3920 N KNOBHILL DR 91423
Certificate Information: 3920 N KNOBHILL DR 91423
- Application / Permit
- 15010-10000-02575
- Plan Check / Job No.
- B15LA09927
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW SINGLE FAMILY DWELLING WITH 2 LEVEL BASEMENTS.
- Permit Issued
- Issued on 1/19/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/20/2015 | APPLICANT |
| Green Plans Picked Up | 8/3/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2015 | ARMEN JIVALAGIAN |
| Corrections Issued | 8/19/2015 | ARMEN JIVALAGIAN |
| Quality Review Completed | 8/26/2015 | BILL STUTSMAN |
| Building Plans Picked Up | 8/26/2015 | APPLICANT |
| Applicant returned to address corrections | 12/29/2015 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 12/6/2016 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 12/19/2016 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 12/28/2016 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/5/2017 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/11/2017 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 1/17/2017 | ARMEN JIVALAGIAN |
| Plan Check Approved | 1/19/2017 | ARMEN JIVALAGIAN |
| Issued | 1/19/2017 | LADBS |
| CofO in Progress | 6/1/2023 | JUAN VALENZUELA |
| Permit Finaled | 6/6/2023 | MICHAEL SMITH |
| CofO Issued | 6/6/2023 | MICHAEL SMITH |
| Permit Finaled | 6/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/23/2015 | ROBERT SAMONTE |
| BHO/Hillside ordinance | Cleared | 9/23/2015 | ROBERT SAMONTE |
| BHO/Hillside ordinance | Cleared | 9/23/2015 | ROBERT SAMONTE |
| BHO/Hillside ordinance | Cleared | 9/23/2015 | ROBERT SAMONTE |
| Eng Process Fee Ord 176,300 | Cleared | 8/3/2016 | SHANNON CAMPBELL |
| Work Adjacent to Public Way | Cleared | 8/3/2016 | WARREN LIU |
| Hydrant and Access approval | Cleared | 8/10/2016 | JOHN DALLAS |
| Miscellaneous | Cleared | 11/15/2016 | LEE GUILBEAUX |
| Permit | Cleared | 11/15/2016 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 12/14/2016 | SAM NAVID |
| BHO/Hillside ordinance | Cleared | 1/6/2017 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/6/2017 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/6/2017 | LEE GUILBEAUX |
| ZI | Cleared | 1/9/2017 | DANALYNN DOMINGUEZ |
| Excavation more than 5-ft deep | Cleared | 1/17/2017 | CALOSHA APPROVED |
| Grading Pre-Inspection | Cleared | 1/17/2017 | ARMEN JIVALAGIAN |
| Green Code | Cleared | 1/18/2017 | ROLLIN GETTLE III |
Contact Information
| Architect | Christman, Gregory D; Lic. No.: C26618 | 1905 CASTILLO STREET SANTA BARBARA, CA 93101 |
| Contractor | J M I Construction Inc; Lic. No.: 993077-B | P O BOX 70756 PASADENA, CA 91117 |
| Engineer | Cai, Luo B; Lic. No.: C80352 | 5244 HUCKLEBERRY OAK STREET SIMI VALLEY, CA 93063 |
| Engineer | Mercado, Lizandro; Lic. No.: S4331 | 25583 AVENUE STANFORD VALENCIA, CA 91355 |
| Engineer | Spindler, Ronald W; Lic. No.: C13194 | 16823 SATICOY STREET VAN NUYS, CA 91406 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/15/2017 | Not Ready for Inspection | JOHN KIDWELL |
| Pre-Inspection | 7/24/2018 | Partial Inspection | JOHN KIDWELL |
| Piling/Pier/Caisson | 9/18/2018 | Conditional Approval | COREY HUPP |
| Piling/Pier/Caisson | 10/16/2018 | Partial Approval | COREY HUPP |
| Piling/Pier/Caisson | 10/17/2018 | Partial Approval | COREY HUPP |
| Piling/Pier/Caisson | 11/15/2018 | Partial Approval | COREY HUPP |
| Piling/Pier/Caisson | 12/10/2018 | Partial Approval | COREY HUPP |
| Piling/Pier/Caisson | 12/18/2018 | Partial Approval | COREY HUPP |
| Deputy Reinf. Concrete | 12/19/2018 | No Access for Inspection | ROBERT SHELLY |
| Piling/Pier/Caisson | 2/26/2019 | Partial Approval | RAYMOND KEHOE |
| Piling/Pier/Caisson | 4/23/2019 | Corrections Issued | THOMAS FINNILA |
| Piling/Pier/Caisson | 7/12/2019 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 7/16/2019 | Partial Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/22/2019 | Not Ready for Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 7/23/2019 | Conditional Approval | THOMAS FINNILA |
