7130 W 85TH ST 90045

Certificate Information: 7130 W 85TH ST 90045

Application / Permit
15010-10000-01813
Plan Check / Job No.
B15LA06827
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
A 3-story single family dwelling( Unit C) "Small lot subdivision pursuant to Tentative Tract Map No. AA 2015-700-PMLA .A certificate of occupancy(temporary or final) shall not be issued until after the final map has been recorded .
Permit Issued
Issued on 7/7/2017
Issuing Office
Metro
Current Status
Issued on 7/7/2017
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/15/2015 APPLICANT
Assigned to Plan Check Engineer 6/18/2015 SAI KHUM
Corrections Issued 6/25/2015 SAI KHUM
Quality Review Completed 6/29/2015 CHARLES CHANG
Building Plans Picked Up 6/30/2015 APPLICANT
Green Plans Picked Up 6/30/2015 APPLICANT
Applicant returned to address corrections 6/20/2016 SAI KHUM
Applicant returned to address corrections 8/11/2016 SAI KHUM
Applicant returned to address corrections 8/22/2016 SAI KHUM
Applicant returned to address corrections 9/19/2016 SAI KHUM
Applicant returned to address corrections 11/1/2016 SAI KHUM
Applicant returned to address corrections 6/13/2017 SAI KHUM
Plan Check Approved 6/14/2017 SAI KHUM
Issued 7/7/2017 LADBS

Permit Application Clearance Information

Address approval Cleared 10/31/2016 ROCHELLE DUNGCA
Permit Cleared 10/31/2016 ROCHELLE DUNGCA
Eng Process Fee Ord 176,300 Cleared 11/1/2016 ALFREDO JARA
Sewer availability Cleared 11/1/2016 ALFREDO JARA
Low Impact Development Cleared 3/16/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 3/30/2017 ROCHELLE DUNGCA
Green Code Cleared 3/31/2017 MARCUS LEVIAS
Specific Plan Cleared 3/31/2017 CLIVE GRAWE
Building over 3-story or 36-ft Cleared 4/21/2017 CALOSHA APPROVED
Miscellaneous Cleared 6/1/2017 LUZ RABELO
Frnt yard landscape/Water mgmt Cleared 6/2/2017 NORALI MARTINEZ
Hydrant and Access approval Cleared 6/6/2017 ROBERT DUFF
Tract Map conditions Cleared 6/6/2017 EDBER MACEDO

Contact Information

Architect Zubick, Anthony Philip; Lic. No.: C19924 P O BOX 931810      LOS ANGELES, CA 90093
Contractor Owner-Builder       ,
Engineer Posadas, John Garcia; Lic. No.: C30786 2063 PASEO LUCINDA      SAN DIMAS, CA 91773
Geologist Schick, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/14/2017 Corrections Issued RONALD WEBER
Footing/Foundation/Slab 9/25/2017 Not Ready for Inspection CRAIG DAVIS
Footing/Foundation/Slab 9/28/2017 Approved RONALD WEBER
PLUMBING-Rough 10/6/2017 Partial Approval RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 11/21/2017 Partial Approval RONALD WEBER
Special/Order Compliance 1/11/2018 Approved CRAIG DAVIS
BUILDING-Rough-Frame 4/12/2018 Not Ready for Inspection RONALD WEBER
Green Building Rough 4/12/2018 Not Ready for Inspection RONALD WEBER
Verify Sprinkler Sign Off 4/12/2018 Not Ready for Inspection RONALD WEBER
ELECTRICAL-Rough 4/18/2018 Not Ready for Inspection RONALD WEBER
PLUMBING-Rough 4/18/2018 Not Ready for Inspection RONALD WEBER
Sewer 4/18/2018 Not Ready for Inspection RONALD WEBER
Wood Frame 4/18/2018 Not Ready for Inspection RONALD WEBER
Special/Order Compliance 4/26/2018 Partial Inspection RONALD WEBER
BUILDING-Rough-Frame 5/2/2018 Not Ready for Inspection RONALD WEBER
Floor/Roof Diaphrgm/Shear Wall 6/5/2018 Partial Approval RONALD WEBER
HVAC-Rough 11/29/2018 Partial Inspection RONALD WEBER
PLUMBING-Rough 11/29/2018 Approved RONALD WEBER
Shower Pan 12/5/2018 Approved RONALD WEBER
BUILDING-Rough-Frame 1/11/2019 Not Ready for Inspection RONALD WEBER
Green Building Rough 1/11/2019 Not Ready for Inspection RONALD WEBER
Interior/Exterior Lathing 1/11/2019 Partial Approval RONALD WEBER
Verify Sprinkler Sign Off 1/11/2019 Not Ready for Inspection RONALD WEBER
ELECTRICAL-Rough 3/27/2019 Corrections Issued JUAN VALENZUELA
HVAC-Rough 3/27/2019 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 3/27/2019 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 4/9/2019 Approved JUAN VALENZUELA
HVAC-Rough 4/9/2019 Approved JUAN VALENZUELA
Special/Order Compliance 6/11/2019 Corrections Issued JUAN VALENZUELA
Insulation 10/29/2019 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 2/21/2020 Approved JUAN VALENZUELA
Drywall Nailing 2/21/2020 Approved JUAN VALENZUELA
Green Building Rough 2/21/2020 Approved JUAN VALENZUELA
Underground Mechanical 2/21/2020 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 2/21/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/23/2020 No Access for Inspection JUAN VALENZUELA
Special/Order Compliance 6/15/2020 Approved CRAIG DAVIS
Special/Order Compliance 7/6/2020 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 7/10/2020 Partial Inspection JUAN VALENZUELA
Special/Order Compliance 12/31/2020 Partial Approval JOHNNY MIRANDA
Special/Order Compliance 1/26/2021 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 9/7/2021 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 1/18/2023 Partial Inspection RICHARD STEINBACH
Special/Order Compliance 1/20/2023 Corrections Issued BOBBY KEY
Sewer 5/15/2023 Approved BOBBY KEY
Special/Order Compliance 5/15/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Final 5/23/2023 Corrections Issued BOBBY KEY
HVAC-Final 6/20/2023 Not Ready for Inspection BOBBY KEY
ELECTRICAL-Final 9/13/2023 Approved BOBBY KEY
HVAC-Final 9/13/2023 Approved BOBBY KEY
PLUMBING-Final 9/13/2023 Not Ready for Inspection BOBBY KEY
Gas Test 4/24/2024 Approved JESUS PINEDA
Special/Order Compliance 5/9/2024 Partial Approval BOBBY KEY
PLUMBING-Final 5/21/2024 Approved BOBBY KEY
Final 6/7/2024 Corrections Issued BOBBY KEY
Green Building Final 6/7/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 6/7/2024 Approved BOBBY KEY