
Reinforced Concrete Frame 11/1/2021 Partial Approval RAFAEL ESPINOZA
Drywall Nailing 11/3/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/5/2021 Partial Approval JAMES POWERS
Insulation 11/5/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Partial Approval JAMES POWERS
Insulation 11/10/2021 Partial Approval JAMES POWERS
Drywall Nailing 11/15/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 11/17/2021 Conditional Approval RAFAEL ESPINOZA
Insulation 11/17/2021 Partial Approval RAFAEL ESPINOZA
Deputy Wood Construction 11/19/2021 Conditional Approval RAFAEL ESPINOZA
Drywall Nailing 11/29/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Partial Approval JAMES POWERS
Insulation 11/29/2021 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/29/2021 Partial Approval JAMES POWERS
Deputy Steel/Welding 11/30/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 12/2/2021 Partial Approval JAMES POWERS
Insulation 12/2/2021 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/3/2021 Partial Approval JAMES POWERS
Insulation 12/13/2021 Partial Approval JAMES POWERS
Drywall Nailing 12/21/2021 Partial Approval JAMES POWERS
Insulation 12/21/2021 Partial Approval JAMES POWERS
Deputy Wood Construction 12/22/2021 Partial Approval JAMES POWERS
Insulation 12/27/2021 Partial Approval JAMES POWERS
Insulation 1/12/2022 Partial Approval JAMES POWERS
Drywall Nailing 1/13/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 1/14/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 1/14/2022 Partial Approval JAMES POWERS
Drywall Nailing 1/14/2022 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Masonry 1/19/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/20/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/21/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/26/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/27/2022 Partial Approval JAMES POWERS
Drywall Nailing 1/27/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/27/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/28/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/1/2022 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 2/2/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 2/4/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/7/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Partial Approval JAMES POWERS
Insulation 2/7/2022 Partial Approval JAMES POWERS
Deputy Wood Construction 2/9/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/14/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 2/14/2022 Partial Approval JAMES POWERS
Insulation 2/14/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/23/2022 Not Ready for Inspection JAMES POWERS
Insulation 2/23/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/24/2022 Partial Approval JAMES POWERS
Insulation 2/24/2022 Partial Approval JAMES POWERS
Drywall Nailing 2/28/2022 Partial Approval JAMES POWERS
Insulation 2/28/2022 Partial Approval JAMES POWERS
Drywall Nailing 3/7/2022 Partial Approval JAMES POWERS
Insulation 3/7/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/11/2022 Partial Approval JAMES POWERS
Drywall Nailing 3/14/2022 Partial Approval JAMES POWERS
Insulation 3/14/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 3/18/2022 Partial Inspection JAMES POWERS
Light Gage Steel Frame 4/18/2022 Not Ready for Inspection DAVID BURKHEAD
Light Gage Steel Frame 4/20/2022 Partial Approval DAVID BURKHEAD
Insulation 4/25/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/26/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 4/26/2022 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 4/29/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 4/29/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/2/2022 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 5/5/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/5/2022 Partial Approval JAMES POWERS
Insulation 5/5/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 5/9/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/9/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/9/2022 Not Ready for Inspection JAMES POWERS
Drywall Nailing 5/10/2022 Partial Approval JAMES POWERS
Interior/Exterior Lathing 5/11/2022 Partial Approval JAMES POWERS
Drywall Nailing 5/24/2022 Partial Approval JAMES POWERS
Insulation 5/24/2022 Not Ready for Inspection JAMES POWERS
Pre-Inspection 6/10/2022 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/25/2022 Partial Approval TED RIES
Verify Sprinkler Sign Off 8/8/2022 Partial Approval JAMES POWERS
Wood Frame 8/9/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/10/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 8/10/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/11/2022 Partial Approval GREGORY POMISH
Deputy Drilled-In Anchors 8/17/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 8/17/2022 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/18/2022 Conditional Approval ERNESTO CORRAL
Light Gage Steel Frame 9/14/2022 Not Ready for Inspection JAMES POWERS
Deputy Steel/Welding 9/19/2022 Partial Approval JAMES POWERS
Final 9/28/2022 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/28/2022 Approved JAMES POWERS
Light Gage Steel Frame 9/28/2022 Partial Approval JAMES POWERS
Reinforced Concrete Frame 9/28/2022 Partial Approval JAMES POWERS