| Deputy Reinf. Concrete | 7/24/2019 | Conditional Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 7/30/2019 | Partial Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 8/8/2019 | Partial Approval | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 8/29/2019 | Conditional Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 8/30/2019 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 9/5/2019 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 9/9/2019 | Partial Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 9/16/2019 | Partial Approval | THOMAS FINNILA |
| Piling/Pier/Caisson | 12/30/2019 | Partial Approval | RAYMOND KEHOE |
| Piling/Pier/Caisson | 2/20/2020 | Partial Approval | CHARLES POWELL |
| Deputy Drilled-In Anchors | 5/14/2020 | Partial Approval | CHARLES POWELL |
| Deputy Reinf. Concrete | 5/14/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 6/22/2020 | Partial Approval | CHARLES POWELL |
| Piling/Pier/Caisson | 7/28/2020 | Partial Approval | CHARLES POWELL |
| Reinforced Concrete Frame | 7/28/2020 | Partial Approval | CHARLES POWELL |
| Deputy Shotcrete | 8/4/2020 | Partial Approval | CHARLES POWELL |
| Deputy Steel/Welding | 8/21/2020 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 10/16/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 12/9/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 1/12/2021 | Partial Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 1/21/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 2/26/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 3/17/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 4/7/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2021 | Partial Approval | CHARLES POWELL |
| Reinforced Concrete Frame | 5/5/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 6/1/2021 | Approved | CHARLES POWELL |
| Wood Frame | 7/2/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 7/16/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2021 | Partial Approval | CHARLES POWELL |
| Deputy Steel/Welding | 9/24/2021 | Conditional Approval | MISAEL ESPARZA |
| Deputy Steel/Welding | 9/27/2021 | Conditional Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2021 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 11/1/2021 | Partial Inspection | MICHAEL PELHAM |
| Wood Frame | 11/12/2021 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/29/2021 | Conditional Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 1/19/2022 | Conditional Approval | MISAEL ESPARZA |
| HVAC-Rough | 2/1/2022 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/16/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 2/16/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 2/16/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/8/2022 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 3/8/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/22/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 3/22/2022 | Approved | MISAEL ESPARZA |
| Insulation | 3/22/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 3/22/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 3/22/2022 | Approved | MISAEL ESPARZA |
| Insulation | 3/25/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 4/8/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/13/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/4/2022 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 10/4/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 10/4/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 10/4/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/13/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 4/13/2023 | Corrections Issued | JUAN VALENZUELA |
| Final | 4/13/2023 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 4/13/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 4/13/2023 | Approved | JUAN VALENZUELA |
| HVAC-Final | 4/13/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 4/13/2023 | Corrections Issued | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 4/13/2023 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 4/13/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 4/13/2023 | Corrections Issued | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 4/13/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/22/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 5/22/2023 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 5/22/2023 | Approved | JUAN VALENZUELA |
| Final | 6/1/2023 | OK to Issue CofO | JUAN VALENZUELA |
| Service/Power Release | 6/1/2023 | Approved | JUAN VALENZUELA |