9364 W BEVERLYCREST DR 90210
Certificate Information: 9364 W BEVERLYCREST DR 90210
- Application / Permit
- 15010-10000-01384
- Plan Check / Job No.
- B15LA05181
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW CONSTRUCTION OF A 2-STORY WITH BASEMENT SINGLE FAMILY DWELLING WITH 3-CAR ATTACHED GARAGE.
- Permit Issued
- Issued on 6/7/2016
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2015 | APPLICANT |
| Green Plans Picked Up | 4/23/2015 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2015 | ERIC WONG |
| Corrections Issued | 5/19/2015 | ERIC WONG |
| Quality Review Completed | 5/20/2015 | KESETE HAREGOT |
| Building Plans Picked Up | 5/21/2015 | APPLICANT |
| Applicant returned to address corrections | 7/30/2015 | ERIC WONG |
| Applicant returned to address corrections | 9/3/2015 | ERIC WONG |
| Plan Check Approved | 9/10/2015 | ERIC HUANG |
| Plan Check Approved | 3/4/2016 | ERIC HUANG |
| Plan Check Approved | 3/9/2016 | ERIC HUANG |
| Issued | 6/7/2016 | LADBS |
| CofO in Progress | 4/14/2021 | BRAD BESCOS |
| Permit Finaled | 4/15/2021 | DEROLD HAUFF |
| CofO Issued | 4/15/2021 | DEROLD HAUFF |
| Permit Finaled | 4/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2015 | ANGEL SALCEDO |
| BHO/Hillside ordinance | Cleared | 6/29/2015 | ANGEL SALCEDO |
| BHO/Hillside ordinance | Cleared | 6/29/2015 | ANGEL SALCEDO |
| BHO/Hillside ordinance | Cleared | 6/29/2015 | ANGEL SALCEDO |
| BHO/Hillside ordinance | Cleared | 6/29/2015 | ANGEL SALCEDO |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2015 | ANGEL SALCEDO |
| Permit | Cleared | 6/29/2015 | ANGEL SALCEDO |
| Hydrant and Access approval | Cleared | 7/23/2015 | JOHN CONNEALLY |
| Sewer availability | Cleared | 8/11/2015 | AVALYN KAMACHI |
| Low Impact Development | Cleared | 8/20/2015 | VIJAY DESAI |
| Stormwater Pollution Mitigatn | Cleared | 8/20/2015 | VIJAY DESAI |
| Roof/Waste drainage to street | Cleared | 8/21/2015 | TERRY PHAN |
| Green Code | Cleared | 9/4/2015 | RICHARD DOCKUS |
Contact Information
| Architect | Ryder, Eric Otto; Lic. No.: C32173 | 2004 19TH STREET SANTA MONICA, CA 90404 |
| Contractor | Precision Building & Development Inc; Lic. No.: 859758-B | 11628 SANTA MONICA BLVD #204 LOS ANGELES, CA 90025 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/18/2017 | No Access for Inspection | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/19/2017 | Partial Inspection | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 6/14/2017 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 10/13/2017 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 10/16/2017 | Conditional Approval | RONALD COWAN |
| Piling/Pier/Caisson | 10/17/2017 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 10/18/2017 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 12/19/2017 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/27/2017 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 1/24/2018 | Conditional Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 1/25/2018 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 2/5/2018 | Partial Approval | CRAIG VAUGHAN |
| Deputy Reinf. Concrete | 2/9/2018 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 2/20/2018 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 2/26/2018 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 4/19/2018 | Not Ready for Inspection | RONALD COWAN |
| Deputy Drilled-In Anchors | 5/14/2018 | Approved | RONALD COWAN |
| Deputy Reinf. Masonry | 5/15/2018 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 5/21/2018 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 5/22/2018 | Conditional Approval | RAUL BARAJAS |
| Underground Mechanical | 6/6/2018 | Not Ready for Inspection | RONALD COWAN |
| Underground Mechanical | 6/8/2018 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 6/15/2018 | Approved | RONALD COWAN |
| Footing/Foundation/Slab | 6/15/2018 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 7/18/2018 | Approved | RONALD COWAN |
| Deputy Reinf. Concrete | 7/27/2018 | Approved | RONALD COWAN |
| Deputy Shotcrete | 8/22/2018 | Approved | RONALD COWAN |
| Excavation/Setback/Form/Re-Bar | 8/22/2018 | Partial Approval | RONALD COWAN |
| Deputy Reinf. Concrete | 8/23/2018 | Approved | RONALD COWAN |
| Wood Frame | 3/21/2019 | Partial Approval | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2019 | Partial Approval | DANNY TOLENTINO |
| HVAC-Rough | 6/21/2019 | Approved | DANNY TOLENTINO |
| PLUMBING-Rough | 6/21/2019 | Approved | DANNY TOLENTINO |
| ELECTRICAL-Rough | 8/8/2019 | Corrections Issued | RICHARD STEINBACH |
| ELECTRICAL-Rough | 8/23/2019 | Approved | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 9/17/2019 | Not Ready for Inspection | RICHARD STEINBACH |
| Deputy Drilled-In Anchors | 9/19/2019 | Conditional Approval | RICHARD STEINBACH |
| Footing/Foundation/Slab | 10/11/2019 | Partial Approval | RICHARD STEINBACH |
| Masonry Wall/Backfill | 11/25/2019 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 2/13/2020 | Approved | RICHARD STEINBACH |
| Footing/Foundation/Slab | 2/21/2020 | Partial Approval | RICHARD STEINBACH |
| Deputy Drilled-In Anchors | 3/13/2020 | Conditional Approval | RICHARD STEINBACH |
| Insulation | 3/23/2020 | Approved | ROBERT CORNELL |
| Interior/Exterior Lathing | 3/23/2020 | Approved | ROBERT CORNELL |
| Drywall Nailing | 4/14/2020 | Approved | RAUL BARAJAS |
| Green Building Rough | 4/14/2020 | Approved | RAUL BARAJAS |
| Sewer | 5/1/2020 | Partial Inspection | RAUL BARAJAS |
| HVAC-Final | 9/1/2020 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Final | 9/11/2020 | Approved | RUBEN SALAS |
| HVAC-Final | 9/21/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Final | 9/21/2020 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 10/6/2020 | Partial Approval | RAUL BARAJAS |
| PLUMBING-Final | 10/6/2020 | Approved | RAUL BARAJAS |
| Special/Order Compliance | 12/15/2020 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 12/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/24/2020 | Approved | RAUL BARAJAS |
| Green Building Final | 12/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 12/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/24/2020 | SGSOV Not Ready | RAUL BARAJAS |
| Service/Power Release | 12/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 12/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 12/24/2020 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 1/14/2021 | Approved | RAUL BARAJAS |
| Final | 1/14/2021 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 1/14/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Reinforced Concrete Frame | 1/14/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/14/2021 | SGSOV No Gas | RAUL BARAJAS |
| Service/Power Release | 1/14/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Smoke Detectors | 1/14/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 1/14/2021 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 1/29/2021 | Approved | RAUL BARAJAS |
| Final | 1/29/2021 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 1/29/2021 | Approved | RAUL BARAJAS |
| HVAC-Final | 1/29/2021 | Approved | RAUL BARAJAS |
| Service/Power Release | 1/29/2021 | Approved | RAUL BARAJAS |
| Smoke Detectors | 1/29/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Special/Order Compliance | 2/16/2021 | Corrections Issued | BRAD BESCOS |
| Final | 4/14/2021 | OK to Issue CofO | BRAD BESCOS |
| Smoke Detectors | 4/14/2021 | Approved | BRAD BESCOS |