Reinforced Masonry Frame 9/28/2022 Partial Approval JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Not Ready JAMES POWERS
Verify Sprinkler Sign Off 9/28/2022 Partial Approval JAMES POWERS
Insulation 9/30/2022 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/30/2022 Partial Approval JAMES POWERS
Deputy Steel/Welding 10/3/2022 Conditional Approval MICHAEL ROSENBERG
Final 10/3/2022 Partial Inspection JAMES POWERS
Final 10/4/2022 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/17/2022 Partial Approval RAFAEL ESPINOZA
Interior/Exterior Lathing 10/25/2022 Not Ready for Inspection GREGORY POMISH
Interior/Exterior Lathing 11/4/2022 Not Ready for Inspection RAFAEL ESPINOZA
Interior/Exterior Lathing 11/9/2022 Partial Approval JAMES POWERS
Final 4/5/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 4/5/2023 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 4/5/2023 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Not Required JAMES POWERS
Verify Sprinkler Sign Off 4/5/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/6/2023 Not Ready for Inspection JAMES POWERS
Special/Order Compliance 4/12/2023 Approved JAMES POWERS
Pre-Inspection 4/17/2023 Partial Inspection RAFAEL ESPINOZA
Final 4/25/2023 Not Ready for Inspection JAMES POWERS
Final 4/26/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/28/2023 Partial Approval JAMES POWERS
Drywall Nailing 5/16/2023 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 5/18/2023 Partial Approval JAMES POWERS
Final 5/18/2023 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/18/2023 Partial Approval JAMES POWERS
Insulation 5/18/2023 Partial Approval JAMES POWERS
Pre-Inspection 5/18/2023 Not Ready for Inspection JAMES POWERS
Reinforced Concrete Frame 5/18/2023 Partial Approval JAMES POWERS
Reinforced Masonry Frame 5/18/2023 Partial Approval JAMES POWERS
Verify Sprinkler Sign Off 5/18/2023 Not Ready for Inspection JAMES POWERS
Final 5/23/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 5/24/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval JAMES POWERS
Insulation 5/24/2023 Partial Approval JAMES POWERS
Special/Order Compliance 11/1/2023 Approved JAMES POWERS
Pre-Inspection 4/30/2024 Partial Approval JAMES POWERS
Special/Order Compliance 5/6/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 5/13/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 5/15/2024 Partial Approval JAMES POWERS
Wall Anchors 5/15/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 5/15/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 5/22/2024 Conditional Approval NICK DANERI
Wood Frame 5/22/2024 Partial Approval NICK DANERI
Drywall Nailing 5/28/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/28/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/5/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/10/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 6/10/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/10/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/10/2024 Partial Approval JAMES POWERS
Wood Frame 6/12/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/13/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/17/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/17/2024 Partial Approval JAMES POWERS
Insulation 6/17/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 6/17/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 6/20/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 6/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/20/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/20/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 6/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/21/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/21/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/24/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/25/2024 Partial Inspection JAMES POWERS
Drywall Nailing 6/26/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/27/2024 Partial Approval JAMES POWERS
Drywall Nailing 6/28/2024 Partial Approval JAMES POWERS
Wood Frame 6/28/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/1/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/1/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Partial Approval JAMES POWERS
Insulation 7/3/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 7/3/2024 Partial Approval JAMES POWERS
Insulation 7/8/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 7/9/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/10/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/11/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/11/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/17/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/17/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/18/2024 Partial Approval JEROME BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 7/18/2024 Partial Approval JEROME BLACKWOOD
Drywall Nailing 7/19/2024 Not Ready for Inspection JAMES POWERS
Insulation 7/19/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval JAMES POWERS
Insulation 7/22/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/23/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Partial Approval JAMES POWERS
Insulation 7/23/2024 Partial Approval JAMES POWERS
Insulation 7/25/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/29/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval JAMES POWERS
