10550 W FONTENELLE WAY 90077
Certificate Information: 10550 W FONTENELLE WAY 90077
- Application / Permit
- 15010-10000-02451
- Plan Check / Job No.
- B15LA09439
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- NEW SECURITY BOOTH WITH ATTACHED ONE CAR GARAGE <<ON 16 PILES/GRADE BEAM/CONCRETE RETAINING WALLS>>
- Permit Issued
- Issued on 3/4/2016
- Issuing Office
- Metro
- Current Status
- Issued on 3/4/2016
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/9/2015 | APPLICANT |
| Green Plans Picked Up | 7/22/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 7/23/2015 | DEAN LEE |
| Corrections Issued | 8/3/2015 | DEAN LEE |
| Quality Review Completed | 8/6/2015 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 8/10/2015 | APPLICANT |
| Applicant returned to address corrections | 10/22/2015 | DEAN LEE |
| Applicant returned to address corrections | 1/4/2016 | DEAN LEE |
| Applicant returned to address corrections | 1/14/2016 | DEAN LEE |
| Plan Check Approved | 3/1/2016 | DEAN LEE |
| Issued | 3/4/2016 | LADBS |
| Permit Expired-Status Void | 8/22/2020 | MATT KELLERMAN |
| Re-Activate Permit | 10/2/2020 | MATT KELLERMAN |
Permit Application Clearance Information
| Permit | Cleared | 9/16/2015 | KARAN PATEL |
| Sewer availability | Cleared | 9/16/2015 | KARAN PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2015 | PAMELA TENEZA |
| Work Adjacent to Public Way | Cleared | 10/14/2015 | DAVID PEREZ |
| BHO/Hillside ordinance | Cleared | 11/13/2015 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 11/13/2015 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 11/13/2015 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 11/13/2015 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 11/13/2015 | RAVIL MANAPOV |
| ZI | Cleared | 12/1/2015 | VINCENT QUITORIANO |
| Green Code | Cleared | 12/4/2015 | MARCUS LEVIAS |
| Distance to fire station | Cleared | 1/21/2016 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 1/21/2016 | ROBERT DUFF |
| Roof/Waste drainage to street | Cleared | 2/29/2016 | SEVAK ISAKHAYAN |
| Stormwater Pollution Mitigatn | Cleared | 2/29/2016 | AMMAR ELTAWIL |
| Excavation more than 5-ft deep | Cleared | 4/5/2016 | CALOSHA APPROVED |
Contact Information
| Architect | Spann, Anthony Paul; Lic. No.: C17602 | 921 DE LA VINA STREET HARRISON DESIGN ASSOCIATES SANTA BARBARA, CA 93101 |
| Contractor | Lucy Development Company; Lic. No.: 913288-B | 16060 VENTURA BLVD 105 ENCINO, CA 91436 |
| Engineer | Liston, Leonard Irvin; Lic. No.: C31902 | 889 PIERCE CT STE 101 THOUSAND OAKS, CA 91360 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 5/25/2016 | Partial Approval | ANTHONY ANDERSON |
| Piling/Pier/Caisson | 6/7/2016 | Partial Approval | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 6/23/2016 | Corrections Issued | ANTHONY ANDERSON |
| Footing/Foundation/Slab | 6/27/2016 | Partial Approval | ANTHONY ANDERSON |
| Excavation/Setback/Form/Re-Bar | 7/27/2016 | Corrections Issued | ANTHONY ANDERSON |
| Excavation/Setback/Form/Re-Bar | 8/3/2016 | Corrections Issued | ANTHONY ANDERSON |
| Excavation/Setback/Form/Re-Bar | 11/17/2016 | Partial Approval | ANTHONY ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2016 | Partial Approval | ANTHONY ANDERSON |
| PLUMBING-Rough | 3/30/2017 | Partial Approval | ANTHONY ANDERSON |
| Special/Order Compliance | 8/12/2017 | Partial Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 1/12/2018 | No Access for Inspection | ANTHONY ANDERSON |
| PLUMBING-Rough | 1/18/2018 | Partial Approval | ANTHONY ANDERSON |
| Interior/Exterior Lathing | 2/13/2018 | Partial Approval | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 4/23/2018 | Partial Approval | ANTHONY ANDERSON |
| ELECTRICAL-Rough | 7/24/2018 | Approved | JONATHAN HOM |
| PLUMBING-Rough | 7/24/2018 | Approved | JONATHAN HOM |
| Insulation | 8/6/2018 | Approved | MATT KELLERMAN |
| Drywall Nailing | 8/13/2018 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 8/13/2018 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 4/13/2019 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 4/20/2019 | Partial Inspection | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 8/12/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 8/14/2020 | Permit Expired-Status Void | MATT KELLERMAN |
| Pre-Inspection | 8/25/2021 | Corrections Issued | MATT KELLERMAN |