Drywall Nailing 7/30/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/1/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/2/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/6/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/7/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 8/9/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/9/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/9/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/12/2024 Not Ready for Inspection DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 8/12/2024 Not Ready for Inspection DANIEL VARNUM
Deputy Wood Construction 8/13/2024 No Access for Inspection DANIEL VARNUM
Drywall Nailing 8/15/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Approval JAMES POWERS
Insulation 8/15/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 8/16/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/19/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/20/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 8/21/2024 Partial Approval JAMES POWERS
Insulation 8/22/2024 Not Ready for Inspection JAMES POWERS
Reinforced Masonry Frame 8/22/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 8/23/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Partial Approval JAMES POWERS
Insulation 8/23/2024 Partial Approval JAMES POWERS
Reinforced Masonry Frame 8/26/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Partial Approval JAMES POWERS
Insulation 8/27/2024 Not Ready for Inspection JAMES POWERS
Insulation 8/29/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 8/29/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 8/30/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/3/2024 Not Ready for Inspection JAMES POWERS
Insulation 9/3/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 9/4/2024 Not Ready for Inspection JAMES POWERS
Insulation 9/4/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 9/4/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Partial Approval JAMES POWERS
Insulation 9/6/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 9/6/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/9/2024 Partial Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Not Ready for Inspection RAFAEL CORTES
Interior/Exterior Lathing 9/9/2024 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval NICK DANERI
Deputy Wood Construction 9/12/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Partial Approval JAMES POWERS
Insulation 9/12/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/16/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Not Ready for Inspection JAMES POWERS
Insulation 9/16/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 9/17/2024 Partial Approval JAMES POWERS
Insulation 9/17/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Partial Approval GREGORY POMISH
Insulation 9/20/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 9/23/2024 Partial Approval JAMES POWERS
Insulation 9/23/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Partial Approval JAMES POWERS
Drywall Nailing 9/26/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/27/2024 Partial Approval JAMES POWERS
Insulation 9/27/2024 Partial Approval JAMES POWERS
Insulation 10/2/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 10/2/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 10/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/3/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Partial Approval JAMES POWERS
Insulation 10/8/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/8/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/9/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/9/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 10/10/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 10/10/2024 Partial Approval NICK DANERI
Drywall Nailing 10/11/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 10/11/2024 Partial Approval NICK DANERI
Drywall Nailing 10/15/2024 Partial Approval NICK DANERI
Insulation 10/15/2024 Conditional Approval NICK DANERI
Wood Frame 10/15/2024 Partial Approval NICK DANERI
Drywall Nailing 10/16/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/17/2024 Partial Approval JAMES POWERS
Wood Frame 10/17/2024 Partial Approval JAMES POWERS
Insulation 10/18/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 10/18/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/18/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/21/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/22/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Not Ready for Inspection JAMES POWERS
Insulation 10/22/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/23/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/23/2024 Partial Approval JAMES POWERS
Insulation 10/23/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 10/24/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 10/24/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 10/25/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/28/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Partial Approval JAMES POWERS
Insulation 10/28/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 10/28/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/29/2024 Partial Approval JAMES POWERS
Insulation 10/29/2024 Partial Approval JAMES POWERS
Drywall Nailing 10/31/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval JAMES POWERS
Insulation 10/31/2024 Partial Approval JAMES POWERS
Insulation 11/1/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/1/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/1/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/4/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval JAMES POWERS
Insulation 11/4/2024 Not Ready for Inspection JAMES POWERS
Drywall Nailing 11/6/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Partial Approval JAMES POWERS
Insulation 11/6/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/6/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/6/2024 Partial Approval JAMES POWERS
Insulation 11/7/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/7/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 11/12/2024 Conditional Approval NICK DANERI
Drywall Nailing 11/12/2024 Partial Approval NICK DANERI
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Partial Approval NICK DANERI
Insulation 11/12/2024 Partial Approval NICK DANERI
Light Gage Steel Frame 11/12/2024 Conditional Approval NICK DANERI
Drywall Nailing 11/13/2024 Partial Inspection NICK DANERI
Drywall Nailing 11/14/2024 Conditional Approval NICK DANERI
Insulation 11/14/2024 Partial Approval NICK DANERI
Interior/Exterior Lathing 11/14/2024 Conditional Approval NICK DANERI
Light Gage Steel Frame 11/14/2024 Partial Approval NICK DANERI
Drywall Nailing 11/18/2024 Partial Approval RONALD JIMENEZ
Insulation 11/18/2024 Partial Inspection RONALD JIMENEZ
Interior/Exterior Lathing 11/18/2024 Partial Inspection RONALD JIMENEZ
Drywall Nailing 11/19/2024 Not Ready for Inspection JEROME BLACKWOOD
Insulation 11/19/2024 Not Ready for Inspection JEROME BLACKWOOD
Interior/Exterior Lathing 11/19/2024 Not Ready for Inspection JEROME BLACKWOOD
Light Gage Steel Frame 11/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/21/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Partial Approval JAMES POWERS
Insulation 11/21/2024 Partial Approval JAMES POWERS
Interior/Exterior Lathing 11/21/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 11/21/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/22/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 11/22/2024 Partial Approval JAMES POWERS
Drywall Nailing 11/25/2024 Not Ready for Inspection RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval RONALD JIMENEZ
Insulation 11/25/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 11/25/2024 Not Ready for Inspection RONALD JIMENEZ
Insulation 11/26/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 11/26/2024 Not Ready for Inspection RONALD JIMENEZ
Light Gage Steel Frame 11/26/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 11/27/2024 Not Ready for Inspection JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/27/2024 Not Ready for Inspection JAMES POWERS
Insulation 11/27/2024 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 11/27/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/2/2024 Partial Approval JAMES POWERS
Insulation 12/2/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/4/2024 Conditional Approval RONALD JIMENEZ
Drywall Nailing 12/4/2024 Not Ready for Inspection RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval RONALD JIMENEZ
Insulation 12/4/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 12/4/2024 Partial Approval RONALD JIMENEZ
Drywall Nailing 12/5/2024 Partial Approval JAMES POWERS
Wood Frame 12/5/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/6/2024 Not Ready for Inspection JAMES POWERS
Insulation 12/6/2024 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 12/6/2024 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 12/10/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/10/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/13/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/13/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/17/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/17/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 12/20/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 12/20/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 12/24/2024 Partial Approval JAMES POWERS
Insulation 12/24/2024 Partial Approval JAMES POWERS
Deputy Reinf. Masonry 1/3/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 1/3/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/3/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Partial Approval JAMES POWERS
Insulation 1/3/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/3/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/3/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/14/2025 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval JAMES POWERS
Insulation 1/14/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/14/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 1/14/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/16/2025 Not Ready for Inspection JAMES POWERS
Insulation 1/16/2025 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 1/16/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/16/2025 Not Ready for Inspection JAMES POWERS
Wood Frame 1/16/2025 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 1/21/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/24/2025 Partial Approval JAMES POWERS
Insulation 1/24/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 1/24/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 1/28/2025 Partial Approval JAMES POWERS
Deputy Wood Construction 1/30/2025 Partial Approval JAMES POWERS
Drywall Nailing 1/30/2025 Partial Inspection JAMES POWERS
Insulation 1/30/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 1/30/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/3/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/3/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/3/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/5/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/5/2025 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 2/12/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/12/2025 Partial Approval JAMES POWERS
Insulation 2/12/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/12/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/18/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/18/2025 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 2/18/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/18/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/19/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/19/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/19/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/24/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/24/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/26/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/26/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 2/26/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 2/27/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/27/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/27/2025 Partial Approval JAMES POWERS
Drywall Nailing 2/28/2025 Not Ready for Inspection JAMES POWERS
Insulation 2/28/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 2/28/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/3/2025 Partial Approval JAMES POWERS
Insulation 3/3/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/3/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/5/2025 Partial Approval JAMES POWERS
Insulation 3/5/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/5/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/5/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 3/7/2025 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 3/7/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/7/2025 Partial Approval JAMES POWERS
Insulation 3/10/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 3/10/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 3/10/2025 Not Ready for Inspection LARRY ARNICK
Insulation 3/11/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/11/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/12/2025 Not Ready for Inspection JAMES POWERS
Insulation 3/12/2025 Not Ready for Inspection JAMES POWERS
Light Gage Steel Frame 3/12/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 3/14/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/14/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/19/2025 Not Ready for Inspection JAMES POWERS
Insulation 3/19/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/19/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/20/2025 Not Ready for Inspection JAMES POWERS
Insulation 3/20/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/24/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/24/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/26/2025 Partial Approval JAMES POWERS
Drywall Nailing 3/27/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 3/28/2025 Partial Approval JAMES POWERS
Drywall Nailing 4/2/2025 Partial Approval JAMES POWERS
Interior/Exterior Lathing 4/2/2025 Not Ready for Inspection JAMES POWERS
Drywall Nailing 4/3/2025 Not Ready for Inspection JAMES POWERS
Interior/Exterior Lathing 4/3/2025 Partial Approval JAMES POWERS
Special/Order Compliance 4/22/2025 Partial Approval JAMES POWERS
Light Gage Steel Frame 5/30/2025 No Access for Inspection JEFFREY FULTON
Light Gage Steel Frame 6/2/2025 Partial Approval JAMES POWERS
Drywall Nailing 6/12/2025 Partial Approval JOEY BUCHANAN
Deputy Reinf. Concrete 8/28/2025 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 8/29/2025 Approved JAMES POWERS
Reinforced Concrete Frame 8/29/2025 Partial Approval JAMES POWERS
Drywall Nailing 9/4/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 9/19/2025 Partial Approval JAMES POWERS
Final 10/7/2025 Not Ready for Inspection JAMES POWERS
Final 10/8/2025 Partial Approval JAMES POWERS
Insulation 10/8/2025 Partial Approval JAMES POWERS
Reinforced Concrete Frame 10/8/2025 Approved JAMES POWERS
Reinforced Masonry Frame 10/8/2025 Approved JAMES POWERS
Verify Sprinkler Sign Off 10/8/2025 Approved JAMES POWERS
Insulation 10/9/2025 Not Ready for Inspection JAMES POWERS
Insulation 10/14/2025 Not Ready for Inspection JAMES POWERS
Deputy Reinf. Concrete 10/15/2025 Partial Approval JAMES POWERS
Final 10/15/2025 Partial Approval JAMES POWERS
Final 10/16/2025 Partial Approval JAMES POWERS
Final 10/17/2025 Partial Approval JAMES POWERS
Special/Order Compliance 10/21/2025 Approved JOEY BUCHANAN
Final 10/28/2025 Not Ready for Inspection JAMES POWERS
Final 11/3/2025 Partial Approval JAMES POWERS
Final 11/6/2025 OK for TCO JAMES POWERS
Special/Order Compliance 11/6/2025 Partial Approval SCOTT SOBEL
Special/Order Compliance 5/19/2026 Approved JOEY BUCHANAN